Calculate the percent change in the labor ratios, Operation Management

Assignment Help:

A department employs 3 types of workers: laborers earning $5 per hour, machine operators earning $9 per hour and maintenance workers earning $16 per hour. For a certain job over 2 time periods, the following data were collected

Type of Employee Number of Labor period #1 Number of Labor for period # 2

Laborer 20 16

Machine Operator 12 16

Maintenance Worker 6 9

Output increased by 20% in period #2 compared to period #1.

a) Compute the Labor productivity ratio for each period.

b) Compute the percent change in the labor ratios


Related Discussions:- Calculate the percent change in the labor ratios

How minimize the work-in-process inventory, The production manager must det...

The production manager must determine the processing sequence for 7 jobs through the grinding and debarring departments. The same sequence will be followed in both departments. The

Mass Production and Continuous Flow Manufacturing, Mass Production and Cont...

Mass Production and Continuous Flow Manufacturing  Continuous systems lie at the other extreme, where demand for a single product is sufficiently high to warrant the installa

Explain some inherent challenges in using decision trees, What are some inh...

What are some inherent challenges in using decision trees effectively in today's organizations? How can these challenges be overcome?

Explain cost benefit analysis, Explain cost benefit analysis. Cost Ben...

Explain cost benefit analysis. Cost Benefit Analysis: This analysis is a mathematical technique for decision-making. This is a quantitative technique used to estimate the eco

Explain marketing infant formula in a developing country, Under what circum...

Under what circumstances, if any, would a firm be justified in marketing infant formula in a developing country?

Explain during the campus spring fling, During the campus Spring Fling, the...

During the campus Spring Fling, the bumper car amusement attraction has a problem of cars becoming disabled and in need of repair. Repair personnel can be hired at the rate of $20

Described in the initial kickoff meeting for a project, Which of the follow...

Which of the following would be the first item to be discussed in the initial kickoff meeting for a project? Answer Understanding of the requirements Understanding of the

What is average costumer waits time in line, A newly opened car wash statio...

A newly opened car wash station has a car wash machine. The machine washes each car in a constant rate of 5 minutes per car. It has been estimated that costumers will arrive accord

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd