Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Define why it is vital to understand the impact of culture, Contrast the dy...

Contrast the dynamics between dominant cultures and subcultures either in a work setting or in society. Explain why it is important to understand the impact of culture

Explain interest and estimate its usefulness to the project, Office Suite p...

Office Suite programs identify the resource that caught your interest and estimate its usefulness to the project management profession.

Auto Parts store manager, Needs to know how to run office affairs and to ha...

Needs to know how to run office affairs and to handle the paperwork of all customers as they come in each day, and take care of the work load of the employees as to setting up the

Explain what changes in culture are needed at the plaza inn, 1. How could t...

1. How could the Plaza Inn develop a collaborative strategy? Develop a specific plan. 2. How could technology help solve the problems at the front desk? Explain what you propose

Explain what is nominal damage, What is the difference between compensatory...

What is the difference between compensatory damages and consequential damages? Provide at least one relevant example of each that was not included in your textbook. What is nominal

Human Resource, 1. What in your view are the central human resources issues...

1. What in your view are the central human resources issues involved in this case?

Logistics., explain the role of product characteristics on the logistics de...

explain the role of product characteristics on the logistics decision

Primary elements of each of the three kinds of risk control, What are the p...

What are the primary elements of each of the three types of risk control? Assume you are in a hazard hunt; list a few factors in your job that may contribute to a hazard and how li

Explain what is the stocks required rate of return, GD inc has preferred st...

GD inc has preferred stock outstanding that pays a dividend of $5 at the end of each year. The preferred sells for $50 a share. What is the stocks required rate of return? Show wor

Explain what are the advantages of adopting this technology, An accounts re...

An accounts receivable manager processes 200 checks per day with an average process time of 15 working days. What is the average number of accounts receivable checks being processe

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd