Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

What is the design mix concrete, What is the Design Mix concrete Determ...

What is the Design Mix concrete Determination of  the proportions of  cement, aggregates and water to  achieve the required strengths in concrete is made by designing  the  con

Piers and piles, what is the difference between piers and piles?

what is the difference between piers and piles?

Explain the term -tendon splices, Tendon splices Tendon splices are us...

Tendon splices Tendon splices are used to join tendons when continuous prestressed concrete , members require long tendons to achieve continuity. Several types of tendon splic

Determine the load which a square footing, Two load tests were performed at...

Two load tests were performed at a site-one with a 50 cm square plate and the other with a 75 cm square plate. For a settlement of 15 mm, the loads were recorded as 50 kN and 90 kN

Local vehicle parapet strong enough to contain vehicles, Q. Local vehicle p...

Q. Local vehicle parapet strong enough to contain vehicles? Majority of local parapets are 1.1m high in addition they are designed to resist impact from a 1.5ton car moving at

Enumerate the term - superposing the stress variations, Enumerate the term ...

Enumerate the term - superposing the stress variations If the case of concentric pre-stressing is considered, we can appreciate that stress at any section of the beam is compr

Critical-depth relationship, If y1 and y2 are alternate depths of a rectang...

If y1 and y2 are alternate depths of a rectangular channel show that Yc³ =2y1²y2²/(y1+y2) Also specific energy E = y1²+y1y2+y2²/(y1+y2)

#soil survey., Explian obstacles in chaining but not ranging.

Explian obstacles in chaining but not ranging.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd