Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

What is partial prestressing, What is Partial Prestressing It is a form...

What is Partial Prestressing It is a form of prestressing in which tensile stresses are permitted, upto a limited extent, in concrete under working loads. As the permitted tens

What is thermo-electric prestressing, What is Thermo-electric prestressing ...

What is Thermo-electric prestressing We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other mea

What is pratt truss, Q. What is Pratt truss? Pratt truss is characteriz...

Q. What is Pratt truss? Pratt truss is characterized by having its diagonal members (except the end diagonals) slanted down towards the middle of bridge span. Under such struct

Dissimilarity between open stirrups and closed stirrups, Question What is d...

Question What is dissimilarity in request between open stirrups and closed stirrups in Concrete beams? Answer Open stirrups are supplied principally to oppose shear forces in

Principal stresses and strains, Principal Stresses and Strains: Princi...

Principal Stresses and Strains: Principal Stresses and Strains is a very important link in the analysis of solids so as to make sure safe design of different components of str

Explain subcritical flow and supercritical flow, Explain Subcritical flow a...

Explain Subcritical flow and Supercritical flow Subcritical flow: The depth of flow is greater than critical depth and the velocity of the fluid is slow. Also termed "tranquil"

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Cement, manufacture of cement by dry process

manufacture of cement by dry process

Determine the ground elevation, The trigonometric levelling from the survey...

The trigonometric levelling from the surveyor's notes is shown below. The ground elevation of T (ft) is most nearly: Solution:  The elevation of point P can be found from: E

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd