Calculate the Cycle and Production Rate for Single-Machine Robotic Cell

Determine the cycle and production rate for a single-machine robotic cell for an 8-hr shift if the system availability is 85%. Also find out the percent utilization of machine and robot. On average, the machine takes 35 sec. to process a part. The other robot operation times are as follows:

Robot moves the shaft to the lathe                                            1.5 sec

Robot unloads the shaft from the lathe                                       0.5 sec

Robot picks a shaft from the conveyor                                        4.0 sec

Robot loads the shaft onto the lathe                                          1.0 sec

Robot moves the conveyor                                                        1.5 sec

Robot puts the shaft on the outgoing conveyor                            0.5 sec

Robot moves from the output conveyor to the input conveyor        5.0 sec

Description of Solution Approach

The total cycle time of 49 seconds is achieved by adding all of the activities of the robot by including the machining time and other related activities. The production rate is the reciprocal of cycle time. The production rate considering system availability is therefore

Production rate = 1 unit /49 sec. (60 s / min) (60 min / h) (  8 h/ shift) (0.85% uptime)

                       = 500 units per shift

Machine Utilization = Machine cycle time /Total cycle time

                           = 35/49 = 0.7142 or 71.42%

Robot utilization = Robot cycle time /Total cycle time

                        = 14/49 = 0.2857 or 28.57


Related Discussions:- Calculate the cycle and production rate

Mechanics of solids, What is Principle of superposition (Uniform cross-sect...

What is Principle of superposition (Uniform cross-section s/t multiple loads)

Cyclic service for vessels, when does the cyclic service apply for pressure...

when does the cyclic service apply for pressure vessels in batch plant (operation)

What is the pull required on brake arm to stop wheel, A simple band brake p...

A simple band brake performs on a drum of 600mm in diameter that is running at 200 r.p.m. The coefficient of friction is 0.25. The brake band has a contact at 270 o one end is fas

Symbol, I need a symbol for push and turn

I need a symbol for push and turn

Java Language and Virtual Machine Specifications, I need assignment help in...

I need assignment help in Java Language and Virtual Machine Specifications, write short notes on Java Language and Virtual Machine Specifications.

Process selection and sequencing, Process Selection and Sequencing In th...

Process Selection and Sequencing In this, some factors, which have an influence in all processes, are discussed. The factors include size, shape complexity, tolerances and produ

Implementation of material requirement planning, Implementation of Material...

Implementation of Material Requirement Planning: The total requirements for a material from an MRP schedule are given in the following table :

Show the coating application, Q. Show the Coating Application? Immediat...

Q. Show the Coating Application? Immediately following surface preparation, the cleaned pipe shall be uniformly preheated by a non-contaminating method to the application tempe

Clausius inequality - thermodynamics, Clausius inequality - thermodynamics:...

Clausius inequality - thermodynamics: Whenever closed system undergoes cyclic process, cyclic integral is less than zero (that is negative) for an irreversible cyclic process

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd