Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Approaches to expanding long term capacity, Approaches to Expanding long te...

Approaches to Expanding long term Capacity There  are two  major  approaches to  expanding  the long  term capacity  viz. All at once and Building  a capacity  increm

Case Study, After working for 30 years, Ramjee Somjee Dutt opted for VRS an...

After working for 30 years, Ramjee Somjee Dutt opted for VRS and started a courier company and did very well in the first four years. He was now looking for expansion of his busine

Line Balancing, What do you understand by “line balancing”? What happens if...

What do you understand by “line balancing”? What happens if balance doesn’t exist?.

Visual basic 2010 problems, Are the practice questions at the end of the ch...

Are the practice questions at the end of the chapters in starting out with Visual Basic 2010 5th edition a good representation of the questions in the Test Bank?

Manager case, In the table given below the Distribution Manager is expected...

In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what woul

Describe when stakeholder identification occurs, Explain when stakeholder i...

Explain when stakeholder identification occurs and explain the importance of stakeholder analysis

Explain the differences unsecured credit and secured credit, Compare and co...

Compare and contract unsecured credit and secured credit, and explain the key differences. Provide an example for each.

We want to consider some accounting ideas, We need to consider some account...

We need to consider some accounting ideas in order to cover this weeks Objective # 3. So in that regard, for your own business, which method of accounting would you use, the "accru

Explain the challenges you foresee in using the mbti, Describe the challeng...

Describe the challenges you foresee in using the MBTI instrument or Keirsey Temperament Sorter in a project management situation and how you would address them. Speculate the accep

Concept of a productivity boundary and operating efficiency, 1. Porter (199...

1. Porter (1996) attempts to resolve the issue of Skinner's quandary with trade-offs by introducing the concept of a productivity boundary and operating efficiencies. Explain where

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd