Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Question For a l ong slender structure similar to beams, propping is compulsory after elimination of formwork with reasons? Answer After concreting, time at which arresting of
Unsealed contraction joints in concrete pavement For unreinforced concrete pavement, contraction joint is an approximately 3mm wide groove with a depth of about one-third to o
Design of the stormwater drainage system for the sub-division Work needed: The following tasks require to be performed for the drainage network: Compute stormwater r
Q. Local Scour at obstructions in rivers? When the water flow in river is deflected by obstructions such as bridge piers, scouring would occur arising from formation of vortexe
explain distomat
Determine the Steps for routine inspection? A routine inspection should normally include: - A Level I inspection on 100% of the underwater portion of the structure to determ
Which of the following stress-strain curves represents a soft and weak material? Solution: As depicted, stress is on the y-axis while the x-axis represents strain.Whe
What is compacting factor
Q. Explain about Warren Truss? A truss is a simple structure whose members are subject to axial compression and tension only and however not bending moment. The most common tru
The cost of utilities, taxes and maintenance on a home is $3,000 per year. The amount of money that would have to be invested now at 8% to cover these expenses for the next 5 year
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd