Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Concrete, Determine the quantity of materials required per batch and probab...

Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows

Steel truss, size of steel truss for span of 5m

size of steel truss for span of 5m

Soil plug in marine piling system of steel tubular pile, Soil plug in marin...

Soil plug in marine piling system of steel tubular pile with reinforced concrete infill At the time of initial driving process, open-ended steel piles are driven through the s

Surveying, what is compass survey and and its method

what is compass survey and and its method

Define abrasion of steel structures - inspection of bridge, Define Abrasion...

Define Abrasion of steel structures? Abrasion of steel structures can generally be recognised by a worn, smooth, polished appearance of the surface.  Abrasion is caused by cont

Define the shrinkage limit and shrinkage ratio, The oven-dry weight of a pa...

The oven-dry weight of a pat of clay is 1.17 N and the weight of mercury displaced by it is 0.855 N. suppose the specific gravity of solids as 2.71, verify the shrinkage limit and

Geotechnical engg., friction circle method of stability of slope

friction circle method of stability of slope

Distomat, short note of distomat

short note of distomat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd