Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Define Pressure on an Inclined Plane Similar to a vertical plane, fluid pressure increases linearly with increasing depth. The average pressure on an inclined plane occurs at t
How to calculate the centroid of parabola?
Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2
In case of simple bending after simply supported beam, derive that M/I = s /y = E/R.
(i) A dry soil has a void ratio of 0.65 and its grain exact gravity is = 2.80. What is its unit weight? (ii) Water is added to the sample so that its degree of saturation is 60%
an opening of width 3m and height 2.7 in a brick masonary has to be provided with door cum window. plan, elevation, section and 2 joining details
Question In linking fenders to pier organizations, would single lock nuts or double lock nuts be used? Answer In pier structures connection offenders to piers is a
define unit
Question Why do BS8007 specify permissible crack width of water retaining structure as 0.2mm for severe, extremely severe exposure? Answer For break width less than
Q. Show the Grout curtain around excavation? When excavation work is performed in grounds with highly permeable soils, other than installation of well points to lower down grou
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd