M/s XYZ Ltd manufactures a product “PLVS” at its plant at Meerut, the maximum capacity of which is 200 units per month. Details of raw materials which go into the making of 1 units of “PLVS” are provided to you below:-
Sl.No Raw material description Standard Qty per finished unit (No) Standard purchase price per unit (Rs. 00)
1 A 1 6
2. B 2 5
3. C 3 4
4. D 4 3
5. E 5 2
6. F 6 1

Standard fixed overheads are Rs. 20,00,000/- per month whereas the standard variable overhead rate has been estimated as equal to Rs.1,400/- per unit of finished good.

You are required to compute the
a) Standard cost of the product.
b) Compute the production volume variance in case the company produces and sells only 100 units of finished goods in the concerned month.
c) Compute the usage and material price variances considering the following actual data (actual production and sale: 100 units)

Related Discussions:- case study

#title.welding., Does the atmospheric pressure inside of a tube aproximatel...

Does the atmospheric pressure inside of a tube aproximately a half an inch in diameter cause resistance against an end plug being flash welded to the end of it and what would be th

Hot and cold working, the amount of cold working metal can withstand is dir...

the amount of cold working metal can withstand is directly related to which properties? name two and also discuss the effect that cold working has upon these properties?

Career help, hey, i am doing b.e in chemical engineering but by aggregate i...

hey, i am doing b.e in chemical engineering but by aggregate is 55%. i would like to know what courses and preparation i have to do to get a good job. pls reply as soon as possible

Financial management, Sharpe Knife Company expects sales next year to be $1...

Sharpe Knife Company expects sales next year to be $1,500,000 if the economy is strong, $800,000if the economy is steady, and $500,000if the economy willb e strong, a 50 percent pr

Sas software, I need assistance in SAS software based stats questions, can ...

I need assistance in SAS software based stats questions, can you provide me solution?

Petroleum Production.., 1. . Using the graph of pore/fracture pressure for ...

1. . Using the graph of pore/fracture pressure for the Holly Field propose a casing scheme for the well using the graphical approach. Discuss the suitability of the selected casing

Uncertainty propagation, Uncertainty propagation In order to calculate ...

Uncertainty propagation In order to calculate the error of a quantity derived from a mathematical formula which has measured variables with errors, one should use the uncertain

Liquidity ratios, Liquidity Ratios: The liquidity ratios of the company hel...

Liquidity Ratios: The liquidity ratios of the company help in determining the ability of the company to convert its current or liquid assets readily into cash. Higher the ratios be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd