Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Define the types of transmission in ultrasonic system, Define the Types of ...

Define the Types of Transmission in Ultrasonic System? Types of Transmission Three Types of Transmission through the testing element is possible, namely: - Direct transmi

Unsymmetrical bending, An 8 kN.m moment is applied at the end of a block fi...

An 8 kN.m moment is applied at the end of a block fixed into the ground as illustrated in thefigure below. The moment vector (double arrow head representation) acts in line with th

Illustrate the concept of load balancing, Concept of load balancing In ...

Concept of load balancing In above cases of concentric and eccentric pre-stressing, straight tendon profiles (or tendon shapes) along the beam span have been considered. If a t

Steel structure, what do mean by outstand element of compression flange, in...

what do mean by outstand element of compression flange, internal element of compression flange and web general

#title beam design, how to calculate loads acting on a simple supported bea...

how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#

Material engineering assignment, select three materials metal and non meala...

select three materials metal and non mealat at least one of the selected materials shold change its property

#titlecivil war.., how can you know that the civil war real.

how can you know that the civil war real.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd