Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Question
What is major importance of air void content in bituminous pavements?
Answer
Air void content of bituminous materials is important control parameter for quality of bitumen being laid and compacted. If air void content is also high, it let for intrusion of air and water. Furthermore, it also increases rate of hardening of binders which create premature embrittlement of pavements. In adding, too high a void satisfied will also lead to differential compaction question to traffic loads and result in creation of ruts and grooves along wheel track.
Though, a minimum amount of air void has to be maintained to avoid instability during compaction progression and to provide space for bitumen flow in long-term consolidation under interchange loads. A enough amount of air voids have to be designed to create room for expansion of binder in summer and compaction by road traffic as optional by National Association of Australian State Road Authorities in 1968, or else bleeding and loss of stability might occur and pavement will deform readily under severe loads.
how to make plain scale
Resultant Force on a Given Area of a Horizontal Plane By equation, the total vertical force applied to an area A on the plane is: Resultant Force R = ΡA = (lb/ft 2 )(ft 2 )
what is torsional moment of resistance
what is brick masonry
Calculation of deformation For calculation of deformation at some stage before the total creep is reached, it may be assumed that about half the total creep takes place in f
ratio of moorum and aggregate
The discharge of water collected from a constant head permeameter in a period of 15 minutes is 500 ml. The internal diameter of the permeameter is 5 cm and the measured difference
What is the meaning of Elastic Shortening of Concrete At the transfer stage, compressive prestressing force is transferred to the concrete. Due to this compressive force, concr
I want to ask about mathcad prime 2.0, when I want to save my work it shows that I can''t save it because Excel is busy ,, what I have to do to fix this problem ??
Calculate the surface dimensions of Sedimentation Tank A treatment plant upgrade calls for design of sedimentation basins to handle a flow rate of 8 MGD. The basins are for a T
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd