Computer the schedule variance schedule performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Computer the schedule variance schedule performance index

Make a scope statement for a coffee shop, Prepare a scope statement for a c...

Prepare a scope statement for a coffee shop. Remember to be tangible, measurable, and specific. The components: Project Objective, Deliverables, Milestones, Technical Requirements,

Explain city water supply system, The network in figure below shows the pip...

The network in figure below shows the pipeline transportation system for treated water from the treatment plant (node 1) to a city water supply system (node 14). The arc capacities

Find the critical path, Using the information given in the following table:...

Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration. Activities Precedes Duration Start a,b,c - a d 5 d f 6

What is the annual carrying rate, ABC Aircraft uses 3,000 drill bits annual...

ABC Aircraft uses 3,000 drill bits annually. Each drill bit costs $50 and each order ABC places costs $25. The annual carrying rate is 40% of unit cost. ABC has contracted with the

Explain business model and strategies changed overtime, 1. Why has Southwes...

1. Why has Southwest's business model and strategies changed overtime? 2. In what ways is Southwest Trying to improve its competitive advantage in 2011? 3. Give examples of a

Explain factors contributing to competitive rivalry include, Factors contri...

Factors contributing to competitive rivalry include A) The corporate attitudes toward marketing strategies B) Nature of the product and homogeneity of market C) The suppor

Explain planning of the project, You have been appointed as a project manag...

You have been appointed as a project manager for a high dollar project for the private sector and you have been asked by your boss to identify the stakeholder groups and the indivi

How break even analysis helps in solving the problems, How Break even Analy...

How Break even Analysis helps in solving the problems. Break even Analysis assists solving the problems of following:  (a) What volume of sales will be necessary to cover?

Explain major components of information management, Discuss the five (5) ma...

Discuss the five (5) major components of information management / information technology (IM / IT) governance with a focus on how they will collectively improve the quality of heal

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd