Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Explain about the managing inventory, Q. Explain about the managing invento...

Q. Explain about the managing inventory. Managing inventory (stock): Retailers buy stock or inventory and sell that to customers; that manufacturers buy raw material and ele

Explain the network is overloaded, Information asymmetry exists when - T...

Information asymmetry exists when - The network is overloaded - Sellers and buyers have the same information - One party in a transaction had more important information th

Explain adequately staff the office, Recommend one specific way that Thomas...

Recommend one specific way that Thomas can adequately staff the office in light of the many problems he has already experienced. Be sure to keep in mind the cultural issues that pl

Explain capital expense, Eric Johnson (using data from Problem 1.6) determi...

Eric Johnson (using data from Problem 1.6) determines his costs to be as follows: • Labor: $10 per hour • Resin: $5 per pound • Capital expense: 1% per month of investment • Energy

Explain production department says that to achieve, The sales department te...

The sales department tells management that they can increase revenue by 20 percent by increasing sales 20 percent, but the production department says that to achieve that number of

Explain lead time, Explain Lead Time. Lead Time : Lead Time is the tim...

Explain Lead Time. Lead Time : Lead Time is the time that takes the stock to reach from Re-order point to minimum stock level. This may be also defined as the time as elapses

Flow process chart - process design, 1. Examine the flow process chart in t...

1. Examine the flow process chart in the figure and try to develop an improved method for the future, taking advantage of the technologies becoming available. Answer: There are

Calculate the path mean and network diagram, For the following data: ...

For the following data:   Time (in Days)   Activity Immediate Predecessor Optimistic Most Likely

Depict serializability graphs, Draw serializability (precedence) graphs for...

Draw serializability (precedence) graphs for the following schedules and state whether each schedule is (conflict) serializable. For each serializable schedule, determine the equiv

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd