Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Q. Show the Functions of hydraulic jump? The usage of hydraulic jump in hydraulic engineering isn't uncommon and creation of such jumps has numerous purposes: (i) Its majo
State and prove parallelogram law of forces
uses concrete slump test
Define and distinguish among coefficient of volume compressibility and coefficient of consolidation. Explain clearly one method of computing coefficient of consolidation, given
use of rapid sand filter in grey water treatment units
Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i
Question What are the major functions of following features observed in a typical manhole ? Answer (i) Groove near benching, (ii) R.S.J. (iii) double seal manhole cove
Reasons of common occurrence of "inadequate pile founding level" in piles of piers The most severe load on piers usually is the horizontal load owing to berthing and mooring o
Ropeways: The system of ropeways consists of : (a) a cable suspended between towers, and (b) cars which move on the cable. Case with capacity upto 20 passengers is us
A -3.00% grade intersects a +1.25% grade at Sta. 85+80 and elevation 210.00 ft. A 350-ft vertical curve connects the two grades. Determine the station and elevation of turning po
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd