Define the minimum and maximum cycle times, Operation Management

Assignment Help:

An assembly line with 11 tasks is to be balanced. The longest task is 2.7 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 18 minutes. The line will operate for 800 minutes per day.

a. Determine the minimum and maximum cycle times.

b. What range of output is theoretically possible for the line?

c. What is the minimum number of stations needed if the maximum output rate is to be sought?

d. What cycle time will provide an output rate of 200 units per day?


Related Discussions:- Define the minimum and maximum cycle times

Group layout, Can I know what is group layout

Can I know what is group layout

Explain project management profession, Microsoft Project, identify the reso...

Microsoft Project, identify the resource that caught your interest and estimate its usefulness to the project management profession.

Production control, Production Control Meaning and Definition ...

Production Control Meaning and Definition Production control involves implementation of production plans or schedules by coordinating different activities. It seeks to

Compute panera breads strategy and its effectiveness, Evaluate Panera Bread...

Evaluate Panera Breads strategy and its effectiveness with executing the strategy within the competitive fast-casual restaurant marketplace. Discuss the pitfalls to this strategy a

Explain how the government can implement information plan, Propose a plan f...

Propose a plan for how the government can implement information security plans to ensure its critical information is safe and protect.

Two handed process chart and multiple activity charts, Two Handed Process C...

Two Handed Process Chart and Multiple Activity Charts Two-handed process chart  For fixed-position manual processes such as the assembly of small devices, this type of ch

Explain how many cords of wood would he have to split, The owner of Firewoo...

The owner of Firewood To Go is considering buying a hydraulic wood splitter which sells for $50,000. He figures it will cost an additional $100 per cord to purchase and split wood

Explain individual employees and improve cooperation, How can a pay for per...

How can a pay for performance system increase motivation of individual employees and improve cooperation?

Dipict a diagram of the process using the format, Analyzing a Taco Bell Res...

Analyzing a Taco Bell Restaurant ch7 p. 240 13th edition 1 Draw a diagram of the process using the format in Exhibit 7.3 2 Consider a base case where a customer arrives every 40 se

Explain product-by-value analysis, Prepare a product-by-value analysis for ...

Prepare a product-by-value analysis for the following products, and given the position in its life cycle, identify the issues likely to confront the operations manager, and his or

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd