Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Define Cyclic Force Transfer Test of Shock Transmission Unit? This test is specified to prove that the STU would function as intended during a seismic event. The STU shall be t
Properties of Stones The following properties of the stones should betake into account before choosing them for engineering works: Structure: The structure of the stone ca
Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o
Q. What is Rail Lubricators? 1. P & M type of lubricators - These lubricators can be used for lubrication of FF rails as well as BH rails. 2. Elgi grease pump - Elgi Bucket
Q. Fixed vs pinned connection between piles and pile caps? The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile hea
#question.
I have assignment for hydraulics can you help for that
Q. Direction of approaching velocities of ships during berthing? One of the key effects of angle of approaching velocities of ships is its influence of energy to be absorbed by
Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by the engineer engaged in the design of pre-stressed concrete membe
what is premix carpet open graded and where is it used and what are its limitations ?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd