Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Correction for construction period, You are aware that construction of any ...

You are aware that construction of any type of structure takes sometime. Pressure due to the building will be applied gradually and not instantaneously. Excavation for the construc

Corrosion, How is corrosion perverted...?

How is corrosion perverted...?

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

Geology class, I want to get answer of each questions that I Have in a sep...

I want to get answer of each questions that I Have in a separate paragraphs, and the information should be from sources so please fro each question that you answer write after it t

Usage of double air valves and single air valves, Question In designig ...

Question In designig of watermains, how to decide usage of double air valves and single air valves ? Answer Single air control device let squeezing air out of p

Whole barings, Ask question #Minexaple of wholeiwhole baring 100 words acce...

Ask question #Minexaple of wholeiwhole baring 100 words accepted#

Rectilinear motion, A train starts from rest as A and accelerates at 1,7m/...

A train starts from rest as A and accelerates at 1,7m/s2 to full speed at which it maintains until the brakes gives it a deceleration of 1,7m/s2 to stop at B. AB=1,6km. determine

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd