Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Settlement due to reduction in volume of soil, Q. Settlement due to Reducti...

Q. Settlement due to Reduction in Volume of Soil? The weight of the structure causes reduction in volume of soil due to expulsion of pore water from the voids. This reduces the

Road materials, Road Materials Earthwork and pavements constitute a si...

Road Materials Earthwork and pavements constitute a significant part of the cost of a road. Hence it is desirable that thorough investigations be done about the availability o

Functions and desirable characteristics of pavements, Functions and Desirab...

Functions and Desirable Characteristics of Pavements Function of Pavement A pavement is that part of a road on which vehicles travel. The pavement has the following f

Design volume of the aeration basin - sewer construction, Design volume of ...

Design volume of the aeration basin - sewer construction: Problem: What is the design volume of the aeration basin? Solution Assuming that 30% of the plant influe

Define npdes sampling requirements, Define NPDES Sampling Requirements? ...

Define NPDES Sampling Requirements? The sampling needs under NPDES are given at 40 CFR Part 122, as part of the needs for applying for an NPDES discharge allow. The needs are b

Moment redistribution, how to draw the shear diagram after redistribution o...

how to draw the shear diagram after redistribution of moments

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Engineering indicators in case of multi speed restriction, Multi Speed Rest...

Multi Speed Restriction (i.e. existence of two or more than two speed restrictions in continuation) When work of deep screening or sleeper renewal is in progress, there is situ

Reasons of ground heaving during pipe-jacking, Reasons of ground heaving du...

Reasons of ground heaving during pipe-jacking It is commonly recognized that ground settlement is one of the significant concern in pipe jacking operation. Though engineer mus

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd