Define the critical path, Operation Management

Assignment Help:

The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede:

Activity Duration (weeks) Precedes

A (start) 1 B, C

B 1 E

C 4 F

E 2 F

F(end) 2 %u2014

a) Draw an AON diagram of the project, including activity durations.

b) Define the critical path, listing all critical activities in chronological order.

c) What is the project duration (in weeks)?

d) What is the slack (in weeks) associated with any and all noncritical paths through the project?

 


Related Discussions:- Define the critical path

The Strategic Significance of Design, What is the strategic significance of...

What is the strategic significance of Design in operations management?

Explain production standards place managements, State how production standa...

State how production standards place managements and unions at odds against each other. Why do some unions prefer the right to strike in this matter while others prefer arbitration

Explain either party since the contract has been illegal, When a contract i...

When a contract is drawn up that becomes void due to illegality, do you believe that it involves the commission of a crime? Has a crime been committed by either party since the con

Job Design, compare and contrast job design with related or dependent proce...

compare and contrast job design with related or dependent processes

Explain which style did you find most effective, Think back to teachers you...

Think back to teachers you have had, and identify one each who fits a supportive style, directive style, participative style, and achievement-oriented style according to the path-g

Explain how can healthcare service providers avoid claims, Part I: Avoid cl...

Part I: Avoid claims rejections A payer may delay or deny payment because of inaccurate or missing information in a submitted claim. Many contracts require payment within a spec

What is an operation setback chart, An operation setback chart _____. is...

An operation setback chart _____. is based on lead times that typically include move and queue times and indicates a schedule for when to make a part. is a schedule for when

Scope, what are the scope of operation research

what are the scope of operation research

Rationalize your compensation as well benefits package, Rationalize your co...

Rationalize your compensation and benefits package. Be sure to indicate the research and considerations that went into the design of the compensation and benefits package.

What is a a simple moving average, A simple moving average_____. (may be mo...

A simple moving average_____. (may be more than 1 answer) A) lags a trend B) is best to use when product demand is unstable. C) cannot be used to filter out random fluctua

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd