Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

What are the disadvantages of the level capacity strategy, What are the dis...

What are the disadvantages of the Level capacity strategy? The disadvantages of the Level capacity strategy are as follows: a. High risk of stock obsolescence when customer

Describe the steps of the collaboration process, 1. State the primary reaso...

1. State the primary reasons for the organizations existence from an analysis of the mission, vision, values, and goals. & Intro. 2. Analyze the reason for the type of organizat

How to determine the sample standard deviation, Determine the sample standa...

Determine the sample standard deviation(s) for the following data: 7, 9, 2, 0, 1, and 5. s = 2.805 s = 3.266 s = 2.927 s = 3.578

Define people to try to justify conduct by the argument, How common do you ...

How common do you think it is for people to try to justify their conduct by the argument that "Everybody's doing it"?

Question eXAM, Defining Operation Management Operations performance...

Defining Operation Management Operations performance Function of operations Evolution of operations management E-business Integrated value c

Explain investment economically acceptable, Orangemen Lofts plans to add 30...

Orangemen Lofts plans to add 300 luxury apartments to its complex in Cohoes. The cost of the land now is $16 million including taxes and fees. The construction cost is expected to

Explain if a wireless signal collides with an object, If a wireless signal ...

If a wireless signal collides with an object whose dimensions are much larger than the signal's wavelength, what is the signal most likely to do? a. reflect b. refract c.

Explain collected at different points, Two samples are said to be independe...

Two samples are said to be independent if they are collected at different points in time. False True

Explain percentage must materials cost be reduced, Merk, Inc., produces ele...

Merk, Inc., produces electronics component on an assembly line. The standard cost for the component is $105 (labor $15, materials $60, and other costs $30). The sellings price is $

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd