Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Explain how much water can be transported per hour, The network in figure b...

The network in figure below shows the pipeline transportation system for treated water from the treatment plant to a city water supply system. The arc capacities represent millions

What are the ways in which corporations can demonstrate, What are three way...

What are three ways in which corporations can demonstrate a sense of social responsibility?

Flow Time, You know that our average weekly sales are $2,500 and the flow t...

You know that our average weekly sales are $2,500 and the flow time is half day. Surely with this information, you should have no problem maintaining an inventory level of $400 to

Libertarian view on the importance of consumer rights, Compare a Utilitaria...

Compare a Utilitarian and a Libertarian view on the importance and enforcement of consumer rights.

How to find the optimal order quantity, Must use Excel for solution Zip ...

Must use Excel for solution Zip Games purchases blank 3.5-inch disks onto which it copies its software for sale through its mail order operation. A disk costs Zip $.20. Processi

Describe factors affecting morale, Describe factors affecting morale. F...

Describe factors affecting morale. Factors that tend to lower or improve the worker morale are: 1. Job Factors - Nature of job, Fatigue and boredom related with the job,

Computer aided design., Computer Aided Design is one of the techniques used...

Computer Aided Design is one of the techniques used by Regal Marine in manufacturing of boats. With the aid of exapmles, critically discuss five (5) techniques that are important t

Define the strategies that you might use in addressing goals, Develop a str...

Develop a strong talent management program globally to develop and retain talent that you have been losing to competitors and downsizing. Discuss the strategies that you might use

Explain probabilites for grades in management science, The following probab...

The following probabilites for grades in management science have been determined based on the past records: Grade Probability A .10

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd