Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Question What are key reasons for conducting pull-out tests for soil nails ? Answer There are largely four bases for this examination- (i) To verify and verify bo
Calculate the Actual Water Cement Ratio A jobsite delivery ticket is shown below for a grout mix. The actual w/c ratio is most nearly: Solution: Note, althou
why water is necessary for concrete
Tack coat - emulsified asphalts vs. cutback asphalts Emulsified asphalt is a suspension of asphalt in water by employing an emulsifying agent that imposes an electric charge o
what are the problems in traditional marine pilling system of steel tubular pile with concrete infill
i want to just understand civil eng main points of all subjects which i becam able to tell some body about this tha what is this ?
Find the maximum stress: A circular bar rigidly fixed at both ends is 1 m long and tapers uniformly from 20 cm diameter at one end to 10 cm diameter at the other end. Find the
Explain the term - Loss of Prestress At the transfer stage, tendons produce compressive stresses in concrete. Sooner or later, the magnitude of these stresses experiences a re
Light-weight Aggregate Prestressed Concrete The use of light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of light-
Q. Granular fill or rock fill essential at the base of concrete retaining walls? It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd