Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Q. Write short notes on Pressure filter for drinking water supply. What are pressure filters and what are its advantages / disadvantages over the normal filter bed. What is p
grading classification
Question: What are dissimilar applications of draglines, backhoes and shovels? Answer: An excavator is distinct as a power-operated digging machine and it includes di
types of concrete and its uses
Question What is key distinction in arranging pumps in series and in parallel? Answer For same pumps with similar functions, if pumps arranged in series, total head
Cross Drainage Work: Several natural streams, rivers and canals cross the road. They have to be led across the road through culverts and bridges. That given structures is kno
Q. Optimum binder content in bituminous pavement? Amount of binder to be added to a bituminous mixture can't be too excessive or too little. Principle of designing the optimum
Question While design life will it be same as return period for design situations ? Answer Design life means least duration a structure is accepted to last. Longe
what do you mean by civil engineer
Q. Show the Excessive movement joints in bridges? Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd