Define the minimum and maximum cycle times, Operation Management

Assignment Help:

An assembly line with 11 tasks is to be balanced. The longest task is 2.7 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 18 minutes. The line will operate for 800 minutes per day.

a. Determine the minimum and maximum cycle times.

b. What range of output is theoretically possible for the line?

c. What is the minimum number of stations needed if the maximum output rate is to be sought?

d. What cycle time will provide an output rate of 200 units per day?


Related Discussions:- Define the minimum and maximum cycle times

Determine that the trade offs of operation system is correct, Determine tha...

Determine that the Trade offs of operations systems is correct You may wish to ponder this trade-offs for a moment and ask the question: is this correct? Consider an organisat

Explain which one minimizes their cost, A swim club is designing a new pool...

A swim club is designing a new pool to replace its old pool. The new pool would need to last for 10 years since the club is planning on relocating after 10 years. A concrete shell

Investment Management Assignment, Prepare an in-depth report recommending t...

Prepare an in-depth report recommending the appropriate investment of AUD$3 million for a five year investment period for a particular investment client. The investment portfolio i

Define ethical responsibilities and social responsibilities, Explain the di...

Explain the difference between ethical responsibilities and social responsibilities of a manager. Please in you own words.

Work measurement, Work Measurement: Work  measurement  goes  hand in  ...

Work Measurement: Work  measurement  goes  hand in  with  method  design. Whereas the method design  are directed towards the study  of the components of a single or multiple

Describe culture and values and ethics, Discuss culture, values, ethics, an...

Discuss culture, values, ethics, and other such elements that lead to differences in social culture; 2) Explain the business and economic implications of differences in culture and

Describe delaying completion of the project, Using the data in Table 13-1, ...

Using the data in Table 13-1, what is the latest possible time that C may be started without delaying completion of the project? Table 13-1 The following represents a project with

Search a financial analysis report of coca-cola, Where can I find a financi...

Where can I find a financial analysis report of coca-cola for the past 5 years. I stress full financial analysis for the past 5years.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd