Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Scheduling in mass continuous, Scheduling In Mass Continuous Schedul...

Scheduling In Mass Continuous Scheduling In Mass Continuous and Project Type Production System The scheduling aspects mentioned so far have been concerned with job shop

Factors influencing plant layout, Factors Influencing Plant Layout While...

Factors Influencing Plant Layout While choosing the layout for a factory the following factors should be taken into consideration: Management Policy: Management has to de

Explain schedule performance index, Question at the end of one of my chapte...

Question at the end of one of my chapters. Would like to see an example of cost and schedule performance index completed. I appreciate the help A sales-related venture had an ac

Compute what is its cost of common equity, The earnings, dividends, and com...

The earnings, dividends, and common stock price of Carpetto Technologies Inc. are expected to grow at 8% per year in the future. Carpetto's common stock sells for $27.75 per share,

Provide examples of organizational situations, Give examples of organizatio...

Give examples of organizational situations that would call for transformational, transactional or charismatic leadership. I have an example of transformational, just can't quite

Line balancing, What do you understand by “line balancing”? What happens if...

What do you understand by “line balancing”? What happens if balance doesn’t exist

Explain the ohio-based company is covered by the nlra, The Ohio-based compa...

The Ohio-based company is covered by the NLRA. The CEO has heard rumblings that the employees may not be satisfied and are looking for representation. The CEO asked you, "If a unio

Introduction of operations strategy, Introduction of Operations Strategy ...

Introduction of Operations Strategy The term strategy, given in the Collins English Dictionary is, 'the art or science of the planning and conduct of a war; generalship; a lon

Technological infrastructure, Identity technological infrastructure that su...

Identity technological infrastructure that supports operations management

Opportunity costs of cells - transportation problem, Having determined all ...

Having determined all ui and vj values calculate for each unoccupied cell ij = ui + vj - cij. The ij represent the opportunity costs of various cells. After obtaining the opportuni

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd