Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Calculate the most probable value, The most probable value of the following...

The most probable value of the following observations on the same angle (35º 17' 42" ; 35º 17' 38" ; 35º 18' 00" ; 35º 17'; 22"; 35º 17' 42");  is most nearly:   35º 17' 40.8

Water quality analysis, Water quality analysis: This water quality ana...

Water quality analysis: This water quality analysis presents an overview of physical characteristics of water, chemical substances that are normally present in water and vario

Define the reservoirs - hydraulic system, Define the Reservoirs - Hydraulic...

Define the Reservoirs - Hydraulic System Typically designed for multiple functions - clean water supply, creating recreational opportunities and flood protection. Reservoirs ar

Cutbacks and emulsions, Cutbacks And Emulsions: Cutbacks A cu...

Cutbacks And Emulsions: Cutbacks A cutback is a bitumen whose viscosity has been reduced by adding a diluent such as naphtha or kerosene. The use of cut-back is not f

Determine the normal and shear stress elements, Determine the normal and sh...

Determine the normal and shear stress elements: The state of stress at a point is given through the stress components σ x = 70 MPa, σ y = 10 MPa, and τ xy = - 40 MPa. Using

Explain condition rating number, Q. Explain Condition Rating Number? 1....

Q. Explain Condition Rating Number? 1. A Condition which warrants rebuilding / re-habilitation immediately. 2. A Condition which requires rebuilding / re-habilitation on pro

Geotechnical, send any civil engineering related questions . i will write t...

send any civil engineering related questions . i will write the answers , please tell us the process .

State the method of pre- tensioning, State the method of Pre- Tensioning ...

State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr

Embankment construction, Embankment Construction: Selection of Soil...

Embankment Construction: Selection of Soil Soil is the material used for embankment construction, though other materials like rock and fly-ash are also used in specia

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd