Calcculate the material costs, Civil Engineering

Assignment Help:

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts spaced at 10-ft centers and an ornate picket infill panel. The material costs for this scope of work is most nearly:

Solution:  Develop a Bill of Materials and multiply quantities by the costs:

Aluminum Posts:  26 x $645.35 = $16,779.10

Picket Infill Panel 25 x $1,985.50 = $49,637.50

    Grand Total   $66,416.60


Related Discussions:- Calcculate the material costs

Construction mesurment, Measurement quantity of excavation, concrete, formw...

Measurement quantity of excavation, concrete, formwork as my assignment brief.

Timber, what are the defects in timber

what are the defects in timber

Offset(survey)., what is meant by the offsets and explain its type?

what is meant by the offsets and explain its type?

State about the pre-tensioned concrete, State about the pre-tensioned concr...

State about the pre-tensioned concrete In pre-tensioned concrete, the tendon stresses are transferred  to concrete by  virtue of bond  of concrete to the  surface of steel tend

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Show the application of concrete crash barriers, Q. Show the application of...

Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl

Moment redistribution, how to draw the shear diagram after redistribution o...

how to draw the shear diagram after redistribution of moments

TicketID: EM135335A06, I only want Part 1 of this order, can you adjust the...

I only want Part 1 of this order, can you adjust the quote?

Treatment plant - sewer construction, Treatment plant - sewer construction:...

Treatment plant - sewer construction: Problem: How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant? Solution An a

Structural analysis_cantilever trusses, Obtain the values and direction of ...

Obtain the values and direction of the supporting reactions of the truss given below. Use the method of section to determine the forces in each member.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd