Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Common defects - bituminous roads: Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt. If an overlay is to be laid on a cracke
Question What is major importance of air void content in bituminous pavements? Answer Air void content of bituminous materials is important control parameter for quali
Q. Explain in details the various operations involved in Through Packing - conventional Maintenance by beater packing. Explain the various operations as per the Permanent Way
Q. Illustrate Layout of corrugated beam barriers? Layout of corrugated beam barriers is that the beams are corrugated in the longitudinal direction so as to it provides higher
Describe the different types of Ant proof courses
Compute Interior or Intersection Angle for the following circular curve: Answer- I = 180° - 60° - 60°= 60
Q. What do you mean by Base fixity? Base fixity When structures such as portal frames are associated to the base foundation, engineers have to determine the degree of fix
fixed beam processer
What is WBM road. How it is constructed?
A flitched beam consists of a wooden joist 150 mm wide and 300 mm deep strengthened by steel plates 12 mm thick and 300 mm deep one on either side of the joist. If the maximum st
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd