Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

AAA, Ask question #MiAAAAnimum 100 wordAs accepted#

Ask question #MiAAAAnimum 100 wordAs accepted#

Primavera, hi contactme 9902142308

hi contactme 9902142308

Pavement drainage, Pavement Drainage: Water enters the pavement layer...

Pavement Drainage: Water enters the pavement layers through cracks, joints and open spaces in the pavement surface. The water reaches the soil sub-grade on which the pavement

Gg, ggggggggggg

ggggggggggg

Explain the term - non-bonded prestressed concrete, Explain the term - Non-...

Explain the term - Non-bonded Prestressed Concrete It is a method of construction in which the tendons are not bonded to the concrete. Ducts, housing the tendons, are not grout

Role of rebate in typical construction joint, Question What is role of reba...

Question What is role of rebate in typical construction joint ? Answer Construction joints are formed on sites to facilitate construction procedure. Though, if improperly constr

Fire resistance of steelwork, Q. Fire resistance of steelwork Because ...

Q. Fire resistance of steelwork Because of the high thermal conductivity of steel, temperature of unprotected steel is almost the same as temperature of fire. Because the yiel

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd