Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain the two main types of financing, How have globalization and informa...

How have globalization and information technology created new opportunities for entrepreneurs? Describe current demographic trends that suggest new goods and services for entrepren

Explain the drug research and distribution industry, If Merck can donate $5...

If Merck can donate $50 million in free doses of ivermectin, what does that say about the amount of revenue the company generates in the drug research and distribution industry?

Describe how sharpen the saw is applied, Explain how "sharpen the saw" is a...

Explain how "sharpen the saw" is applied in the Toyota Production System Grading rubric (Highest quality answers will consider ALL of the following) Describe "sharpen the saw

How to avoid the race condition, To avoid the race condition, the number of...

To avoid the race condition, the number of processes that may be simultaneously inside their critical section is A. 8 B. 1 C. 16 D. 0 E. None of the above

Calculate the expected value of perfect information, Clay Why bark, a soft-...

Clay Why bark, a soft-drink vendor at Hard Rock Cafe%u2019s annual Rockfest, created a table of conditional values for the various alternatives (stocking decision) and states of na

Why jobs needed to produce the shopping carts, A company that makes shoppin...

A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labour content of the jobs needed to produce the shoppi

Explain the fit for gbi of this particular for-profit avenue, Discuss the f...

Discuss the fit for GBI of this particular for-profit avenue Eileen o'brien has chosen?

Process through bank supply its customer with cash on demand, 1. Think of f...

1. Think of four different processes by which a bank might supply its customers with cash on demand. Answer: Examples: over-the-counter at branches, by ATM dispensers in shoppin

Explain direct marketing association website, On the Direct Marketing Assoc...

On the Direct Marketing Association website, what is interesting, how can companies use the website, what information is surprising and why?

Compute the standard time for each work, The Arkade Company has decided to ...

The Arkade Company has decided to use a 15 percent allowance factor based on job time. Calculate the standard time for each work element and for the total job. The frequency equals

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd