Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Float or slack of an activity is positive or negetive, 1. What take place w...

1. What take place when float or slack of an activity is positive Ans: It represents a situation where extra resources are available and the completion of the project is not de

What do you mean by river gauging, Q. What do you mean by River Gauging? ...

Q. What do you mean by River Gauging? Due to certain behavior of rivers the problem of gauging then is quit complex. The purpose of river gauging is to stabilize the river chan

SHEARING STRESS IN CIRCULAR SECTION, SHEAR STRESS DISTRIBUTION INTO CIRCULA...

SHEAR STRESS DISTRIBUTION INTO CIRCULAR SECTION DERIVATION

Air infiltration, Using Matlab/ Simulink software, verify the heating requi...

Using Matlab/ Simulink software, verify the heating requirement (kW) for the building because of  air infiltration and natural ventilation. Note that this needs you to estimate air

Transportation engineering, What areb the philosophical elements of strateg...

What areb the philosophical elements of strategic planning?

Point of virtual fixity of lateral loading for piles, Point of virtual fixi...

Point of virtual fixity and critical length of lateral loading for piles Some engineers can get confused about the difference between the two terms which are point of virtual

Hydaurlics : pelton and francis turbine, what are the factors which influen...

what are the factors which influence the efficiency of the turbine?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd