Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Primavera, hi contactme 9902142308

hi contactme 9902142308

Centroid, how tofind centroid of cercular arc

how tofind centroid of cercular arc

#soil survey., Explian obstacles in chaining but not ranging.

Explian obstacles in chaining but not ranging.

Explain the perception reaction time, Explain the Perception Reaction Time ...

Explain the Perception Reaction Time A significant variable in the successful processing and use of information is the speed with which this is done. Perception-Reaction Time (

Base of concrete retaining walls, Q. Granular fill or rock fill essential a...

Q. Granular fill or rock fill essential at the base of concrete retaining walls? It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom

Explain the aashto classification system, Explain the AASHTO Classification...

Explain the AASHTO Classification System   1.  Identify the percent passing the No.10, No. 40, and No. 200 sieves. Identify the LL and PI of the fraction passing the No. 40 sie

Determine the probable period of time, A clay stratum is 4.5 m thick and re...

A clay stratum is 4.5 m thick and rests on a rock surface. The coefficient of consolidation of a sample of this clay was found to be 4.5 × 10-8 m 2 /s in the laboratory. Verify pro

Building material, how to calculate the specific gravity and water absorpti...

how to calculate the specific gravity and water absorption of coarse aggregate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd