Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Compatibility Condition: Total strain in steel = Total strain in copper i.e. 3 × 10 -4 + 1.965 × 10 -5 P s = 4.5 × 10 -4 + 1.8421 × 10 -5 P c Recognising that P
TH ADVANTAGES OF FLAMISH BOND
Q. Vibration in structures - resilient bearings? When railway tunnels are built close to buildings, ground-borne vibration is transmitted to buildingsthrough compression and sh
Question Should reversible moisture movement be taken into account in estimating movement for movement joints ? Answer Size of concrete is affected by changes in dist
Define Investigation Scour for Underwater Inspection of Bridge? Investigation Scour is probably the most critical item to be aware of when performing an underwater inspection o
Snow weight In spatial trusses, Snow load is much more important than building. As in buildings snow load is only a small proportion of the overall weight of the building, it w
Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was
what is vertical deflection of a beam, a conservative structure and of what use is castigliano theoremn
design of irrigation channel permissible velocity table
Q. What do you mean by No fines concrete? Sometimes no fines concrete is used in houses due to its good thermal insulation properties. Essentially no fines concrete comprises c
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd