Compute the value of the policy variable, Operation Management

Assignment Help:

You are asked to analyze the kanban system of LeWin, a French manufacturer of gaming devices. One of the workstations feeding the assembly line produces part M670N. The daily demand for M670N is 1,800 units. The average processing time per unit is 0.003 day. LeWin is records show that the average container spends 1.05 days waiting at the feeder workstation. The container for M670N can hold 300 units. Twelve containers are authorized for the part. Recall that p- is the average processing time per container, not per individual part.

a. Find the value of the policy variable, a, that expresses the amount of implied safety stock in this system.

b. Use the implied value of a from part (a) to determine the required reduction in waiting time if one container was removed. Assume that all other parameters remain constant.


Related Discussions:- Compute the value of the policy variable

Define constraint its associated binary decision variables, Consider the fo...

Consider the following constraint and its associated binary decision variables: XA + XB + XC = 2. This constraint is an example of a mutually exclusive constraint.

Explain work-in-process and raw materials are needed, The Bawl Corporation ...

The Bawl Corporation supplies alloy ball bearings to auto manufacturers in Detroit. Because of its specialized manufacturing process, considerable work-in-process and raw materials

Describe why variable pay-for-performance plans, Discuss why variable pay-f...

Discuss why variable pay-for-performance plans have become popular and what elements are needed to make them successful.

Compute the operating characteristics of interest, An urn contains nine whi...

An urn contains nine white balls and 11 black balls. A ball is drawn and replaced. If the ball is white your opponent pays you 25 cents. If it is black you pay him 25 cents. You ha

Calculate the standard time for the job, An  industrial  engineer  has obta...

An  industrial  engineer  has obtained the  following data  in connection  with a  time  study on  the lines  of the Hawthorne  studies  taking  four different  elements  and five

.Operational Plan and Budget, Can you create a Operational Plan and Budget ...

Can you create a Operational Plan and Budget if I provide instruction. Also need budget plan to be placed in excel

Balanced scorecard framework - theory of constraints, 1. Can the balanced s...

1. Can the balanced scorecard framework also incorporate benchmarking and the theory of constraints?  2. What's a constraint?  3. Consider your own goals and the resources an

Explain what should johnson estimate time and parts costs, Johnson Industri...

Johnson Industries received a contract to develop and produce four high intensity long distance receiver/transmitters for cellular telephones. The first took 2000 labour hours, and

Consider the influence of changing business models, 1 Consider a local tele...

1 Consider a local telephone company offering triple-play (TV, Internet, and Phone) services to residential customers in a single metropolitan area. What might be the reasons that

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd