QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Evaluation of various reports regarding the effects of earthquake on spatial trusses History and static In this section we aim to provide a summary report of what was happ
Define the Ultrasonic Thickness Measurement? Ultrasonic thickness meters measure the thickness of steel by passing an ultrasonic wave through the member. Thickness measurements
Explain the Limitations of Rebound Hammer? The following characteristics of concrete can affect the correlation of the rebound number with the actual surface hardness and shoul
Q.for ISMB200 having 6.70 m span simply supported so find out load carrying capacity.
Q. Illustrate the Design discharge for foundation? To provide for an adequate margin of safety, the foundation and protective works of a bridge should be designed for a flood d
Determine the condition of each activity in the network flow diagram shown below Ans: a. Activity C can be started only after the completion of activities A and
Specify the various methods of soil exploration and mention the circumstances under which each is best suited. What do you mean by undisturbed sample? Define with a neat sketch
Cumulative distribution function - Poisson distribution: Find the cdf of Y = X 1 , + X 2 where X I and X 2 independently follow Poisson distribution with parameters λ l an
Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o
when i have solved the given assignment work then how will you pay me for that work??
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd