Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Explain pressure balance method and compressed air method, Pressure balance...

Pressure balance method vs. compressed air method in pipe jacking Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutti

Show the direction of gunning in shotcreting, Q. Show the Direction of gunn...

Q. Show the Direction of gunning in shotcreting? At the time of the construction of shotcrete, it is intended at gunning the full thickness in one single operation and this hel

Hazard, • A potential source of harm - Mechanical hazard - Electrical...

• A potential source of harm - Mechanical hazard - Electrical hazard - Cutting hazard - Toxic hazard - Fire hazard - Explosion hazard

How to evaluate quality of bricks, Q. How to evaluate quality of Bricks? ...

Q. How to evaluate quality of Bricks? 1. Clour -Deep red, Carry red, Copper red, colour is indication of uniform burning and also suggests quality of clay used. Over brunt bric

Fluid mechanics, How a water bound macadam road is maintained

How a water bound macadam road is maintained

State the term - constant eccentricity, State the term - constant eccentric...

State the term - constant eccentricity A pre-stressed concrete beam has a width of 300 mm and an overall depth of 450 mm. The permissible stresses in tension and compression du

Brickwork, write buckling and dislodging of brick slip?

write buckling and dislodging of brick slip?

Discuss about the term - end zone, Discuss about the term - End Zone It...

Discuss about the term - End Zone It is the length of a post-tensioned concrete member, at the end, which is required to get a distribution of prestress over the whole of the c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd