Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Explain the underwater problems and material defects, Explain the Underwate...

Explain the Underwater Problems and Material Defects? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as

Survey, explain ranging and reciprocal ranging

explain ranging and reciprocal ranging

Geotechnical Design, I need this to be done perfectly . It is a civil engin...

I need this to be done perfectly . It is a civil engineering assignment. Please let me know if you can solve this perfectly within no more than 40 hours. Thanks.

How can designer cater for stability of minor slips, Question Soil nail...

Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi

Earth Pressure Theories.., While calculating Active Earth Pressure, do Colo...

While calculating Active Earth Pressure, do Coloumb''s Theory and Rehbann''s theory yield same results? I''ve tried and didn''t get the same results. Where might be the mistake?

Road maintenance, find the details of road maintenance in our project work

find the details of road maintenance in our project work

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Radial flow pumps for small flows and high heads, Radial flow pumps for sma...

Radial flow pumps for small flows and high heads In radial flow pumps, a diffuser/volute is generally designed at it outlet to convert the kinetic energy obtained during the pu

Reason of skin reinforcement for deep beams, Question What is reason of sk...

Question What is reason of skin reinforcement for deep beams ? Answer In BS8110, it declares that secondary reinforcement have to be provided for beams greater than 750mm deep

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd