Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Supplier relationships in a supply network, Supplier relationships in a sup...

Supplier relationships in a supply network are categorised in which ways:- Single, multiple, delegated and parallel

Explain the managerial process, The Managerial Process text. Given the proj...

The Managerial Process text. Given the project network provided, compute the early, late, and slack times for the project. Share your calculations and explain how you came up with

Explain if you are picketing your employer for higher wages, If you are pic...

If you are picketing your employer for higher wages and your neighbour is hired to replace you only while you march, the Mackay Doctrine says that, when the strike is over, your ne

Explain process as it relates to risk management, We have now covered the s...

We have now covered the steps of the Active Threat and Opportunity Management (ATOM) process. What is your opinion of the process as it relates to risk management? What are its ben

Functions of work measurement, Functions of work Measurement: 1.      ...

Functions of work Measurement: 1.       To analyze  the operations  and to evaluate them  in terms  of time  from the  point  of view  of  controlling  the activity. 2.

Explain use the marketing research, CASE STUDY Jerry Smith is thinking abou...

CASE STUDY Jerry Smith is thinking about opening a bicycle shop in his hometown. Jerry loves to take his own bike on 50-mile trips with his friends, but he believes that any small

Explain moving averages and exponential smoothing, 1. What is quality funct...

1. What is quality function deployment (QFD)? Provide an example of how it can be used. 2. List the five advantages of successful implementation of group technology. 3. Descr

What seasonal relatives would explain this situation, The manager of a fash...

The manager of a fashionable restaurant open Wednesday through Saturday says that the restaurant does about 31 percent of its business on Friday night, 26 percent on Saturday night

Logistics, Ask question #Minimum 100 words acceptedTopic 2: Logistics Logi...

Ask question #Minimum 100 words acceptedTopic 2: Logistics Logistics is the management of the flow of goods, information and other resources, including energy and people, between

Explain business model and strategies changed overtime, 1. Why has Southwes...

1. Why has Southwest's business model and strategies changed overtime? 2. In what ways is Southwest Trying to improve its competitive advantage in 2011? 3. Give examples of a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd