Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Describe customer service level for an inventory system, Discuss customer s...

Discuss customer service level for an inventory system within the context of quality management

Explain how much of an impact does maturity, 1. How much of an impact does ...

1. How much of an impact does "maturity" level of the industry or company have on strategy? 2. Can you be innovative in a mature industry? 3. Can you be conservative in an in

When manager focus the progress of an affirmative action, when manager moni...

when manager monitors the progress of an affirmative action program to advance minorities within the corporation; reviewing progress on changing in staff attitude; calls a special

Define what can we learned about business and ethics, Details what can we l...

Details what can we learned about business, ethics, and society.

Appropriate control limits for the data, A quality team at Milburn Textiles...

A quality team at Milburn Textiles has been charged with setting up control charts to monitor a key dyeing process that has been improved and now stable.  The ideal temperature for

Airbus, 1)?An analysis of type of operations carried out and operating proc...

1)?An analysis of type of operations carried out and operating processes (i.e., project, batch, mass, professional service, service shop,?mass service, etc.) 2)?An identification

Explain individual incentives used by organizations, Give examples of indiv...

Give examples of individual incentives used by organizations, why these are or are not successful?

What is cutting stock problem, Consider the cutting stock problem that aris...

Consider the cutting stock problem that arises when a company manufactures sheets of standard width 100 and has commitments to supply 40 sections of width 40, 60 sections of width

Explain ethical and conflict of interest issues, Public corporations are le...

Public corporations are led by CEOs and other upper-echelon leaders who, in turn report to shareholders and board of directors (BODs). Interestingly, even though the board overseas

Public Administration, Is the city management form of government better tha...

Is the city management form of government better than the mayor and council form of government?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd