Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

major importance of air void content, Question What is major importanc...

Question What is major importance of air void content in bituminous pavements? Answer Air void content of bituminous materials is important control parameter for quali

What is the meaning of concordant prestressing, Concordant Prestressing ...

Concordant Prestressing In this type of prestressing, tendons follow a concordant profile. The concordant profile of  tendons does not change the support reactions in a statica

Measurements, Explain the concept of average velocity

Explain the concept of average velocity

Univariate normal distribution, Univariate normal distribution: Let X ...

Univariate normal distribution: Let X = (X I , X 2 , ..., X n ,) has the multivariate normal distribution (5.26) of Section 5.4. Show that Y = a X ' follows a univariate norma

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Concrete structure, which section is most effective for a design of beam an...

which section is most effective for a design of beam and why

Varigon theorem, Ask questio #Minimum 100 words accepted# what is varigon ...

Ask questio #Minimum 100 words accepted# what is varigon theorem and what are their application ? its examples

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd