Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Wbm work, ratio of moorum and aggregate

ratio of moorum and aggregate

Show the benefits of adopting marine fill, In reclamation involving large v...

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?  There are two

How to do deflection calculations, How to do deflection calculations Ba...

How to do deflection calculations Basic values of span to effective depth ratios for spans upto 10m may be taken as 7, 20 and 26 for cantilever, simply supported and continuous

Determine the concept of resultant force at a section, Resultant force at a...

Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw

Tests on cement, Tests on Cement: The following tests are conducted o...

Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng

#title, how to convewrt wcb into rcb

how to convewrt wcb into rcb

Upper floor, We need all types of Upper floor

We need all types of Upper floor

Timber, structure of exogenous trees

structure of exogenous trees

Reason of skin reinforcement for deep beams, Question What is reason of sk...

Question What is reason of skin reinforcement for deep beams ? Answer In BS8110, it declares that secondary reinforcement have to be provided for beams greater than 750mm deep

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd