Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Determine the shearing resistance of sand, In a drained triaxial compressio...

In a drained triaxial compression test, a saturated specimen of cohesionless sand fails at a deviator stress of 450 kN/m 2 when the cell pressure was 135 kN/m 2 . Search the ef

Yugty, #quesjjhjhhjtion..

#quesjjhjhhjtion..

Resultant pull, two locomotive moving on opposite bank of a canal can pull ...

two locomotive moving on opposite bank of a canal can pull a vessal parallel to the banks by the means of two rope.the force in the ropes are 20kN and 24kN while the total angle be

Backward and forward curved vanes in pumps, Backward curved vanes vs. forwa...

Backward curved vanes vs. forward curved vanes in pumps  Power of a pump is related to discharge as follows: Power = k 1 Q + (k 2 Q 2 / tan A) Where K 1 and K 2 are

Lorentz transfarmation, explain the concept of time dilation on the basis ...

explain the concept of time dilation on the basis of lorentz transfarmation equations

System analysis and management techiniques, Question 2: A software company ...

Question 2: A software company is considering translating its program into French. Each unit of the program sells for $50 and incurs a variable cost of $10 to produce. Currently, t

Determine the in-situ dry unit weight, Q. The following observations were r...

Q. The following observations were recorded in a Field density determination by sand-replacement method: Volume of Calibrating can = 1000 cm3 Weight of empty can = 10 N We

Write briefly for trolley permits, Q. Write briefly for Trolley Permits? ...

Q. Write briefly for Trolley Permits? It is the permit given to the Moter Trolley / Push Trolley, Cycle / Moped Trolley. It is essential to have Trolley Permit before taking t

Explain civil fe hydraulics and hydrologic systems, Explain Civil Fe Hydrau...

Explain Civil Fe Hydraulics and Hydrologic Systems When spills occur at grade on soils in areas where unconfined aquifers are present, remediation procedures to remove the poll

What is chamfering of rail, Q. What is Chamfering of rail? Chamfering o...

Q. What is Chamfering of rail? Chamfering of rail holes has been done for the life of rail hole is increased and chances of the rail hole developing any crack is eliminated.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd