Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Steel overlap in columns, where we can overlap steel in columns if we use ...

where we can overlap steel in columns if we use 50 or 60 bar diameter as overlap length.

Piling wall, explain about forces acting on a piling wall

explain about forces acting on a piling wall

What is oil interceptors, Q. What is Oil interceptors ? Oils and Grease...

Q. What is Oil interceptors ? Oils and Grease are usually found in stormwater runoff from catchments. They come from spillage and leakage of fuels, lubricants, Vehicle coolants

Yugty, #quesjjhjhhjtion..

#quesjjhjhhjtion..

How can designer cater for stability of minor slips, Question Soil nail...

Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Beams of uniform strength, determine the cross section of a rectangular bea...

determine the cross section of a rectangular beam of uniformly strength for a simply supported beam of 6m span subjected to central concentrated load of 20kN a)by keeping depth of

Deflections of bars, how do one uses the Macauleys model to find deflection...

how do one uses the Macauleys model to find deflections of bars

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd