Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
How to prove varignon theorem in easiest way
Common defects - bituminous roads: Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt. If an overlay is to be laid on a cracke
Tests on Limestones Practical tests are made on lime stones to decide their suitability is following: i. Physical tests ii. Heat test iii.
how to find degree of kinematic indeterminacy
Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by
how to calculate the carbon intensity (gC/MJ) for gasoline ( C7H16 ) , we have the Energy Density = 32.2 MJ/L Fluid Density = 0.727 g/mL
Question What is main mechanism of formation of soil plugs in marine driven steel piles with reinforced concrete infill? Answer Throughout initial driving process, ope
Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo
Define Emerging Trends in Bearings? New innovations have taken place in the area of bridge bearings, notable among them are: (1) Shock Transmission Unit (STU) or Lock Up Dev
Poisson distribution function: Let X I , X 2 , ..., X,& b e n independently and identically distributed random variables each having the same cdf F ( x ). What is the pdf of t
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd