Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Calculate the Total Area (acre) for Lot A 30-ft wide parabolic shaped stream divides the property as shown. The total area (acre) for Lot 6 is most nearly: Solution:
what are the types of foundations
what are the appropriate methods of concreting
Q. Explain about Castellated beams? Castellated beams refer to the type of beams which involve expanding a standard rolled steel section in such a way that a predetermined patt
write a short on vector representation of force(addition and substraction )
Define Steel substructure - underwater inspection of bridge? Steel is used as a structural material and as external protective cladding on concrete foundation elements. Steel f
Retaining Walls: A wall used to retain some material on one or both sides of it can be termed as retaining wall. Commonly, it is used to retain soil at two different levels on
define design period
Shrinkage of concrete in prestressed members The shrinkage of concrete in prestressed members results in a shortening of ensioned wires and hence contributes to the loss of st
Uses of Lime Uses of lime in civil works are following : For making mortar for masonry works and plastering For white washing. For soil stabilization. To produc
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd