Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Determine the term- shrinkage of concrete, Determine the term- Shrinkage of...

Determine the term- Shrinkage of Concrete Shrinkage of concrete is primarily due to gradual loss of moisture which results in change in volume. The shrinkage of concrete depend

Soil in road construction, Soil in Road Construction: Road Embankme...

Soil in Road Construction: Road Embankment and Sub-grade Soil is mainly used as the material for constructing a road embankment. The road embankment supports the road

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Distomat., write a note on distomat

write a note on distomat

Measure the stress increment, A raft of size 4 m × 4 m carries a uniform lo...

A raft of size 4 m × 4 m carries a uniform load of 200 kN/m 2 . Using the point load approximation with four equivalent point loads, measure the stress increment at a point in the

Trusses, Determine the support reactions for the truss shown below

Determine the support reactions for the truss shown below

Instruments, description and details about distomat

description and details about distomat

Fly levelling, what is fly levelling? when it is carried out ?

what is fly levelling? when it is carried out ?

Ground water, Two pumping wells 1,000 m away fully penetrate the same confi...

Two pumping wells 1,000 m away fully penetrate the same confined aquifer. One of the wells pumps at a rate of 1,240 m3/day. The second well pumps at 850 m3/day. If the aquifer has

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd