Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Semi elliptical arch, how can i build a semi-elliptical arch out of bricks?...

how can i build a semi-elliptical arch out of bricks?

How do we calculate absolute pressure, Absolute is equivalent to gauge pres...

Absolute is equivalent to gauge pressure plus atmospheric.

NERNST EQUATION, HOW CAN I MAKE ASSIGNMENT ON THIS TOPIC

HOW CAN I MAKE ASSIGNMENT ON THIS TOPIC

Define rotation - actions in pot bearings, Define Rotation - Actions in POT...

Define Rotation - Actions in POT Bearings? POT bearings are associated with large rotations which are accommodated by the deformation of elastomeric pad. Large cyclic rotations

Design of flexible pavements - road pavements, Design of Flexible Pavements...

Design of Flexible Pavements: The design of flexible pavements is done by the CBR method. The CBR test, described further, gives an indication of the supporting power of the

Internal force of preloaded fasteners, Q. Internal force of preloaded faste...

Q. Internal force of preloaded fasteners? Force in a bolt in a bolted joint relies on the preloading force applied to it at the time of the tightening operation. For example, w

Deflection in concrete structures, Tension reinforcement leads to increasin...

Tension reinforcement leads to increasing deflection in concrete structures? In BS8110 a modification factor is applied to span/depth ratio to take into account effect of tens

Delay of bituminous laying on top of sub-base, Question In case if ther...

Question In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base? Answer When there is a d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd