Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

State the method of pre- tensioning, State the method of Pre- Tensioning ...

State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr

How to calculate the combined stresses, Compute the stresses at top and bot...

Compute the stresses at top and bottom fibers in a simply supported pre-stressed concrete beam with a rectangular cross section, 250 mm wide and 450 mm deep, as shown in Figure, at

Surveying, describe two fundamentals purposes of surveying.

describe two fundamentals purposes of surveying.

Bricks, charactor of fourth class brick

charactor of fourth class brick

Purposes of subdivision of tunnelling faces, Purposes of subdivision of tun...

Purposes of subdivision of tunnelling faces in Sprayed Concrete Linings (SCL) method In using sprayed concrete lining methods for lining a large tunnel in soft ground, tunnelli

Define the marine growth - underwater inspection of bridges, Define the Mar...

Define the Marine Growth - Underwater inspection of bridges? Bridges on many inland waterways are relatively clean and free of marine growth. However, there is likelihood of ma

Consultant , how to convert a varying distributed load to a uniformly distr...

how to convert a varying distributed load to a uniformly distributed load

Define the transmissivity and reynold number, Define the Transmissivity and...

Define the Transmissivity and Reynold Number TRANSMISSIVITY: (T) A measurement of the rate of groundwater movement through different soil and rock materials. For both confined

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Construct the correct network for project, A project requires that activiti...

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd