Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
I retained the soil in my yard by brick with 3 levels to avoid sliding the soil to the street. the appeared part of the bricks from each level is 3 feet and less.The hidden part o
Q. What are basic types of elastomeric bearings? Three basic types of elastomeric bearings are used. 1. Plain elastomeric pads 2. Steel reinforced elastomeric pads 3.
closed traverse maths problems
Dock Wall and Dry Dock: Dock Wall Figure gives the diagram of a dock wall. Figure: Mass Concrete Dock Wall Dry Dock Figure 9 gives the details
Calculate the Total Area (acre) for Lot A 30-ft wide parabolic shaped stream divides the property as shown. The total area (acre) for Lot 6 is most nearly: Solution:
• A potential source of harm - Mechanical hazard - Electrical hazard - Cutting hazard - Toxic hazard - Fire hazard - Explosion hazard
Q. Show the Direction of gunning in shotcreting? At the time of the construction of shotcrete, it is intended at gunning the full thickness in one single operation and this hel
how can find forebearing
Q. Which type of pile cap transfers loads equally to piles, flexible pile cap orrigid pile cap? Loads from columns transferring to pile cap persuade tensile forces at the bott
Explain about the Pot Bearing? POT bearing was developed in 1959 as an alternative to heavy steel sliding bearings. It consists of a circular non-reinforced rubber-pad fully en
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd