Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Sub-surface Drainage: Sub-surface drainage is intended to take away the water seeping through the pervious layers of the soil, causing a high water table, or in cut slopes of
Q. Necessity of air valves in pressurized pipelines? Air valves are broadly categorized into two major types: single air valves and double air valves. Single air valve comprise
Q. Inspection and Quality Control Certificate : A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certif
Q. Explain Strain compatibility in mini-piles? In designing the axial capacity of mini-piles, grout can be taken into account in the contribution of axial load capacity. Though
Common ways to present the project schedule include all except: a. Gantt charts b. Milestone charts c. PERT charts D. Project Network Diagrams with dates added So
Example for Beam Flexure Design Select the lightest W section for the simply supported beam shown below. The beam length is 12ft. The nominal loading is: w d = 4.0 kip/ft (i
A 1.8 m square column is founded at a depth of 1.8 m in sand, for which the accurate N-value is 24. The water table is at a detph of 2.7 m. Verify the net allowable bearing pres
EXPLAIN THE USE OF INTERPOLATION IN CREATING CONTOUR LINE
write a short on vector representation of force(addition and substraction )
Define Types of Deterioration in Steel Substructure There are 5 major types of deterioration in steel substructure in the marine environment: - Corrosion - Abrasion - Loo
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd