Compute a schedule using least-total-cost lot sizing, Operation Management

Assignment Help:

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Compute a schedule using least-total-cost lot sizing

Calculate the non-registered investments, Calculate how much  they will be ...

Calculate how much  they will be  able  to  save  in non-registered investments each year until their retirement. This is Rose and Leonard's first look at a retirement plan. Will t

mba, What happens if balance doesn’t exis

What happens if balance doesn’t exist

Explain what remedies are available to him, Kristina places an order for a ...

Kristina places an order for a cake on Flowers bakery's web site. She then calls the baker to tell him that she will pay him $1000 for the specially designed cake if he will guaran

Explain project management is a strategic necessity, Project Management is ...

Project Management is a strategic necessity for the success of any business. Based on the reading in the chapters what do you think are the 5 most critical points in delivering suc

[email protected], What are all the steps involved in Work St...

What are all the steps involved in Work Study

Find the shipping costs for company a to ship one unit, Company A has four ...

Company A has four plants locating in different cities across the region. There are three markets the company is selling its products to. Currently, each plant can only produce 500

Explain effects of indiscipline, Explain effects of indiscipline. Effe...

Explain effects of indiscipline. Effects of Indiscipline: The indiscipline in industry brings in exact adverse effects. These are as given here:- a) Increase in the give

Explain organizations need to calculate a threshold, Why do organizations n...

Why do organizations need to calculate a threshold for a reorder? How could this affect sales?

Explain decision alternatices and various levels of demand, The following p...

The following payoff table provides profits based on various possible decision alternatices and various levels of demand at Amber Gardner's software firm

Explain what ways does this benefit a project, Some companies choose not to...

Some companies choose not to tie resources to their projects. In what ways does this benefit a project? In what ways does this hinder a project?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd