Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Different tape corrections
Soil Compaction: Soils used in road construction need to be thoroughly rolled and compacted. Compaction of soil is needed for the following reasons. (a) A well compacted s
Question Is it resourceful that engineers rely solely on Hiley's formula in designing of H-piles? Answer About 90 percent of H-piles accept Hiley's formula for desig
Question What is major disparity between capping beams and ground beams for piles? Answer Capping beams for piles plan to transferring loads from directly spaced c
Role of Each Mode of Transport: Each mode of transport has its own role to play in a country. The role of each is as under: Roads : Road transport carries 80 per cent of
What is the meaning of term -Slip in Anchorage In the case of post-tensioned concrete, when the tendons are anchored at the ends of concrete members, a slip of tendons takes
what is the water bound macadam road
Explain the Bridge Selection Criteria - Underwater inspection? Various factors influence the bridge selection criteria. As a minimum, all structures must receive routine underw
assingnment
Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd