Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Structural engg, how static and dynamic frames are works?

how static and dynamic frames are works?

Regression, I would like to ask what is regression and its function?

I would like to ask what is regression and its function?

Calculate the amount of concrete - construction management, An electrical c...

An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank

Aaaaaa, what is the reciprocal ranging ? with neat sketch ?

what is the reciprocal ranging ? with neat sketch ?

Describe the terms inside clearance and outside clearance, a) Explain with ...

a) Explain with a neat sketch how will you carry out the wash boring method of soil exploration. What are its merits and demerits? b) Describe the terms 'inside clearance' and '

Characteristic strength of concrete, In addition to its own weight, the bea...

In addition to its own weight, the beam in Figure is to carry a uniformly distributed live load of 12 kN/m. Figure 1 also shows the cross-sectional details of the beam. Design a

Construct the shear force and bending moment diagrams, A Beam A B 12 meter ...

A Beam A B 12 meter long rests on supports 9 meter apart the right hand end over hanging the supports by 1 m and the left hand end by 2 m . The beam carries a uniformity distribute

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd