Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain close the gap between management and employees, Identify what HR m...

Identify what HR mechanisms can be introduced in the international firm today to build a strategic business partnership, close the gap between management and employees while bui

Explain when the doctor dictates a decimal such as point1, What do you do w...

What do you do when the doctor dictates a decimal such as "point 1"?

Material Requirements planning, Material Requirements planning is more than...

Material Requirements planning is more than Inventory system "discuss

Organizing process flows, Organizing Process Flows Five types of proc...

Organizing Process Flows Five types of process are distinguished. They are Project Production System Job Shop Production system Batch Production system

Moving average in local organic food market, Weekly sales of 10-grain bread...

Weekly sales of 10-grain bread at the local organic food market are in the table below. Based on this data, forecast Week 9 using a five-week moving average. Week Sales 1

Explain how is the search industry changing, How is the search industry cha...

How is the search industry changing? What forces seem most likely to bring about major change to the industry within the next three to five years?

Explain proposed investment in the warehouse extension, What overall recomm...

What overall recommendations would you make to Francis Lamouche about the proposed investment in the warehouse extension?

Explain what does ethical egoism believe, What does ethical egoism believe ...

What does ethical egoism believe we should embrace as a cocept for living? How alien is this to Christian worldview? How does Ayn Rand argue the benefits of this concept? What does

Describe strategic planning process, As a part of the strategic planning pr...

As a part of the strategic planning process, our firm will have to examine external factors with the EFE Matrix and internal factors with the IFE Matrix. If we only do one of these

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd