Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain what challenges or barriers may happen, You are part of a group of ...

You are part of a group of newly hired team superintendents with Riordan Manufacturing. Your group was hired to lead new teams and begin production of the newly designed CardiCare

Compute demand for a product, Historical demand for a product is:January DE...

Historical demand for a product is:January DEMAND 12 / February DEMAND 11/March DEMAND15/ April DEMAND 12/ May DEMAND 16 /June DEMAND 15 a. Using a weighted moving average with

Economics, Economics issues and operation research solutions

Economics issues and operation research solutions

How do we link strategic and operational change, 1. How do we link strategi...

1. How do we link strategic and operational change?  Answer: Hambrick and Cannella present a 5-step approach:  1. obtain broad inputs at the formulation stage  2. assess o

Explain the advantages of the scientific method, Describe the advantages an...

Describe the advantages and disadvantages of the scientific method and qualitative approaches to research

Explain main benefits of the just-in-time system, 1) What are at least thre...

1) What are at least three main benefits of the just-in-time system? Present and explain them 2) What are at least three main drawbacks/problems of the just-in-time system? Pres

Abc, Explain in brief the meaning, Steps involved in linear programming pro...

Explain in brief the meaning, Steps involved in linear programming problem formulation with and example

Find revenue growth and overall financial performance, What actions do you ...

What actions do you think management at Sam's Club should take to boost revenue growth and overall financial performance? What actions do you think management at BJ's Wholesale sho

Imagine this is the only position of its kind organization, Imagine this is...

Imagine this is the only position of its kind in the organization. From this perspective, design a performance appraisal program to assess your job performance.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd