Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Landslides - road under special conditions, Landslides: Landslides ar...

Landslides: Landslides are common in the Himalayan hill roads. The main causes contributing to landslides are: (a) Removal of lateral support at the bottom of a hill due t

Explain the principles involved in successful stabilisation, Normal 0 ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Fluid mechanics , i have three civil engineering fluid mechanics. 1 manomet...

i have three civil engineering fluid mechanics. 1 manometer problem 2 estimate the discharge for a channel 3 pipe system - direction of flow in line and what the value of flow in l

Determine the percentage of sand, A certain soil has 99% by weight finer th...

A certain soil has 99% by weight finer than 1 mm, 80% finer than 0.1 mm, 25% finer than 0.01 mm, 8% finer than 0.001 mm. Draw the grain-size distribution curve and determine the pe

Applied physics, Write the principle of reversibility of light.

Write the principle of reversibility of light.

Determine the load which a square footing, Two load tests were performed at...

Two load tests were performed at a site-one with a 50 cm square plate and the other with a 75 cm square plate. For a settlement of 15 mm, the loads were recorded as 50 kN and 90 kN

Define the in-depth inspections for bridge, Define the In-depth inspections...

Define the In-depth inspections for Bridge? In-depth inspection is a detailed inspection of one or more members below the water level to detect any deficiencies not readily app

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd