Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

PLANKING AND STRUTING FOR SHALLOW EXCAVATION, DEFINITION TYPE STEP OF CON...

DEFINITION TYPE STEP OF CONSTRUCTION STEP OF SAFETY

Calculate surface loading rate for each clarifier, A wastewater plant is op...

A wastewater plant is operating at 10MGD with a suspended solids concentration of 200mg/L. It has 6 clarifiers operating in parallel. Each clarifier is 40 foot in diameter and 10 f

Cement, uses of heavy weight aggregate

uses of heavy weight aggregate

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

Mechanics of solids, Ask question #MinThe maximum instantaneous extension, ...

Ask question #MinThe maximum instantaneous extension, produced by an unknown falling weight through a height of 4 cm in a vertical bar of length 3 m and of cross sectional area 5 c

Determine the statement about construction earthwork, Which of the followin...

Which of the following statements about construction earthwork are true: I.  The volume of earth known in its natural state is known as bank-measure; in-situ; in-place; virgin

Block contouring, how to calculate contour surveyed area

how to calculate contour surveyed area

Report, report on lintels and arches

report on lintels and arches

Rectangular tie, using an optical square how would you perform a rectangula...

using an optical square how would you perform a rectangular tie?

Fy steel, what is the yield stress for reinforcement steel?

what is the yield stress for reinforcement steel?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd