Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Classification of timber based on availability:, Classification Based on Av...

Classification Based on Availability: Forest departments categorized timbers based on the availability as X=Most common. 1415 m 3 or more per year Y=Common. 355 m 3 to 1415

Define emerging trends in bearings, Define Emerging Trends in Bearings? ...

Define Emerging Trends in Bearings? New innovations have taken place in the area of bridge bearings, notable among them are: (1) Shock Transmission Unit (STU) or Lock Up Dev

Water treatment, what is filtration membrane, is it''s type mechanism

what is filtration membrane, is it''s type mechanism

Determine the size and number of aeration basins, Determine the Size and Nu...

Determine the Size and Number of Aeration Basins? For a community of 100,000, determine the size and number of aeration basins in a municipal activated sludge treatment facilit

#support reactions, calculate the support reaction as shown in figure;

calculate the support reaction as shown in figure;

Define the pump and motor efficiencies - hydrolic system, Define the Pump a...

Define the Pump and Motor Efficiencies Equations account for the loss of power, primarily due to mechanical friction as a result of rotating components in the pump and motor.

#memory, assign for memory unit

assign for memory unit

Human values, give the two aspects of honesty& explain

give the two aspects of honesty& explain

Elongation, Elongation of bar due to self weight

Elongation of bar due to self weight

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd