1) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.

Related Discussions:- data warehouse

How many precision resistors requires a weighted resistor, A weighted resis...

A weighted resistor digital to analog converter using N bits requires a total of ? Ans. Digital to analog converter, a weighted resistor using N bits needs a total of N precisi

OS, why we say OS is a resource allocator and control program

why we say OS is a resource allocator and control program

What is fan-out, What is fan-out? Estimate the average count of every "...

What is fan-out? Estimate the average count of every "many" association encountered with the path. Multiply the individual fan-outs who obtain the fan-out of the whole path, wh

State the various security tools, State the various Security Tools Sec...

State the various Security Tools Securing an Intranet is not a simple task. Just as articles in a house are protected by use of various types of security systems such as lock

Why do we call motherboard a motherboard, Motherboard is called as motherbo...

Motherboard is called as motherboard because in the world all borned creature is directly attached to her mother & after it all the relations makes due to her mother so in the simi

# real life business subsystem, Is production, marketing, personal, materia...

Is production, marketing, personal, material, finance are the real life business subsystems? if yes, then how?

Which rule is used for the expansion of nested macro calls, The expansion ...

The expansion of nested macro calls done by using of? Ans. LIFO rule is used for the expansion of nested macro calls.

Define the resolution of externally defined symbols, Resolution of external...

Resolution of externally defined symbols is performed by Ans. By Linker resolution of externally defined symbols is performed.

Modelsim, design a basic computer

design a basic computer

Artificial neural networks, Artificial Neural Networks: However imagin...

Artificial Neural Networks: However imagine now in this example as the inputs to our function were arrays of pixels and there actually taken from photographs of vehicles such

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd