Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Light-weight Aggregate Prestressed Concrete The use of light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of light-
how do i Setting up The total station theodolite?
Hi Sir I have a graduation project part (A) in this semester. I have chosen topic (Analysis and design of Swimming Pool). I got this project ready from friend so I want Presented
why the force is resolved
Absolute pressure is measured from a vacuum (0 PSI) and atmospheric pressure is14.7PSIa or 14.7 PSI above a vacuum 1PSI on a tire pressure gauge is known as 1PSIg = 15.7PSIa 10PSIg
what is the errors faced in leveling servey
Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440. The average crew-hour cost is $15,879 for this
whatis difference between premix asphalt carpeting and asphalt concrete pavement
Pavement of evaluation
advantages and disadvantages
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd