Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Bridge engineering, How to calculate economic span of ss bridge

How to calculate economic span of ss bridge

Mechanics, in what condition curve s-t curve is concave and convex

in what condition curve s-t curve is concave and convex

Roofs, Dimensions of trusses

Dimensions of trusses

Bearing, convert the following whole circle bearing to QBs... WCB of AB=45 ...

convert the following whole circle bearing to QBs... WCB of AB=45 degree and 30 mintus

Maintenance of gravel roads, Maintenance of Gravel Roads: The mainten...

Maintenance of Gravel Roads: The maintenance consists of : filling up of potholes/depressions with fresh gravel and compacting after light sprinkling with water. g

Define the meaning of circular prestressing, Define the meaning of circular...

Define the meaning of circular prestressing In circular prestressing, tendon wires are wrapped under tension over the concrete pipes which are pre-cast. The tension in the ten

Define the net positive suction head, Define the Net Positive Suction Head ...

Define the Net Positive Suction Head All values in the equations are in units of feet.  Note: Only use values related to the suction side of the pump.   NPSHR = Net Posi

Railway drawings, section of railway tracks in india ,all dimensions in met...

section of railway tracks in india ,all dimensions in meters

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd