A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts spaced at 10-ft centers and an ornate picket infill panel. The material costs for this scope of work is most nearly:

Solution:  Develop a Bill of Materials and multiply quantities by the costs:

Aluminum Posts:  26 x $645.35 = $16,779.10

Picket Infill Panel 25 x $1,985.50 = $49,637.50

    Grand Total   $66,416.60


Related Discussions:- Calcculate the material costs

Problems in turbid water - underwater inspection of bridge, Define Problems...

Define Problems in turbid water - underwater inspection of bridge? There are three main problems, which limit the viewing performance of an underwater camera. These are: -

Building classification, Why I is the missing after h and J is written in t...

Why I is the missing after h and J is written in the classification of building

Example of pure bending, • The bar carries equal weights at equal distances...

• The bar carries equal weights at equal distances from the weight lifter's hands • The reactions (R) at the hands must be equal and opposite to the weights • The pair of for

Explain the statements about the differential levelling, Explain the Statem...

Explain the Statements about the Differential Levelling I.  Bench mark (BM) - relatively permanent point of known elevation as indicated on the Contract drawings  II. Back s

State the short term effects of concrete, State the Short Term Effects of c...

State the Short Term Effects of concrete These are various types of effects produced, nearly instantaneously, due to the application of external loads on structures. An example

Stacking of materials for building, briefly explain the stacking of materia...

briefly explain the stacking of materials in the site for general building?

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Construction of the building, a) Certain data for the materials used in the...

a) Certain data for the materials used in the construction of the building, e,g, insulation, building materials, air spaces, etc.  b)  Draw, with appropriate dimensions, the cro

Traditional granular sub-base, Question For rigid pavement, what is rec...

Question For rigid pavement, what is recompense of using lean concrete sub-base instead of traditional granular sub-base? Answer There are some shortcomings of using

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd