Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

Organization might choose an organizational development, How would you expl...

How would you explain the contracting process to someone who had never heard of organizational development, why is this important. Describe how an organization might select an org

Explain sources of manpower recruitment, Explain Sources of Manpower Recrui...

Explain Sources of Manpower Recruitment. Sources of Manpower Recruitment:  (i) From in the Company The sources of manpower recruitment for any company are as following

Explain how globalization is affecting the political, Discuss how globaliza...

Discuss how globalization is affecting the political, legal, and economic forces impacting todays business environment?

Technology which encourages user contributions, Technology which encourages...

Technology which encourages user contributions and interactivity is known as Web 2.0.

Find out the nash equilibrium, In a project, executive and boss are working...

In a project, executive and boss are working together. The executive can be sincere  or insincere, and the Boss can either reward or penalize. The executive gets no advantage for b

Explain hospital is to be built to provide medical, Suppose a new hospital ...

Suppose a new hospital is to be built to provide medical and healthcare service to 5 towns coordinate (5,6), (1,3), (13,7),(11,2) and (8,1) on map, the transportation network is re

Explain fatigue and delay, a. You are chartered to set a time standard for ...

a. You are chartered to set a time standard for a worker assembling 96 piece jigsaw puzzles. The following times have been collected from five different operators with one observat

Explain why do you think unionism is on the wane, Why do you think unionism...

Why do you think unionism is on the wane? Do you think unions will ever regain their membership strength and political influence? What impact might this decline have on the America

Production, Production Production is any process or  procedure develope...

Production Production is any process or  procedure developed to transform a set  of input elements  such as men,  materials capital, information and energy into a specified set

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd