Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Define the concept of a career, Discuss the concept of a career. What are t...

Discuss the concept of a career. What are the Four Career Stages- List each one with its specific characteristics

Explain a university web server has five main components, A University Web ...

A University Web server has five main components each with the same reliability. All five components must work for the server to function as intended. If the University wants to ha

Describe financial leverage and give two examples, Define financial leverag...

Define financial leverage and give two examples to support your definition?

Explain sample means and sample ranges have been computed, Checkout time at...

Checkout time at a supermarket is monitored using a range and mean chart. Six samples which contain 20 observations per sample have been collected and the sample means and sample r

Make a fictional company and develop a memo to communicate, Create a fictio...

Create a fictional company and develop a memo to communicate the importance of a business continuity plan to the board of directors. The completed assignment should be at least 25

Explain what is the probability distribution of the time, Consider a queuin...

Consider a queuing system with 2 types of customers. Type 1 customers arrive according to a Poisson process with a mean rate of 5 per hour. Type 2 customers arrive according to a P

Quality, Ques: What do you think happened to the quality, variety, availabi...

Ques: What do you think happened to the quality, variety, availability or cost of agricultural or manufactured products - or the level of competition? Ans: Quality increased; va

Explain the concept of merit goods, Explain the concept of merit goods with...

Explain the concept of merit goods with reference to the formal provision of education in a country.  Merit goods are those goods and services that society values and the gover

Performance measurement and effectiveness of operations, Question: A ba...

Question: A bank has a section of its business which has two functions:- 1. answering credit control queries from customers both by telephone and in writing; 2. invest

Explain essentials of system analysis and design, Essentials of System Anal...

Essentials of System Analysis and Design Read the Hoosier Burger scenario on page 199 in Chapter 6 of the text and address the following (you only need to complete parts a throu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd