Continuous prestressed concrete beam design , Civil Engineering

Assignment Help:

Assignment:-Continuous Prestressed Concrete Beam Design

A cast in-place 3-span prestressed concrete T-beam is to be designed. The T-beam concsists of an 8-in thick reinforced concrete deck slab integrally cast onto rectangular girders that have webs 48-in deep by 15-in wide. The spans are to be 90,, 120, 90 ft.
Adopt the following properties:
-f’c = 6ksi
-fpu=270ksi, dt=0.5in
-k=0.005/ft, mu=0.2. Up to 19 tendons can be bundled into a 3.0-in dia. duct.

Design:

1.    One T-girder to balance self-weight, where the slab is 8-ft wide.
2.    Use end-to end continuous prestress, with a load balancing approach. Attempt to minimize the tendon force by maximizing the drape. Balance as closely as practicable the dead load only by assuming 15% time-dependent losses.
3.    Check stresses and losses. For this, draw stress-blocks at critical locations of maximum positive and negative moments in each soan.
4.    Determine the ultimate moment capacity of the designed section at key positive negative and positive moment locations.

5.    Determine the maximum uniformly distributed live load that can be carried over the span based on achieving U=1.2D + 1.6L

-Service load conditions. For this check allowable stresses, including temperature stress effects as per AAASHTO and also deflection limits (L/800).
-Ultimate load conditions without moment-redistributuion (an elastic solution).
-Ultimate load with moment redistribution permitted. Note you may need to add additional mild steel at the interior support regions to improve section ductility.

6. Based on the resulting shear force distribution, design the shear reinforcement.


Related Discussions:- Continuous prestressed concrete beam design

Calculate the number of paths and critical paths, Calculate the Number of P...

Calculate the Number of Paths, Number of Critical Paths and Project Duration For the project network shown, the total number of paths through the network; number of critical pa

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Factor that affect the bearing capacity of a shallow footing, State the var...

State the various factors that affect the bearing capacity of a shallow footing. Write short note critical notes on settlement of foundations. How do you ascertain whether a fou

How we can check caisson is stable or not, A box caisson, 10 m high, is 18 ...

A box caisson, 10 m high, is 18 m × 9 m at the base. The weight of the caisson is 9 MN and its centre of gravity is 4.2 m above the base. Check whether the Caisson is stable. If

Solis mensuration, the two side are 17 cm and 28 cm long. and the lenght of...

the two side are 17 cm and 28 cm long. and the lenght of the drawn to the third side is equal to 19.5cm. find tghe distance from an endpoint of this medianto the longest s8ide

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Graduate, fabrication methods of ironmongery

fabrication methods of ironmongery

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd