Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Explain the strength design (lrfd), Explain the Strength Design (LRFD)   ...

Explain the Strength Design (LRFD)   1. γ Factors are applied to loads and φ factors applied to resistance. 2. Unfactored service loads receive a load factor γ > 1.0

Road materials, Road Materials Earthwork and pavements constitute a si...

Road Materials Earthwork and pavements constitute a significant part of the cost of a road. Hence it is desirable that thorough investigations be done about the availability o

Disparities b/w epoxy grout cement grout and cement mortar, Question What a...

Question What are the key disparities between epoxy grout cement grout and cement mortar ? Answer Epoxy grout contains of epoxy resin, epoxy hardener and sand or aggregates.

High temperature in laying bituminous pavement, High temperature in laying ...

High temperature in laying bituminous pavement Generally bituminous materials are also broadly categorized into two types viz bitumen McAdamsand hot-rolled asphalts. At the ti

Heating season duration , Change the model to take into account the variati...

Change the model to take into account the variation in outdoor temperature for a "typical" day in the heating season based on the heat loss by the fabric and the heating of incomin

Determine the settlement of the foundation, The thiclcness of the normally...

The thiclcness of the normally consolidated soft clay layer is 6 m. The natural water content is 31 percent. The specific gravity of the soil being 2.68 with a liquid limit of 4

Wet mix Macadam, Test required before laying or after laying.

Test required before laying or after laying.

Keywords of airport management, Keywords of Airport management: Air T...

Keywords of Airport management: Air Traffic Control: A system by which air routes, flight rules for flying aircraft and navigational facilities are provided in an airport.

Steel overlap in columns, where we can overlap steel in columns if we use ...

where we can overlap steel in columns if we use 50 or 60 bar diameter as overlap length.

Construction of embankment, Construction of Embankment: The following...

Construction of Embankment: The following steps describe embankment construction : (a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd