Calculate the number of paths and critical paths, Civil Engineering

Assignment Help:

Calculate the Number of Paths, Number of Critical Paths and Project Duration

For the project network shown, the total number of paths through the network; number of critical paths; and, project duration (days) is most nearly:

a. 6; 2; and, 26 

b. 6; 1; and, 26 

c. 5; 1; and, 25

d. 3; 3; and, 24

539_Calculate the Number of Paths, Number of Critical Paths and Project Duration.png

Solution:  List the number of paths and calculate the duration for each.  

L M O R T V   = 4 + 7 + 2 + 2 + 2 + 9 = 26-days -- Critical

L M O S U     = 4 + 7 + 2 + 3 + 7 = 23-days

L M Q V      = 4 + 7 + 6 + 9 = 26-days - Critical 

L M Q U    = 4 + 7 + 6 + 7 = 24-days

L N P Q U    = 4 + 3 + 6 + 7 = 20-days

L N P Q V    = 4 + 3 + 3 + 6 + 9 = 25-days


Related Discussions:- Calculate the number of paths and critical paths

What is the tensile strength of wood, The tensile strength of a material is...

The tensile strength of a material is the value at which the material fails when subjected to a tensile force. (Tensile means a force pulling the wood fibers lengthwise, as opposed

Retaining wall, whether the wall has adequate sliding resistance

whether the wall has adequate sliding resistance

Pavement width - geometric design of roads, Pavement Width: The pavem...

Pavement Width: The pavement widths commonly adopted are : Single lane                 :           3.75 m Intermediate lane     :           5.5 m Two lane

Define pavement design - transportation, Define Pavement Design - Transport...

Define Pavement Design - Transportation 1. Asphalt surface a. Estimate Design Traffic b. Determine the Structural Number (SN) for the given traffic, roadway, and soil cha

Explain the coordinate system, Explain the Coordinate System 1. A Bench...

Explain the Coordinate System 1. A Benchmark provides only elevation data. 2. Coordinate System provides northing and easting coordinates within a defined system. 3. Coor

Explain cercla and sara - hazardous waste regulations, Explain CERCLA and S...

Explain CERCLA and SARA - Hazardous Waste Regulations In 1980, the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) was enacted to address tho

Computer programming, compare 2 numbers and print either the message identi...

compare 2 numbers and print either the message identifying the greater than number(or) the message starting that both number are equal

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd