Compute the experience curve, Business Economics

Assignment Help:

Compute the experience curve:

Chuck Raverty, General Manager of Carey Builders, a Baltimoreconstruction company is considering bidding for a construction contract on the new Corey Business School (CBS) building at Hopekeen State University.  Construction is scheduled to start in late summer 2013.  Chuck expects to compete for this contract with Wharton Construction, an out-of-state rival.  There is also a chance that the Smith Corporation, a construction company based in Silver Springs, MD will bid on the contract.

Carey has completed four such university building projects so far and is working currently on a similar project that will be completed before the CBS project starts in 2013.  Thus, Carey will have the experience of having completed five projects when it starts the CBS project, if it wins the contract. The latest completed project (i.e., their fourth) cost Carey a total of $34.3 million, of which $25.8 million was raw material cost.  Also, an internal cost analysis has shown that Carey's second project (completed in 2002) cost a total of $30.0 million, of which the raw material cost was $20.0 million.  Since all the projects that Carey has worked on are structurally similar, Chuck expects this cost dynamic to hold for his future value-added costs and believes that this past cost information may be useful for forecasting purposes.

Hutt and Speh (HS) Corporation, a leading building supplies company has informally agreed to supply all the raw material for the CBS project for $43.9 million. Chuck knows that the costs of gearing up to submit a bid on the CU project would involve incrementalfixed costs of $75,000, nonrefundable contract guarantee fees to HS Corporation amounting to 1% of the contracted raw material cost, and setup costs equal to 2% of the project's value-added costs. Thsee "bid development costs" are not recoverable (and must be written off) if Chuck fails to win the bid.  Hence, Chuck wants to include these costs in figuring his bid.

Phil Ferrari, Chuck's former graduate school buddy is the Senior Contract Manager for Hopekeen University and reminded Chuck that because of priorities favoring in-state awards, Carey has an advantage if it bids on the CBS building. Chuck thought this was encouraging.  He assesses that if bidding only against Wharton, Carey's probabilities of winning the contract at bid prices involving specific markup levels on forecasted total costs are (no intermediate markups, e.g., 7% or 18%, are allowed):

            Markup:                                                            0%       5%       10%      15%      20%      25%

            Probability of contract award to Carey                  1.0        0.8        0.7        0.4        0.3        0.0

A.  Compute the experience curve implied in Carey's past project costs.

B.  Compute what Carey should forecast for value-added costs for the CBS project.

C.Compute Carey' total ($) cost for the CBS project and (for each bid markup level) the associated gross ($) profit margin if it wins the CBS contract.  (Assume that HS Corporation will meet its raw material price commitment)

D. What $ amount should Carey bid for the project (assume Chuckmaximizes expected profit)?

E. Chuck now learns that Smith Builders is also certain to bid on the LSB project.  Carey will then lose the in-state advantage and Chuck's revised estimates of the probability that Carey will win theCBS contract are:

 

            Markup:                                                            0%       5%       10%      15%      20%

            Probability of contract award to Carey                  1.0        0.7        0.4        0.3        0.0

What should Carey bid for the CBS project given this information (recall that Chuck maximizes expected profit)?

F.  How will your answer change if Chuck felt that there was only a 50% probability that South State would bid on the project?  Show your computations and briefly explain your answer.

G.  Chuck wonders if maximizing expected profits is a good approach to making these decisions and seeks your advice on whether to bid higher or lower than the expected profit maximizing bid.  What advice would you give him?

H.  Chucklearns that Hopekeen Statepalns on building an executive education facility in 2015 and that the CBS contract winner will have an inside track in the bidding.  Should this information affect his bid on the CBS project?  Why or why not?


Related Discussions:- Compute the experience curve

Causes of market failures, Question: (a) Discuss the conditions necessa...

Question: (a) Discuss the conditions necessary to achieve Pareto Efficiency. (b) Competitive markets are generally assumed to lead to a Pareto optimal allocation of resource

NPV, How do I calculate NPV with benefits and costs?

How do I calculate NPV with benefits and costs?

Prepare an interview plan for the post of business analyst, Prepare an inte...

Prepare an interview plan for the post of Business Analyst in your team. a. Welcome then introductions/administrative objectives/agenda. Found rapport. b. Ask questions conc

What do you understand by the term "anthropometry"?, QUESTION 1 (a) Wha...

QUESTION 1 (a) What, according to you, are the ergonomic problems associated with the use of visual display units? Describe the measures which can be taken to eliminate these p

How do economists differ from accountants, How do economists differ from ac...

How do economists differ from accountants in the use of the term profit ? Definition of rev and accounting costs Explanation/outline of opportunity costs, for example

Traditional - modern sectors and rural-urban migration, What are the tradit...

What are the traditional, modern sectors and rural-urban migration? Rural-urban migration: Rural-urban migration is the movement of labour through the countryside to cities

Defines the stages of e-government development, QUESTION ‘To assist pol...

QUESTION ‘To assist policy makers discern e-Government initiatives in relation to their responsibility vis-à-vis other governmental issues, it is critical that the Governmen

What are the predictions of dependency theory, What are the predictions of ...

What are the predictions of dependency theory? The predictions of dependency theory: • DCs exploit LDCs (Less Developed Countries) by extracting their surplus value. Surplu

Price elasticity of demand, QUESTION 1 (a) Explain the relationship bet...

QUESTION 1 (a) Explain the relationship between scarcity, choice and opportunity cost. (b) How is choice about the use of scarce resources made in a market economy? QUES

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd