Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Explain the purpose of embedding puddle flange, Purpose of embedding puddle...

Purpose of embedding puddle flange inside the walls of closed valve chambers When valves are closed to stop water flow in a pipeline, a thrust is produced along the direction o

Define the pre-tensioned concrete construction, Define the pre-tensioned co...

Define the pre-tensioned concrete construction We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time

English, Features of literary writing

Features of literary writing

Determine the example of tendon splices, Determine the example of tendon s...

Determine the example of tendon splices Following are some examples of  tendon splices. (a) Torpedo splice (b) Clamp splice (c)  Screw connectors

Design nominal reinforcement to piles, Question Is it true that there i...

Question Is it true that there is no essential to design nominal reinforcement to piles. Answer In BS8110 and BS5400 Pt.4, they need provision of nominal reinforce

FLAMISH BOND, TH ADVANTAGES OF FLAMISH BOND

TH ADVANTAGES OF FLAMISH BOND

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd