Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
What are main and key benefits of piers constructed monolithically with bridge deck over usage of bearings?
Breast Walls Needed to buttress uphill slopes. Figure : Breast Check Walls Small retaining structures provided in series to arrest landslides. Gabio
Example of Foundation depth and arrangement: For example, if the maximum discharge of a river is 1000 cu m per sec, and the silt factor is 0.60, the maximum scour depth is :
location of hydrolic jump
Cross-sectional area of flow (ft 2 ) (A) For rectangular channels = (w)(d). For trapezoidal channels, divide the flow area into two side triangles and one center rectangle, so
how many bag of cement make a cubic
Explain the term - Moderate Prestressing In this form of prestressing, no limit is imposed on the magnitude of tensile stresses which may be produced in a concrete member unde
Explain the Steady and Uniform Flow Steady flow: Flow quantity does not change over time. Uniform flow: The slopes of the energy grade line S = dE/dL, the hydraulic grade li
Ask question #Minimum 100 words ameccepted#
what is the allwoable combined aggregates Fineness Modulus
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd