An assembly line with 11 tasks is to be balanced. The longest task is 2.7 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 18 minutes. The line will operate for 800 minutes per day.

a. Determine the minimum and maximum cycle times.

b. What range of output is theoretically possible for the line?

c. What is the minimum number of stations needed if the maximum output rate is to be sought?

d. What cycle time will provide an output rate of 200 units per day?


Related Discussions:- Define the minimum and maximum cycle times

Explain cost-reimbursement contracts for the government, Find an example of...

Find an example of a project in which one of these two types was used in a real federal contract. These two types refers to contrast fixed-price and cost-reimbursement contracts fo

Describe scope process, Which of the following items best depicts the Defin...

Which of the following items best depicts the Define Scope process? A. It begins by determining product scope / deliverables and culminates in a project scope statement. B. It be

Describe find the shortest route from node 1 to node 6, Find the shortest r...

Find the shortest route from Node 1 to Node 6. From Node To Node Distance 1 2 150 1 3 200 2 3 100 2 4 200 2 5 50 3 4 350 3 5 300 4 6 100 5 6 100 Which Answer is it? 300 450 550 650

What is cutting stock problem, Consider the cutting stock problem that aris...

Consider the cutting stock problem that arises when a company manufactures sheets of standard width 100 and has commitments to supply 40 sections of width 40, 60 sections of width

Gaining Trust with Culture Disparties, Ask quFor this assignment, you will ...

Ask quFor this assignment, you will apply critical thinking to what you have learned up to this point in this course regarding the successes and failures of the U.S. health care sy

Explain the processing times for the five job, Suppose SPT rule is being us...

Suppose SPT rule is being used in a "dynamic" scheduling problem. There are five jobs A,B,C,D, and E ready to be processed at the present time. The processing times for the five jo

Production efficiencies and reducing unit costs, A manufacturer concerned m...

A manufacturer concerned mainly with production efficiencies and reducing unit costs is known as Production oriented.

Explain strategic and budgetary decisions, Identify and discuss factors tha...

Identify and discuss factors that can increase the size and complexity of the information system structure (beyond those discussed in the text). •Make at least three recommendation

Descibe the stages of contract formation, Maria, who lives in Seattle, sent...

Maria, who lives in Seattle, sent Koji a letter via first class mail, stating, "Koji, I think your 2003 Ford SUV is worth $20,000. I will give you $20,000 cash for it." Koji receiv

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd