Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
A saturated clay layer 4 m thick is located 6 m below GL. The void ratio of the clay is 1.0. When a raft foundation is located at 2 m below GL, the stresses at the top and bottom o
A clay layer 24 metres thick has a saturated unit weight of 18 kN/m 3 . Ground water level occurs at a depth of 4 metres. It is proposed to construct a reinforced concrete foundati
calculate npsh
free body diagram of a walk bridge
which truss is suitable for 19*22m span on which mangalore tiles can be placed or shud steel truss be preferred for such span and which 1 is more profitable in rural desiggn...
how can we build a complete home on an area of 500 meter squares with garden and house and a garage
Need this assignment due in 10 hours
Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish
write buckling and dislodging of brick slip?
1) A propped cantilever beam ABC is 7m long.It has the point C fixed and Point A on a roller support.It carries a 200Kn point load at a distance 3m from A.There is a moment of 80KN
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd