Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Accuracy and range - angle measurement, Accuracy and Range - Angle measurem...

Accuracy and Range - Angle measurement: Accuracy and Range:-Angle measurement:-Most modern total station instruments measure angles by means of electro-optical scanning of ext

Centroid, use of centroid in civil engineering

use of centroid in civil engineering

Slope protection, what is the type of slope protection that use rocks and p...

what is the type of slope protection that use rocks and put cements between those rocks??the concept is same as brick layer

Engineering Graphics, Draw a parabola , height 40mm and bass 120mm using of...

Draw a parabola , height 40mm and bass 120mm using offset method

Harbours - water transportation, Harbours: Types of Harbours ...

Harbours: Types of Harbours There are two types of harbours, viz : (a) Natural harbour, which is protected from storms and waves by the natural configuration of t

Best efficiency point and operating point for pumps, Q. Best efficiency poi...

Q. Best efficiency point and operating point for pumps? In a pumping system, a system curve can be derived based on static head needed to lift up the fluid and variable head be

How can a temporary diversion to laid, Q. How can a temporary diversion to ...

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months. Ans.- Temporary diversion

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd