Contractor to continue concreting works, Civil Engineering

Assignment Help:

Question
If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works?

Answer
This is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue.

The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers.
This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test.

The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-

(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures.

(ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?

 


Related Discussions:- Contractor to continue concreting works

Ceramic tiles for construction material, Q. Ceramic Tiles for construction ...

Q. Ceramic Tiles for construction material? For public toilet bath rooms , kitchen etc to ensure cleanliness floors should be provided with ceramic tile. For water points on

Physics, write short note on terrestrial telescope

write short note on terrestrial telescope

Strenght of meterials 2, Difference between direct and bending stress diagr...

Difference between direct and bending stress diagrams

What is diversion tunnel in a dam, When a dam is to be built, a diversion t...

When a dam is to be built, a diversion tunnel is usually bored by solid rock next to the dam site to bypass the dam construction site. The dam is built while the river flows by the

Specify the various methods of soil exploration, Specify the various method...

Specify the various methods of soil exploration and mention the circumstances under which each is best suited. What do you mean by undisturbed sample? Define with a neat sketch

Sewer manhole, minimun difference in level of inlet and oulet pipe level in...

minimun difference in level of inlet and oulet pipe level invert in manhole

Uses of bricks, Uses of Bricks In the following civil works Bricks are ...

Uses of Bricks In the following civil works Bricks are used: a. in building blocks. b. For lining of ovens, chimneys and furnaces. c. As aggregates in providing water

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd