Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Define cyclic force transfer test of shock transmission unit, Define Cyclic...

Define Cyclic Force Transfer Test of Shock Transmission Unit? This test is specified to prove that the STU would function as intended during a seismic event. The STU shall be t

Properties of stones, Properties of Stones The following properties of ...

Properties of Stones The following properties of the stones should betake into account before choosing them for engineering works: Structure: The structure of the stone ca

Necessity of pile tip cover for rock-socketed H-piles, Q. Necessity of pile...

Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o

What is rail lubricators, Q. What is Rail Lubricators? 1. P & M type of...

Q. What is Rail Lubricators? 1. P & M type of lubricators - These lubricators can be used for lubrication of FF rails as well as BH rails. 2. Elgi grease pump - Elgi Bucket

Fixed and pinned connection between piles and pile caps, Q. Fixed vs pinned...

Q. Fixed vs pinned connection between piles and pile caps? The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile hea

Hydraulics assignment , I have assignment for hydraulics can you help for t...

I have assignment for hydraulics can you help for that

Direction of approaching velocities of ships during berthing, Q. Direction ...

Q. Direction of approaching velocities of ships during berthing? One of the key effects of angle of approaching velocities of ships is its influence of energy to be absorbed by

Problems formed while design of pre-stressed concrete, Determine the proble...

Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by  the engineer engaged in the design of pre-stressed concrete membe

Premix carpet open graded, what is premix carpet open graded and where is i...

what is premix carpet open graded and where is it used and what are its limitations ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd