Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Question Throughout concreting of diaphragm walls , three tremie pipes are used in single time. But, only one concrete truck is obtainable. How have to concreting works been a
Functions of different reinforcement in a typical pile cap Loads from columns transferring to pile cap persuade tensile forces at the bottom of cap. For example, by using trus
Explain the Inventory inspections - Inspection of Bridge? These inspections are normally performed following new construction, modifications, or repair to establish as-built or
kaltile joint
Ask question #MinThe maximum instantaneous extension, produced by an unknown falling weight through a height of 4 cm in a vertical bar of length 3 m and of cross sectional area 5 c
whatiscreepofmetal&typesdescribe
Question What will functions of water stops in joints of box culverts and drainage channels ? Answer Principal function of water stops is to stop liquids, water-borne materials
how to compute the compound elements particularly outstanding element of compression flange if 2-ismb300 are placed side by side
For IRC Class AA loading in existing industrial areas, what is load (kN/m) has to applied base don the wheel loads. especially raft foundation & roads are at same level.
Given: beam deminsions: flange width=22" FLANGE THICKNESS=7" WEB WIDTH=7" SECTION HEIGHT=40" f'c=5000psi f'ci=3500psi fpu=270ksi Ap=eighteen 1/2" diam strands superim
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd