Calculate the total board feet, Civil Engineering

Assignment Help:

A project engineer has ordered 100 hardwood boards, 1-1/4-in thick by 8-in wide and 8-ft long.  The total board feet ordered is most nearly: 

Solution:

1.25" x 8" x 8' x 100-pcs = 666.67 board feet (answer)

Or, (1.25" x 8" x (8'x 12"/1')/ 12) x 100-pcs  

  = 666.67 board feet

 

858_The total board feet.png

 


Related Discussions:- Calculate the total board feet

Explain the confined aquifer and piezometric surface, Explain the Confined ...

Explain the Confined Aquifer and Piezometric Surface Confined Aquifer Groundwater is confined by impervious geologic stratums on all sides. The water may be under pressure.

Calculate concrete yield in cubic feet per sack of cement, Calculate the Co...

Calculate the Concrete Yield in Cubic Feet per Sack of Cement A concrete mix design is 1: 1.9: 2.8 by weight.  The water cement ratio is 7 gallons of water per sack.  The aggre

Illustrate the design discharge for foundation, Q. Illustrate the Design di...

Q. Illustrate the Design discharge for foundation? To provide for an adequate margin of safety, the foundation and protective works of a bridge should be designed for a flood d

Influence Line for shear at Support, I have to draw the IL for the shear at...

I have to draw the IL for the shear at a roller support and am not sure how it should look

Angle&direction, whate does mean bearing?with example

whate does mean bearing?with example

Calculate load distribution factor, Load Distribution Factor: The form...

Load Distribution Factor: The formula for deriving at the number of repetitions of the standard axle load during a design period of n years is: N =365 × A × VDF × F [(1 + r

Roads construction in marshy land, precaution to be taken for roads constru...

precaution to be taken for roads construction in marshy land

Elongation, Elongation of bar due to self weight

Elongation of bar due to self weight

Calculate the parameters for setting out curve, Q For a curve of 50, apex ...

Q For a curve of 50, apex angle of 900 and transition length of 60m, calculate the parameters for setting out curve by a Theodolite for TTP, mid point of transition, CTP and a p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd