Calculate the total board feet, Civil Engineering

Assignment Help:

A project engineer has ordered 100 hardwood boards, 1-1/4-in thick by 8-in wide and 8-ft long.  The total board feet ordered is most nearly: 

Solution:

1.25" x 8" x 8' x 100-pcs = 666.67 board feet (answer)

Or, (1.25" x 8" x (8'x 12"/1')/ 12) x 100-pcs  

  = 666.67 board feet

 

858_The total board feet.png

 


Related Discussions:- Calculate the total board feet

Show ph value of water, Q. PH Value of Water? It is a symbol for hydrog...

Q. PH Value of Water? It is a symbol for hydrogen ion concentration and indicates acidity or alkalinity. When P H Value more than 7 water is alkaline and less than 7 water is a

Stiff or soft fenders be designed for berthing in piers, Question Is it...

Question Is it necessary that stiff or soft fenders be designed for berthing in piers? Answer Elasticity of fenders is related to ability to release stored energy duri

Incremental launching mode of bridge construction, In i ncremental launchin...

In i ncremental launching mode of bridge construction, what are ways adopted to increase sufficient resistance of superstructure during launching practice?

Batching of concrete, Introdaction , volume batching , weighat batchin...

Introdaction , volume batching , weighat batching , mesaring of water

Steady flow energy equation, If there is steady flow, nothing changes with ...

If there is steady flow, nothing changes with time.  1. The properties of the fluid at entry and exit are constant. 2.  The properties of the fluid at any point in the contro

Determine load carried by each cylinder, Determine load carried by each cyl...

Determine load carried by each cylinder: A hollow steel cylinder of cross-sectional area 2000 mm 2 concentrically surrounds a solid aluminium cylinder of cross-sectional area

Inspection and quality control certificate, Q. Inspection and Quality Contr...

Q. Inspection and Quality Control Certificate : A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certif

Determine the preliminary settlement analysis, Preliminary settlement analy...

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stra

LOADS, what are the difference between UDL and UVL?

what are the difference between UDL and UVL?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd