Calculate the standard production, Operation Management

Assignment Help:

Calculate the standard production  per shift  of 8 hours duration  with the followings data:

Observed time  per unit 5 minutes

 Rating  factor 120 %

 Total allowances 33.33 of normal time.

 Solution  : Normal  time per unit= Observed time  / unit X rating factor

             = 5X 120 /100= 6 minutes

Allowance  = 33.33 of normal  time

33.33X 6 / 100= 2 minutes

 Standard  time / unit  = normal  time  / unit  +Allowances

  = 6+2= 8 minutes / unit

 Standard production  in shift of 8 hours

  = 8X 60 / 8 = 60 units.


Related Discussions:- Calculate the standard production

Hill approach to manufacturing operations, Hill Approach to Manufacturing O...

Hill Approach to Manufacturing Operations - Operation Management  Hill's five step approach to developing manufacturing operations illustrated in table below (Hill, 1993). A

Which factors influence the choice of evaluation design, What factors influ...

What factors influence the choice of evaluation design? Which of these factors would have the greatest influence on your choice of an evaluation design? Which would have the smalle

Explain project charter is to help the project team, One purpose of the pro...

One purpose of the project charter is to help the project team and the project sponsor to commit to the project

Explain quantitative vs qualitive research methods, What are your thoughts ...

What are your thoughts around quantitative vs qualitive research methods? Can you list pros and cons for each one?

Explain decision making and control processes, 1. From an international cul...

1. From an international cultural perspective, how much of an impact is on the timely decision making and control processes can there be when there is a difference in national and

Define relationship between job satisfaction and performance, When Scott Tw...

When Scott Tweedy picked up a magazine article on how to manage health care workers, he was pleased to some advice. Scott was concerned about poor or mediocre performance on

Find number of job requests, Value: 10.00 points Problem 3-4 An electrical ...

Value: 10.00 points Problem 3-4 An electrical contractor's records during the last five weeks indicate the number of job requests: Week: 1 2 3 4 5 Requests: 16 18 14 17 18 Predict

Explain what are the correlation coefficient, Mark Gershon, owner of a musi...

Mark Gershon, owner of a musical instrument dis-tributorship, thinks that demand for guitars may be related to the number of television appearances by the popular group Maroon 5 du

Explain what is the annual holding cost, Your company manufactures turbine ...

Your company manufactures turbine blades for engines in production batches for each type. For one type of blade, the A39T, you have an annual demand of 10,000 units. It costs you $

Explain a formal or informal mutual agreement, Explain a formal or informal...

Explain a formal or informal mutual agreement. - The mutual agreement may be as given below: (a) Union security. (b) Bonus, wages and other benefits. (c) Terms and con

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd