Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Spun pipes, what is flush joint and confined joint in rcc spun pipes?

what is flush joint and confined joint in rcc spun pipes?

Define the influence line-beam shear, Define the Influence line-beam shear?...

Define the Influence line-beam shear?   1.  Replace point of interest with a link element of nominal length.  If the point of interest is a reaction, place a hinge at that poin

Write short notes on impact test, Q. Write short notes on Impact Test? ...

Q. Write short notes on Impact Test? Impact test for ballast shall be carried out using Impact testing machine. The test sample shall be prepared out of ballast so as to con

Castellated beams – reasons for its widespread usage, Q. Explain about Cast...

Q. Explain about Castellated beams? Castellated beams refer to the type of beams which involve expanding a standard rolled steel section in such a way that a predetermined patt

Diffrence between hudsons and van der meer formula, Q. Diffrence between Hu...

Q. Diffrence between Hudsons and Van der Meer formula? Hudson's formula is usually adopted in preliminary design to attain rough initial estimate of rock size. This formula is

Define the marine growth - underwater inspection of bridges, Define the Mar...

Define the Marine Growth - Underwater inspection of bridges? Bridges on many inland waterways are relatively clean and free of marine growth. However, there is likelihood of ma

Determine the thickness of flexible pavement layer, Determine the thickness...

Determine the thickness of flexible pavement layer 2 given the following:  FACTS: Total Structural Number required = 7.0 Total number of layers = 2 Layer 1 consists of

Explain frame members effective lengths, Explain Frame Members Effective Le...

Explain Frame Members Effective Lengths a. Effective length is a product of an effective length factor (k) and the actual length of the column. b. k depends on the rel

Calculate the final volume of the compacted soil, 1. 130,000-yd 3 of banke...

1. 130,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%.  The final volume of the compacted

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd