Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Calculates the energy required, Write a program called, A1Q1, that reads a ...

Write a program called, A1Q1, that reads a single letter.   It will then display the corresponding ASCII code of the letter and prints the next character and the character which is

Unsymmetrical bending, An 8 kN.m moment is applied at the end of a block fi...

An 8 kN.m moment is applied at the end of a block fixed into the ground as illustrated in thefigure below. The moment vector (double arrow head representation) acts in line with th

Harbours, natural phenomenon affecting the designs of harbours

natural phenomenon affecting the designs of harbours

True or false, an increase in consumer income will affect the supply of any...

an increase in consumer income will affect the supply of any given product

What is load carrying capacity of a pile, Q-  What are loads and forces ta...

Q-  What are loads and forces taken into account for designing a pile and what is load carrying capacity of a pile. Ans. For designing a pile the following loads and force ar

Diffrence between hudsons and van der meer formula, Q. Diffrence between Hu...

Q. Diffrence between Hudsons and Van der Meer formula? Hudson's formula is usually adopted in preliminary design to attain rough initial estimate of rock size. This formula is

Geotechnical engg., friction circle method of stability of slope

friction circle method of stability of slope

Calculate the volume of excavation, Calculate the Volume of Excavation ...

Calculate the Volume of Excavation Using the information given in Figure, the volume of excavation in yd 3 is most nearly:   Solution: Use the average end area meth

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd