Compute the schedule variance and cost performance index, Operation Management

Assignment Help:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Related Discussions:- Compute the schedule variance and cost performance index

The budget projections for the cost of computer hardware, The final element...

The final element of the information systems plan specifies resources required to carry it out. The capital budget should include projections for the cost of computer hardware, net

Explain a risk of disciplining employees, A risk of disciplining employees ...

A risk of disciplining employees is that some employees retaliate. To avoid that risk, what organizational policies might encourage low-performing employees to leave while encourag

Contents of an operations strategy , Contents of an Operations Strategy  ...

Contents of an Operations Strategy  The contents of an operations strategy is the policies, plans, performance targets which the organisation wishes to achieve. To determine

Merits of continuous or flow production, Merits of Continuous or Flow Produ...

Merits of Continuous or Flow Production 1.The direct labor content will be reduced since the comprehensive pre planning which is necessary will often produce economies in time.

Determine a pareto analysis of the errors, 1. Construct and inerpret ...

1. Construct and inerpret a control chart for the packing slip data. 2. Construct a Pareto analysis of the errors. 3. What information might a separate char

Which kind of portable computer will meet everyones needs, Your organizatio...

Your organization plans to acquire 250 new portable computers. The finance vice president has asked you to lead a project team assigned to define users' computer hardware needs and

Explain individual employees and improve cooperation, How can a pay for per...

How can a pay for performance system increase motivation of individual employees and improve cooperation?

Explain what purpose does the project charter serve, a. What purpose does t...

a. What purpose does the Project Charter serve? b. What are the main components or sections of the Project Charter? c. What purpose does the Project Definition Document serve

Layout, disconnected or functional layout

disconnected or functional layout

Explain how the employees effectively execute strategy, Select a company th...

Select a company that you believe uses employees to achieve a competitive advantage. Discuss how the employees effectively execute the strategy and how the company can sustain this

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd