Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Determine the stresses set up in the brass, Determine the stresses set up i...

Determine the stresses set up in the brass: A compound bar is constructed from three bars 50 mm wide by 12 mm thick fastened together to form a bar 50 mm wide by 36 mm thick.

Explain bridge selection criteria - underwater inspection, Explain the Brid...

Explain the Bridge Selection Criteria - Underwater inspection? Various factors influence the bridge selection criteria. As a minimum, all structures must receive routine underw

Define the cost of shock transmission unit, Define the Cost of shock transm...

Define the Cost of shock transmission unit? There is a keen competition among the few STU manufacturers. For the second Bassein Creek Bridge, the average cost of two STUs of ca

Truss, modified pratt truss with detailing in 3D

modified pratt truss with detailing in 3D

What is partial prestressing, What is Partial Prestressing It is a form...

What is Partial Prestressing It is a form of prestressing in which tensile stresses are permitted, upto a limited extent, in concrete under working loads. As the permitted tens

Civil, vcdjvoidj pirioi oique

vcdjvoidj pirioi oique

Purpose of using capping layers in pavement construction, Q. Purpose of usi...

Q. Purpose of using capping layers in pavement construction? When California Bearing Ratio of subgrade is checked to be below a specific percentage (for example 5%), a capping

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd