Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Location decision and layout selection, 1. general procedures for making lo...

1. general procedures for making location decision 2. factors to consider in layout selecgtion

Explain how many units produced to maximize the profit, The Toys-R-4-U Comp...

The Toys-R-4-U Company has developed two new toys for possible inclusion in its product line. Setting up the production facilities to begin production would cost $50,000 for toy 1

Explain how would they be measured, Based on the description of Coyote Comm...

Based on the description of Coyote Community College and its environment, what specific types of measures should they include in each of their perspectives of the balanced scorecar

Describe develop a system for evaluating the productivity, As the administr...

As the administrative manager in a law office, you have been asked to develop a system for evaluating the productivity of the 15 lawyers in the office. What difficulties are you go

Linear Programming, Solve the following Linear Programming Problem using Si...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1+ X2 = 2 X1, X2 = 0

Explain growth and globalization strategies, Given Pitney Bowes' growth and...

Given Pitney Bowes' growth and globalization strategies, analyze the forces for and against maintaining an organizational culture that supports diversity as a business imperative

Give the definition of a team, QUESTION (a) Give the definition of a te...

QUESTION (a) Give the definition of a team as well as elaborate on the purpose of having teams in the organisation. (b) Explain the different processes that take place in a

What is communication in an organisation structure, What is Communication i...

What is Communication in an organisation structure. Communication: An organisation structure gives channels for the flow of information on that the decisions of the organisat

Goldratt - theory of constraints, Goldratt - Theory of Constraints 1 i...

Goldratt - Theory of Constraints 1 identify the systems constraints  2 exploit the systems constraints  3 subordinate everything else to the above decision  4 elevate

What are advantages of using multiple sourcing strategies, What are the adv...

What are the advantages of using multiple sourcing strategies? Advantages of using multiple sourcing: a. May assist negotiate and drive down prices while more suppliers e

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd