Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

CANTILEVER RETAINING WALL, NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HI...

NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HIGH, SATURATED UNIT WEIGHT IS 16KN/M3, SURCHARGE IS 7KN/M2, LOAD ABOVE WALL SUPPORTED ON WALL STEM IS 10KN/M RUN, ANGLE IN INTERNAL F

Design the 2-span continuous center, Design the 2-span continuous center T-...

Design the 2-span continuous center T-beam, B2, for the floor syetem shown below. The girders that the beam frames into are all 24" wide. Using fc'= 5 ksi, and fy = 60 ksi. The ser

Explain the kinematic viscosity, Explain the Kinematic Viscosity Ratio ...

Explain the Kinematic Viscosity Ratio of a fluid's Viscosity to the same fluid's Density.  Greek symbol: ν nu    ν = μ/ρ = Absolute Viscosity/Mass Density    Units: ft

Define the disintegration - underwater inspection of bridge, Define the Dis...

Define the Disintegration - underwater inspection of bridge? Disintegration of concrete may be defined as the deterioration of concrete into small fragments or particles result

Concrete technology, what is the actual quantity of water to be mixed in va...

what is the actual quantity of water to be mixed in various grade of concrete and also the size of gravel to be mixed with in RCC work. Also I want to know the difference between a

Calculate load distribution factor, Load Distribution Factor: The form...

Load Distribution Factor: The formula for deriving at the number of repetitions of the standard axle load during a design period of n years is: N =365 × A × VDF × F [(1 + r

#soil survey., Explian obstacles in chaining but not ranging.

Explian obstacles in chaining but not ranging.

Levellng, introduction of levelling

introduction of levelling

Engeneering surveying, demonstrate your understanding of the term setting o...

demonstrate your understanding of the term setting out

Measure the ultimate settlement due to pumping, A clay stratum of 18 metres...

A clay stratum of 18 metres thickness was found above a sand stratum when a boring was made. The clay was consolidated under the present overburden pressure. The hydrostatic pressu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd