Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Explain the processing times for the five job, Suppose SPT rule is being us...

Suppose SPT rule is being used in a "dynamic" scheduling problem. There are five jobs A,B,C,D, and E ready to be processed at the present time. The processing times for the five jo

Determine the feasible solution of transportation problem, A firm owns faci...

A firm owns facilities at six places. It has manufacturing plants at places A B and C with daily production of 50, 40 and 60 units respectively. At points E, E and F it has three w

Why company declines to correct the flaw, Scenario 2: A supervisor discover...

Scenario 2: A supervisor discovers a design flaw, which she believes is a safety hazard. She informs the company through the proper channels. The company declines to correct the fl

Aggregation or composition, You are to produce a report on the 'Animal Farm...

You are to produce a report on the 'Animal Farm' Case Study that identifies the significant ambiguities, records your assumptions, and explains your design decisions (with your UML

Sffdfd, Why mary parker follett ideas tended to be popular

Why mary parker follett ideas tended to be popular

Market forecasting methods for predicting demand levels, What are the marke...

What are the market forecasting methods for predicting demand levels? Market forecasting methods for predicting demand levels: a. Survey or sample of buyer’s intentions pr

Explain small proportion of unionized employees, Why would it be harder for...

Why would it be harder for heavily unionized organizations to settle on their bargaining targets than for those with a small proportion of unionized employees?

Explain mixed strategies in production planning, Distinguish between pure a...

Distinguish between pure and mixed strategies in production planning. Provide examples of each strategy.

Explain hertzberg''s dual factor theory of motivation, According to Hertzbe...

According to Hertzberg's dual factor theory of motivation, one set of factors is known as Hygiene factors.

Influence of the product life cycle - operation strategy, Influence of the ...

Influence of the Product Life Cycle - Operation Strategy The influence of the product life cycle on operational performance objectives are: The life cycle curve shown in th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd