Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Find which among the following statements are correct, If random variable X...

If random variable X follows the Normal distribution. X~Normal(10,10). Which among the following statements are correct? Answer a. P(X b. P(X=10)=0 c. P(X>8)=1-P(X

Work study, techniques & applicationa

techniques & applicationa

Explain what is the expected project length, Task time estimates for a prod...

Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Activity Time (in hours) Predecessors A 6.0 - B 7.2 __ C

Impact on the it group of supporting a variety of devices, What is the impa...

What is the impact on the IT group of supporting a variety of devices?

Answer, A paper mill produces two grades of paper viz., X and Y. Because of...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Explain penetrated market, Which market do customers who have purchased and...

Which market do customers who have purchased and are driving Audi automobiles represent? a. Target market b. Available market c. Potential market d.

Describe skills or abilities you would need to develop, "CIOs" Please respo...

"CIOs" Please respond to the following: •Assess the role of the CIO within any health care organization and describe the key characteristics a CIO would need to possess to be effec

Explain can you be innovative in a mature industry, 1. How much of an impac...

1. How much of an impact does "maturity" level of the industry or company have on strategy? 2. Can you be innovative in a mature industry? 3. Can you be conservative in an in

Explain concept of sustainability in operations management, Explain the con...

Explain the concept of sustainability in operations management. The concept of sustainability within operations management: Sustainability in operations management is regarding

Explain ethical and managerial elements, Submit a 1,000-1,250-word paper th...

Submit a 1,000-1,250-word paper that identifies and examines various legal, ethical, and managerial elements as they apply to employee monitoring. Cite at least 2 references tha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd