Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Fore bearing, find out the interior angleS with diagrame LINE AB, BC, CD, D...

find out the interior angleS with diagrame LINE AB, BC, CD, DE, EA Fore bearing 60''30" , 122'' , 46'' , 205''30" , 300''

State the short term effects of concrete, State the Short Term Effects of c...

State the Short Term Effects of concrete These are various types of effects produced, nearly instantaneously, due to the application of external loads on structures. An example

Key distinction in arranging pumps in series, Question What is key dist...

Question What is key distinction in arranging pumps in series and in parallel? Answer For same pumps with similar functions, if pumps arranged in series, total head

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Biodiversity, actual meaning of it? Is it a unit to measure the functions o...

actual meaning of it? Is it a unit to measure the functions of enviroment?

Aggregate crushing test, Aggregate Crushing Test: In which the layer o...

Aggregate Crushing Test: In which the layer of aggregates in a cylindrical measure is subjected to a compressive load of 40 T, and the per cent fines generated are determined,

Curves, procedure on conducting curves in field

procedure on conducting curves in field

Explain frame members effective lengths, Explain Frame Members Effective Le...

Explain Frame Members Effective Lengths a. Effective length is a product of an effective length factor (k) and the actual length of the column. b. k depends on the rel

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd