Calculate the npv is elevated for project hk, Business Management

Assignment Help:

a) Students will require to carry out a full quantitative investment appraisal:

 

Project HK

Project UK

Payback

2 years, 7 months

2 years

ARR

22.5%

20.83%

NPV

$21,141

$19,990

  • Based on the financial data, Project UK has a shorter payback (by just over 6 months), so if liquidity is an issue, then the firm should choose for this venture.
  • However, the ARR is higher if the firm opts for Project HK; although both are considerably higher than any return from savings at a bank
  • The NPV is elevated for Project HK (by a $1241 or 6.23%)
  • Overall, on financial grounds, Project HK seems the improved option if the business is prepared to wait a further 6 months or so before it accomplish payback.

In addition, investment assessment methods should consider the qualitative factors (the PORSCHE mnemonic) that affect the business and the investment. For example, there needs to be a consideration of organizational the views of stakeholders and objectives.

 


Related Discussions:- Calculate the npv is elevated for project hk

E-commerce cost benefit analysis, Sun Gas wants to move its sales order sys...

Sun Gas wants to move its sales order system to the Web. Under the proposed system, gas stations and other merchants will use a Web browser and, after typing in a password for the

Determine the strengths and limitations of theories, QUESTION 1 Discuss...

QUESTION 1 Discuss some of the assumptions that underlie the construction of various types of communication theories. QUESTION 2 What are the rationale and foundational

Explain the theories of belbin and tuckman, Mr. Brian Smith is the 0fficer-...

Mr. Brian Smith is the 0fficer-in-charge of a group of 15 persons, all posted in the correspondence/registry services of the Texman Services, a company in the insurance business.

Developing plans for areas of responsibility, Work Breakdown Structures (WB...

Work Breakdown Structures (WBS) - explain the value, role and use of the WBS methodology in project management. Planning within organizations takes place at strategic, tactical

High-context culture and low-context culture, QUESTION 1 Both encoding ...

QUESTION 1 Both encoding and decoding of messages lay traps for the unwary intercultural communicators (Hall, 1959 - The Silent Language). Using appropriate examples, discuss t

Explain updating and improving current product line, Explain about the cont...

Explain about the continually updating and improving the current product line. Creating a Constant Flow of New Products or Continually Updating & Improving the Current Product

Define good governance, QUESTION 1 a) Define good governance b) Desc...

QUESTION 1 a) Define good governance b) Describe the importance of good governance in the business context QUESTION 2 Taking the Mauritian context in consideration

Explain relationship development theories, Question: i) Recall a time w...

Question: i) Recall a time when you have been the target of rumours or gossip. How might these influence the development of a friendship (whether the gossip is spread by the pe

Explain any two motivational theories, QUESTION 1 (a) Define the concep...

QUESTION 1 (a) Define the concept of span of control (b) Describe the factors that may impact on the choice of the organization structure (c) What are the different busin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd