Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Make a product structure for heather, Operations Mgmt. 10th edition Hiezer/...

Operations Mgmt. 10th edition Hiezer/Render Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, whic

Relationship that exist among companies and profit motives, Explain the rel...

Explain the relationship that exist between companies, profit motives, competition and private property.

Explain the three steps in completing a job analysis, As an entrepreneur, h...

As an entrepreneur, how would you go about doing a job analysis for the first employee you are going to hire in your new business? What are the three steps in completing a job anal

Explain primary responsibility for productivity, Productivity should be a c...

Productivity should be a concern of every business organization. a. How is productivity defined? b. How are productivity measures used? c. What part of the organization has primary

Master production scheduling, Master Production Scheduling The master s...

Master Production Scheduling The master schedule ( or master production schedule of MPS) sets the quantity of each end item (finished product) to be completed in each time peri

Hard, Ask quesThe Delicious Apple Company has orchards in Red City, Golden,...

Ask quesThe Delicious Apple Company has orchards in Red City, Golden, and Macville Estimated amounts of apples to be available from the three orchards are the following: Red City

Find required return on similar risk bonds, Bond validation-Semi-annual int...

Bond validation-Semi-annual interest. Find the value of a bond maturing in 6yrs. with a $1,000 par value and a coupon interest rate of 12% (6% paid semi-annually) if the required r

A main outcome of electronic data interchange, A main outcome of electronic...

A main outcome of electronic data interchange (EDI) is   To save paperwork by using structured electronically transmitted data.

What are advantages of using multiple sourcing strategies, What are the adv...

What are the advantages of using multiple sourcing strategies? Advantages of using multiple sourcing: a. May assist negotiate and drive down prices while more suppliers e

Explain in-depth the contrast and comparison, Need to describe in-depth the...

Need to describe in-depth the contrast and comparison of instrumental versus intrinsic within the business ethics development.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd