Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Determine about the pre-stressed concrete beam, Determine about the pre-str...

Determine about the pre-stressed concrete beam A pre-stressed concrete beam has a width of 200 mm and an overall depth of 400 mm. The permissible stresses in tension and compre

Particle size distribution - soil compaction, Particle Size Distribution (G...

Particle Size Distribution (Gradation): The particle size distribution is determined by passing the aggregates through a set of standard IS sieves (Figure) and determining th

State the design process of prestressed concrete, State the Design process ...

State the Design process of Prestressed Concrete Most of the times, the design process is an interactive and trial procedure in which the cycle of analysis - design - analysis

Show the overlays on concrete bridge deck, Q. Show the Overlays on concrete...

Q. Show the Overlays on concrete bridge deck? After years of servicing, some overlays can be applied on the top surface of bridges. Overlays on concrete bridge decks achieve th

3 wire leveling, can you give me some examples and problems in 3-wire level...

can you give me some examples and problems in 3-wire leveling?

Cost-volume relationship, Cost-volume relationship: Cost-volume relati...

Cost-volume relationship: Cost-volume relationship is illustrated through a simple example dealing with the cost of operating an automobile. To perform the analysis following

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Sanitary, Design a sewer network

Design a sewer network

Matrix method of analysis, Ask question #Explalin a joint frame by stiffne...

Ask question #Explalin a joint frame by stiffness method

Plinth wall, is it necessary for to put plinth wall in buildings

is it necessary for to put plinth wall in buildings

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd