Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Deflections of bars, how do one uses the Macauleys model to find deflection...

how do one uses the Macauleys model to find deflections of bars

Example for productivity analysis and improvement, Example for Productivity...

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

Transitional jacks designed in pipe jacking projects, Question Why are ...

Question Why are transitional jacks designed in pipe jacking projects? Answer While development of pipe jacking stops, building up of confrontation is extremely

FOUNDATION, TYPE OF FOUNDATION IN LATERITE SOIL

TYPE OF FOUNDATION IN LATERITE SOIL

Construction health & safety, List different access equipment & their uses ...

List different access equipment & their uses wih pictures

Define the types of pump performance curves, Define the types of Pump Perfo...

Define the types of Pump Performance Curves Two types of pump performance curves: x-axis = flow rate; y-axis = head (TDH). Characteristic curves: Provided by the pump m

Explain the contracted rectangular weir, Explain the Contracted Rectangular...

Explain the Contracted Rectangular Weir Weir plate has sides which extend above the maximum water surface, directing the flow through an opening (b = weir length). Typically th

How the water table is lowered, The water table is lowered from a depth of ...

The water table is lowered from a depth of 3 m to a depth of 6 m in a deposit of silt. The silt remains saturated even after the water table is lowered. What would be the enhance i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd