Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Construct the control chart, Telephone inquiries of 100 cell phone company ...

Telephone inquiries of 100 cell phone company customers are monitored daily at random.  Incidents of incorrect information or other nonconformities (such as rudeness to customers)

Calculate mad for each forecast, Weekly sales of copy paper at Cubicle Supp...

Weekly sales of copy paper at Cubicle Suppliers are in the table below. Forecast week 8 with a three-period moving average and with a four-period moving average. Compute MAD for ea

Objectivise and benefits of work study, Objectivise and Benefits of Work St...

Objectivise and Benefits of Work Study Objectivise of Work Study a)Provide more and improved physical means to motivate the workers. b)Improve the basic process by resear

Explain what additional facts could cause the decision, Ema graduated from ...

Ema graduated from a very prestigious college and was in her second year of medical school. Ema's parents did not have the resources to help her pay for college. For the past six y

Logistics, Ask question #Minimum 100 words acceptedTopic 2: Logistics Logi...

Ask question #Minimum 100 words acceptedTopic 2: Logistics Logistics is the management of the flow of goods, information and other resources, including energy and people, between

, What happens if balance doesn’t exis

What happens if balance doesn’t exist

Lead time - operations management, Lead Time - Operations Management E...

Lead Time - Operations Management Estimated time from release of an order requesting the manufacture or procurement of any item until the time it is available. The lead time (

Explain collective bargaining, Collective bargaining replaces management's ...

Collective bargaining replaces management's traditional authority to unilaterally establish terms and conditions of employment with bilateral negotiations. How has the collective b

Distinguish between legal and employee rights, Q1. What is the biggest chal...

Q1. What is the biggest challenge posed by egoisn Q2. Distinguish between legal and employee rights Q3. How is strategy different from a business model? How is it similar?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd