Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Write short note on skv process of thermit welding, Q. Write short note on...

Q. Write short note on SKV  process of thermit welding? This term is used for welding by Alumino thermic process with short preheat time. The time required for preheat with pet

Cement testing, explain the importance of following standard procedure

explain the importance of following standard procedure

Show the functions of sleepers in railway, Q. Show the Functions of sleeper...

Q. Show the Functions of sleepers in railway? Functions of sleepers in railway works are as below:  (i)  The primary function of a sleeper is to grip the rail to gauge and t

Bridge abutment be placed under an embankment, Question It should be necess...

Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with dive

Determine the weight of solids mixed in the suspension, In a hydrometer ana...

In a hydrometer analysis, the corrected hydrometer reading in a 1000 ml uniform soil suspension at the start of sedimentation was 28. After a lapse of 30 minutes, the corrected hyd

Scale., how many scale are there and what are they use

how many scale are there and what are they use

Fly levelling, what is fly levelling? when it is carried out ?

what is fly levelling? when it is carried out ?

How to set location of the bridge, Q. How to set Location of the bridge? ...

Q. How to set Location of the bridge? A bridge is normally located where the river section has minimum width so that the structure becomes shorter and economical. As far as pos

Drawing, how to draw an elipse

how to draw an elipse

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd