Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Explain the equation for length of spiral curve, Explain the Equation for L...

Explain the Equation for Length of Spiral Curve Length of Spiral Curve can be calculated using the following equation L s = 3.15V 3 /RC Where: V - Design Speed in MPH

Prismatic compass, Figure, working,principle of prismatic compass

Figure, working,principle of prismatic compass

For the plane area shown determine the first moments, for the plane area sh...

for the plane area shown determine the first moments with respects to the x & y axis & the location of the centroid

Define the highlights of critical path method, Define the Highlights of Cri...

Define the Highlights of Critical Path Method A network analysis technique used to predict project duration by analyzing which sequence of activities has the least amount o

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Explain the term - uniaxial - biaxial -triaxial prestressing, Explain the t...

Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di

Define shear slump and collapse slump in slump test, Q. Define Shear slump ...

Q. Define Shear slump and collapse slump in slump test? There are three kinds of slump which can take place in a slumps test, namely, true slump, shear slump and collapse slump

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd