Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Question In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base? Answer When there is a d
any new innovative metods to protct building from disater
Where to overlap rcc column
reparation of subgrade in sqm for a road of span 12 km and width 5.25m,with shoulders of 0.75m span on both the sides...considering extrawidening too......plz help...i m preparing
Q. What is Diaphragms in bridges? Diaphragms in bridges The principal function of diaphragms is to provide stiffening effect to deck slab in case bridge webs aren't situat
Define Chemical Deterioration - Underwater inspection of Bridge? Chemical deterioration may occur in concrete, which has not been properly compacted, or through environmental p
Explain about the Pot Bearing? POT bearing was developed in 1959 as an alternative to heavy steel sliding bearings. It consists of a circular non-reinforced rubber-pad fully en
what is the yield stress for reinforcement steel?
Inspite of the problems of sample disturbance, if 1) e or E vs log p curve is interpreted, reasonably with some corrections for sample disturbance, 2) if the sample disturbance
A retaining wall with a vertical back 5 m high supports cohesion less backfill of unit weight of 19 kN/m 3 . The upper surface of the backfill rises at an angle of 10° with the hor
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd