Consolidation settlement, Civil Engineering

Assignment Help:

The integration of strain over the depth is settlement. The method of producing the settlement is non-recoverable when the intensity of stress is removed. Hence, a permanent reduction in void ratio has resulted in the soil media.

Strain in all coarse grained and partially saturated fine grained soils occurs very soon after the application of the stress. Application of stress to saturated fine-grained soils produces strains that are time dependent. The resulting settlements are also time-dependent and are called Consolidation Settlements.

The time needed for consolidation settlements to take place depends on the dissipation rak of excess pore pressure due to external loading.?he tilt in the Leaning Tower of Pisa is at least partly due to differential consolidation settlements that have been ongoing over the last 700 years.


Related Discussions:- Consolidation settlement

Survey, what is road survey ?

what is road survey ?

Cement, manufacture of cement by dry process

manufacture of cement by dry process

Define the term - cracking load and proof stress, Define the term - Crackin...

Define the term - Cracking Load and Proof Stress Cracking Load The load on the structural member at the time of the initiation of first visible crack in concrete is know

Determine the preliminary settlement analysis, Preliminary settlement analy...

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stra

Calculate the fuel consumed, A 160-HP Diesel engine (peak fuel consumption ...

A 160-HP Diesel engine (peak fuel consumption = 0.04-gal/HP-hr) hydraulic excavator operates on a cycle time of 20 seconds during a 50-min/hr.  During the filling of the bucket cyc

Strength of Materials , Need to know about compressive strength test and te...

Need to know about compressive strength test and tensile strength test of cement

Explain total dynamic head (tdh), Total Dynamic Head: (TDH) y-axis plo...

Total Dynamic Head: (TDH) y-axis plot point related to each x-axis flow rate along the system curve plot. TDH = h a = TSH + h f + v 2 /2g       v 2 / 2g usually small

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd