Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain introduction to optimum design, Why are there no solutions for Intr...

Why are there no solutions for Introduction to Optimum Design textbooks?

Explain critical path consists of only five activities, You are working on ...

You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical pat

Explain defect and passed inspection, A manager states that his process is ...

A manager states that his process is really working well. Out of 1,500 parts, 1,477 were produced free of a particular defect and passed inspection. Based upon Six-Sigma theory, ho

Explain spread harmful rumours gossips uses bad language, Sara spread harmf...

Sara spread harmful rumours gossips uses bad language and lack civility in relationship while at work/ in which of the following is sarah engaging in/1.proert deviance/ 2 productio

Explain the probable destiny competing products, Consider this: Lee Peterso...

Consider this: Lee Peterson has invented a new product that detects water leaks due to broken pipes and sends out an alarm similar to a smoke alarm. However, Lee has very little pe

Steps in layout planning and design, Steps in Layout Planning and Design ...

Steps in Layout Planning and Design For a given product at a stated volume of production a process most appropriate must be determined. The process that is determined like any

Describe what the advantages of making vs buying, You are the Vice-Presiden...

You are the Vice-President of Manufacturing for a company which manufactures small personal appliances. Your R & D department has designed a revolutionary, new type of electric t

Explain monetary value on the social and the environmental, Can you put a m...

Can you put a monetary value on the social and the environmental benefits?

Explain labour agreements, Outline and explain the three major elements (an...

Outline and explain the three major elements (and their arguments) contained in the controversial question as to whether union security provisions should be negotiated in labour ag

Explain what purpose does the project charter serve, a. What purpose does t...

a. What purpose does the Project Charter serve? b. What are the main components or sections of the Project Charter? c. What purpose does the Project Definition Document serve

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd