Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Mechanism of taking up loads for concrete paving blocks, Mechanism of takin...

Mechanism of taking up loads for concrete paving blocks  Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet

Soil Mechanics, What relationship between Atterberg limits and cohesion

What relationship between Atterberg limits and cohesion

Major ways to undertake negative skin friction, Question What are major...

Question What are major ways to undertake negative skin friction ? Answer (i) Utilize slender pile sections since smaller pile area when subject to same working load

Friction dampers, what is friction damper and there types?

what is friction damper and there types?

Breast walls, Breast Walls Needed to buttress uphill slopes. ...

Breast Walls Needed to buttress uphill slopes. Figure : Breast Check Walls Small retaining structures provided in series to arrest landslides. Gabio

Harbours, natural phenomenon affecting the designs of harbours

natural phenomenon affecting the designs of harbours

Surveying, how to solve the problems of cross sectional surveying and profi...

how to solve the problems of cross sectional surveying and profil questions

Micro-organism ratio, Micro-organism ratio: Determine the F/M ratio (i...

Micro-organism ratio: Determine the F/M ratio (in units of lbs BOD5/lb MLSS-day) using data provided in the above example problem. Solution By definition, F/M = Q S

Cutting edge in well foundation, Q. Cutting edge in well foundation? Th...

Q. Cutting edge in well foundation? The function of cutting edge on well foundation is basically to cut through the earth which being sunk. The angle of well curb pushes the ea

Tests on bitumen, Tests on Bitumen: The following tests are conducted...

Tests on Bitumen: The following tests are conducted on bitumen to find its suitability as a road binder : (a) Penetration test (b) Softening Point test (c) Flash Poi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd