Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Write definition of afflux and skew bridge, Write definition of the followi...

Write definition of the following - (i) Afflux. ( ii ) Free Board. ( iii ) Clearance. ( iv ) Via duct. ( v ) Skew Bridge ( vi ) Cause Way. ( vii ) Clear Span. ( v

Survey, underground installations

underground installations

Compute the maximum allowable concentrated live load, Given for the section...

Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac

Vitrification, what is this process?whats its procedure?need some case stud...

what is this process?whats its procedure?need some case studies

Determine the water-cement ratio, A concrete batch plant provided the Desig...

A concrete batch plant provided the Design Strength for the engineer's mix design to match the project's specification requirement for a 4000 psi Tremie pump mix.  The Water-cement

Distomat, applications of distomat in briefly

applications of distomat in briefly

Paint, painting wood work

painting wood work

Design nominal reinforcement to piles, Question Is it true that there i...

Question Is it true that there is no essential to design nominal reinforcement to piles. Answer In BS8110 and BS5400 Pt.4, they need provision of nominal reinforce

Introduction to engineering mechanics, Deternim the angle A for which the m...

Deternim the angle A for which the moment of the 500N force is maximum about a point o. also find the maximum momentum

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd