Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Surving, describe the methods of reducing the levels,and their relative adv...

describe the methods of reducing the levels,and their relative advantages and disadvantages.

Calculate the amount put into saving account, Calculate the Amount put into...

Calculate the Amount put into Saving Account If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is m

Effect of concrete placing temperature, Effect of concrete placing temperat...

Effect of concrete placing temperature on early thermal movement Rate of hydration of cement paste is related to placing temperature of concrete. Rate of heat production is giv

Construction measurment, calculating quantity of excavation, formwork, conc...

calculating quantity of excavation, formwork, concrete

Explain the permissible settlement, Q. Explain the Permissible Settlement? ...

Q. Explain the Permissible Settlement? Any foundation may fail in shear or by excessive settlement. The failure due to shear is checked by adopting safe value of bearing capa

Determine the density index in the natural state, A soil sample with a grai...

A soil sample with a grain specific gravity of 2.67 was filled in a 1000 ml container in the loosest possible state and the dry weight of the sample was found to be 14.75 N. It was

Define concrete substruct - underwater inspection of bridges, Define Concre...

Define Concrete substruct - underwater inspection of bridges? Plain, reinforced, and pre-stressed concrete are used for construction of underwater elements. Since the majority

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd