Compute efficiency of transformer in power factor lagging, Electrical Engineering

Assignment Help:

Q. A 10-kVA, 200:400-V, single-phase transformer gave these test results:

• Open-circuit test (LVwinding supplied): 200V, 3.2 A, 450 W

• Short-circuit test (HV winding supplied): 38 V, 25 A, 600 W

Compute the efficiency when the transformer delivers half its rated kVA at 0.85 power factor lagging.


Related Discussions:- Compute efficiency of transformer in power factor lagging

Cmos processes, CMOS processes: The low-performance "lateral" bipolar ...

CMOS processes: The low-performance "lateral" bipolar transistors occasionally employed in CMOS processes are sometimes designed symmetrically, i.e., with no distinction betwe

Perfect gases avogadro''s hypothesis, Equal volumes of all gases contain th...

Equal volumes of all gases contain the samenumber of molecules when the volumes are measured at the same p and T. Therefore for a given volume at the same p and T, with the same

What do you mean by instrument transformers, Q. What do you mean by Instrum...

Q. What do you mean by Instrument transformers? These are generally of two types, potential transformers (PTs) and current transformers (CTs). They are designed in such a way t

What is a coprocessor, What is a coprocessor? It is a specially designe...

What is a coprocessor? It is a specially designed microprocessor which take care of mathematical calculations including integer and floating point data .it is intended to work

Ac machines, AC Machines: We have learnt the fundamental concepts of t...

AC Machines: We have learnt the fundamental concepts of the transformer, induction motors and special type fractional kilowatt (kW) machines. In the section of transformer you

Explain the discovery of neutron. mention its properties, Explain the disco...

Explain the discovery of neutron. Mention its properties. Discovery of Neutron: The existence of neutron was first predicted by Rutherford in the year 1920. But it was discov

Survey methods and analysis - power supply, Survey Methods and Analysis - P...

Survey Methods and Analysis - Power Supply There are two major methods of gathering information from customers: qualitative and quantitative.  Quantitative Rese

Control system, I need some help for doing the assignment

I need some help for doing the assignment

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd