Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Shear slump and collapse slump in slump tests, Question What is sign of sh...

Question What is sign of shear slump and collapse slump in slump tests? Answer There are three varieties of slump that might occur in slumps test, specifically, slump, shear

Doors, About Doors,windows&vendilators

About Doors,windows&vendilators

Explain rebound hammer - underwater non-destructive testing, Explain Reboun...

Explain Rebound Hammer - Underwater non-destructive testing? The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condit

Determine the thermal stress in the bar, Determine the thermal stress in th...

Determine the thermal stress in the bar: A stepped bar made of aluminum is held between two supports. The bar is 900 mm in length at 38ºC, 600 mm of which is having a diameter

Concrete cover to enhance fire resistance, Q. Concrete cover to enhance fir...

Q. Concrete cover to enhance fire resistance? In the event of exposing concrete structures to a fire, a temperature gradient is established across the cross section of concrete

Classification of bricks, Bricks may be broadly classified as following: ...

Bricks may be broadly classified as following: Paving bricks Building bricks Special bricks A.   Fire bricks B.   Building Bricks: These bricks are utilized fo

Diagram of distribution pipelines from an overhead tank, Q. There is a colo...

Q. There is a colony having 15 blocks of Type - II quarters, each block having 8 quarters. Make out a diagram of distribution pipelines from an overhead tank and up to the quarters

Determine the diameter of the footing, A circular footing is resting on a s...

A circular footing is resting on a stiff saturated clay with qu = 250 kN/m 2 . The depth of foundation is 2 m. Verify the diameter of the footing if the column load is 600 kN. S

How to design banks, Q. How to design banks? When approach banks are of...

Q. How to design banks? When approach banks are of medium height upto 3 m, the material may be homogeneous. For bigger heights zoned section with impervious core and pervious o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd