Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Q3. What do you understand by “line balancing”? What happens, Q3. What do y...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Compute the line efficiency of longest processing time, Balance the assembl...

Balance the assembly line in Exhibit 8.12 for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an eight-hour shift, and use the rule, choose the assignab

Explain what type of discharge of the contract, Mary has a City Credit Card...

Mary has a City Credit Card (CCC) and has run up a $13,000 debt. She calls the company and explains that she can't pay the full amount, but will be willing to pay $10,000 if they w

Explain rtp, Orange Company is allocating its advertising budget for its ne...

Orange Company is allocating its advertising budget for its new smartphone targeting graduate and undergraduate students in RTP. The company has invited representatives from the lo

Problems that can plague groups as organizations is groupth, One of the rec...

One of the recognized problems that can plague groups and organizations is groupthink. Do some research on the groupthink phenomenon? What is it? When does it occur? What are some

Explain earned value measurement is a technique, Earned value measurement i...

Earned value measurement is a technique: Answer Suitable for risk monitoring and control Unsuitable for risk monitoring and control Suitable for risk monitoring but uns

Process technology life cycle , Process Technology Life Cycle Process ...

Process Technology Life Cycle Process technologies have life cycles related to product life cycles as shown in figure below. Over time unit manufacturing costs diminish for ma

Explain improving operations, What would you recommend to the company if th...

What would you recommend to the company if they asked you to advise them in improving their operations?

Explain competitive advantage only exist for a short time, With the realiti...

With the realities of today's technological innovation and the realities of the current economy, competitive advantage only exist for a short time and are quickly outdated. Agree o

MBA-2, What do you understand by line balancing what happens if balance doe...

What do you understand by line balancing what happens if balance doesn''t exist

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd