Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Changeable depth bridge decks, Question What is the sucker deck principle f...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greater tha

Degree, what classes do you have to take and what are some school options?

what classes do you have to take and what are some school options?

Difference between compaction and consolidation of soil, Briefly explain th...

Briefly explain the difference between compaction and consolidation of soil. What is the effect of compaction on soil properties? Ans.- Compaction - The process of increas

Determine the expected extension at the jack, A cylindrical concrete tank,...

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  10 5   N/mm 2 )  jacked  at 4 points, 9

Determine the bar sizes and spacing, Referring to problem 1, in order to me...

Referring to problem 1, in order to meet a 1-hour fire code rating the slab thickness must be at least 4.00. Based on the information given in problem 1 and with a slab thickness o

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

California Bearing Ratio, What is the California bearing ratio for granular...

What is the California bearing ratio for granular A, Granular B, 19 mmm Crusher Run Limestone, 50 mm Crusher run limestone, HL3 and HL8 Asphalt?

Theodolote, List out the permanent adjustments of dumpy level.

List out the permanent adjustments of dumpy level.

Invoice Method, How to raise an invoice with WCT for Civil construction job...

How to raise an invoice with WCT for Civil construction job?

Illustrate the concept of load balancing, Concept of load balancing In ...

Concept of load balancing In above cases of concentric and eccentric pre-stressing, straight tendon profiles (or tendon shapes) along the beam span have been considered. If a t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd