Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Describe the role that organizational learning, Explain the role that organ...

Explain the role that organizational learning and creativity play in helping managers to improve their decisions.

Calculate the total cost of ordering and carrying clay pots, 1. Garden Vari...

1. Garden Variety Flower Shop uses 1000 clay pots a month. The pots are purchased at $3 each. Annual carrying costs per pot are estimated to be 25% of cost, and ordering costs are

Work study, link between work study and value analysis?

link between work study and value analysis?

How the job of industrial manager becomes more difficult, How the job of in...

How the job of industrial manager becomes more difficult? However, the job of industrial Manager becomes still more difficult because of: (i) Change in technology; (ii) C

Location planning and analysis: problems, A manufacturing company preparing...

A manufacturing company preparing to build a plant is considering three potential locations for it.

LINE BALANCING, WHAT DO YOU UNDERSTAND BY LINE BALANCING

WHAT DO YOU UNDERSTAND BY LINE BALANCING

Products produced by project, 1. Identify products which you would expect t...

1. Identify products which you would expect to be produced by each of the following configurations: project, job shop, and batch and continuous. Answer: Many possible answers:

Line balacing, what happens if line balancing does not exist

what happens if line balancing does not exist

Explain what are the coordinates of the central location, A small rural cou...

A small rural county has experienced unprecedented growth over the past 6 years, and as a result, the local school district built the new 500-student North Park Elementary School.

Case Study, #quBloomsday Outfitters produces T-shirts for road races. They ...

#quBloomsday Outfitters produces T-shirts for road races. They need to acquire some new stamping machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd