Calculate the cycle and production rate , Mechanical Engineering

Assignment Help:

Calculate the Cycle and Production Rate for Single-Machine Robotic Cell

Determine the cycle and production rate for a single-machine robotic cell for an 8-hr shift if the system availability is 85%. Also find out the percent utilization of machine and robot. On average, the machine takes 35 sec. to process a part. The other robot operation times are as follows:

Robot moves the shaft to the lathe                                            1.5 sec

Robot unloads the shaft from the lathe                                       0.5 sec

Robot picks a shaft from the conveyor                                        4.0 sec

Robot loads the shaft onto the lathe                                          1.0 sec

Robot moves the conveyor                                                        1.5 sec

Robot puts the shaft on the outgoing conveyor                            0.5 sec

Robot moves from the output conveyor to the input conveyor        5.0 sec

Description of Solution Approach

The total cycle time of 49 seconds is achieved by adding all of the activities of the robot by including the machining time and other related activities. The production rate is the reciprocal of cycle time. The production rate considering system availability is therefore

Production rate = 1 unit /49 sec. (60 s / min) (60 min / h) (  8 h/ shift) (0.85% uptime)

                       = 500 units per shift

Machine Utilization = Machine cycle time /Total cycle time

                           = 35/49 = 0.7142 or 71.42%

Robot utilization = Robot cycle time /Total cycle time

                        = 14/49 = 0.2857 or 28.57


Related Discussions:- Calculate the cycle and production rate

Factored axial load, You have been selected to assist the structural engine...

You have been selected to assist the structural engineer for a bridge replacement project.  Your task is to design the size of the footing for an interior bridge pier, based on the

Merchant force circle diagram, (a) Draw neatly and accurately the Merchant ...

(a) Draw neatly and accurately the Merchant force circle diagram. Mention clearly the forces involved, the constructional steps and the assumptions made [do not derive the forces]

Determine the thermal efficiency of cupola, With the help of neat diagrams ...

With the help of neat diagrams explain various parts of Cupola. Define its operation. How the thermal efficiency of Cupola calculated? What do you mean by Die casting process? G

Cad-cam data exchange, CAD-CAM Data Exchange: The interface SET transf...

CAD-CAM Data Exchange: The interface SET transferred information on wire-frames, surfaces, B-representation and FEM models as well as technical drawings and scientific data. I

Cutting test, Cutting Test:             Once the sand blasted blade we...

Cutting Test:             Once the sand blasted blade were went through the washing process. Quality Control technician will randomly pick 15 pieces of blade to go for cutting

Explain tee joints, Tee joints -The square tee joint requires a fillet weld...

Tee joints -The square tee joint requires a fillet weld that can be made on one or both sides. It can be used for light or fairly thick materials. For maximum strength, considerabl

Rigid bodies, A sign of uniform density weighs 270 lb and is supported by a...

A sign of uniform density weighs 270 lb and is supported by a ball-andsocket joint at A and by two cables. Determine the tension in each cable and the reaction at A.

Application of cost-volume-profit relationships, Application of Cost-Volume...

Application of Cost-Volume-Profit Relationships: Quality stores open for 10 hours a day. Company is considering decreasing the store hours through one hour. This shall resul

Calculation of total energy - thermodynamics, T ota l Energy: Total ...

T ota l Energy: Total energy possessed by system is the sum of all types of stored energy. Thus it will be given by E total  = PE + KE + U = mgh + 1/2mv 2  + U It is ex

Determine the net rate of work output, A piston and a cylinder machine obta...

A piston and a cylinder machine obtains a fluid system, which passes through a complete cycle of four processes. In the mean while a cycle the sum of all heat transfer is 150KJ and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd