Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
ratio of moorum and aggregate
In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material? There are two
How to do deflection calculations Basic values of span to effective depth ratios for spans upto 10m may be taken as 7, 20 and 26 for cantilever, simply supported and continuous
Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw
Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng
how to convewrt wcb into rcb
We need all types of Upper floor
The design of flexible pavements how it is used
structure of exogenous trees
Question What is reason of skin reinforcement for deep beams ? Answer In BS8110, it declares that secondary reinforcement have to be provided for beams greater than 750mm deep
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd