Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Define Pressure on an Inclined Plane Similar to a vertical plane, fluid pressure increases linearly with increasing depth. The average pressure on an inclined plane occurs at t
can i use lockfix to making cantilever beam
You have been selected to assist the structural engineer for a bridge replacement project. Your task is to design the size of the footing for an interior bridge pier, based on the
Define rocks,types of rock,rock formations
Softening Point Test: The temperature at which bitumen softens is determined by the "Ring and Ball" test (Figure). (a) Diagram of Apparatus at Beginning of Test (b
A clay layer 5 m thick has double drainage. It was consolidated under a load of 127.5 kN/m2. The load is enhanced to 197.5 kN/m 2 . The coefficient of volume compressibility is 5.7
Define Pavement Design - Transportation 1. Asphalt surface a. Estimate Design Traffic b. Determine the Structural Number (SN) for the given traffic, roadway, and soil cha
types of windows
Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo
An oven-dry soil sample of volume 225 cm3 weighs 3.90 N. If the grain specific gravity is 2.72, determine the void-ratio and shrinkage limit. What will be the water content which w
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd