Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Geo Technical Project, I have a geo technical Project that I need to be sol...

I have a geo technical Project that I need to be solved correctly and accurately within 15 hours exact, please. Steps and details must be included. Thanks a lot and let me know ASA

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Determine the grain exact gravity, (i) A dry soil has a void ratio of 0.65 ...

(i) A dry soil has a void ratio of 0.65 and its grain exact gravity is = 2.80. What is its unit weight? (ii) Water is added to the sample so that its degree of saturation is 60%

Build of a cmplete home, how can we build a complete home on an area of 500...

how can we build a complete home on an area of 500 meter squares with garden and house and a garage

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Compacted thickness of bituminous pavement, Q. Compacted thickness of bitum...

Q. Compacted thickness of bituminous pavement? The choice of compacted thickness is closely related to the nominal maximum size of aggregates of bituminous materials. Based on

Jetties, JETTIES: A jetty is a structure projecting into the sea from ...

JETTIES: A jetty is a structure projecting into the sea from the shore line for receiving ships. They are made of RCC trestles with a deck to accommodate railway track and roa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd