Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Is focused factory concept applicable in service sector, Is the 'focused fa...

Is the 'focused factory' concept described by Skinner applicable in the service sector? Answer:  Yes, think of Schmenner's service-process matrix and the lower quadrant entitled

Explain as the administrative manager in a law office, As the administrativ...

As the administrative manager in a law office, you have been asked to develop a system for evaluating the productivity of the 15 lawyers in the office. What difficulties are you go

Situational Leadership Theory, Describe possible gaps you observe within Si...

Describe possible gaps you observe within Situational Leadership Theory. What strategies or adjustments in your own behavior, thinking, or worldview might you consider or employ to

Describe what was the labor productivity, Last week employees at Renee's Fa...

Last week employees at Renee's Fashions worked 360 hours to produce 128 garments. Of these, 8 were seconds which were sold at the outlet store for $90 each. The remaining 120 garme

Define criteria that considered to perform the project, One of the most imp...

One of the most important aspects of managing risk for a project is to accurately define the size of the project. Determine the criteria that must be considered to perform the proj

Dont know, Q. A textile manufacturer is interested in optimally determined...

Q. A textile manufacturer is interested in optimally determined inventories for cutting operations for a children’s product line. The production manager would like to establish th

Describe difference between significance and meaningfulness, What is the di...

What is the difference between significance and meaningfulness? Which one is more important to experimental results and why do you think so?

Explain develop an aggregate production plan, ABC Company, a manufacturer o...

ABC Company, a manufacturer of roofing supplies, has developed monthly forecasts for roofing tiles. The forecasted demand and the expected production days for months March to Augus

Explain comparable worth, In detail, express your opinion regarding the "Co...

In detail, express your opinion regarding the "Comparable Worth" issue.

Explain must decide between two different forecasting tech, An analyst must...

An analyst must decide between two different forecasting techniques for weekly sales of roller blades: a linear trend equation and the naive approach. The linear trend equation is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd