Calcculate the material costs, Civil Engineering

Assignment Help:

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts spaced at 10-ft centers and an ornate picket infill panel. The material costs for this scope of work is most nearly:

Solution:  Develop a Bill of Materials and multiply quantities by the costs:

Aluminum Posts:  26 x $645.35 = $16,779.10

Picket Infill Panel 25 x $1,985.50 = $49,637.50

    Grand Total   $66,416.60


Related Discussions:- Calcculate the material costs

Determine the probable period of time, A clay stratum is 4.5 m thick and re...

A clay stratum is 4.5 m thick and rests on a rock surface. The coefficient of consolidation of a sample of this clay was found to be 4.5 × 10-8 m 2 /s in the laboratory. Verify pro

Pulverized fly ash as cement replacement, Q. Pulverized fly ash as cement r...

Q. Pulverized fly ash as cement replacement? Pulverized fly ash is a type of pozzolans. It is analuminous or siliceous material that possesses no binding ability by itself. Whe

Insurance required to be incorporated in deal, Question Is procurement ...

Question Is procurement of third party insurance required to be incorporated in deal for construction works? Answer Purpose of third party insurance is to guard contra

Ground water, Two pumping wells 1,000 m away fully penetrate the same confi...

Two pumping wells 1,000 m away fully penetrate the same confined aquifer. One of the wells pumps at a rate of 1,240 m3/day. The second well pumps at 850 m3/day. If the aquifer has

Physics, about lenses & mirrors for assignment

about lenses & mirrors for assignment

State the laws governing compaction of cohesion less soils, a) What are th...

a) What are the laws governing compaction of (i) cohesion less soils like sand and (ii) moderately cohesive soils like sandy clay ? b) To what compaction pressure does the

Diferential equations, show that Y = 4e2x - 2e-3x is a solution of initia...

show that Y = 4e2x - 2e-3x is a solution of initial-value problem (d2y)/(dx2)+ (dy)/(dx) - 6y=0 ; y(0)=6 ; y’(0)=2 . is Y = 2e2x - 4e-3x also a solution of this proble

Amount of water that added to achieve the optimum moisture, Geotechnical pr...

Geotechnical project specifications require that the soil's optimum moisture content of 24% be maintained during the roadbed's construction.   The field moisture test finds that fi

Docks, DOCKS: Types of Docks Docks are artificial enclosures ...

DOCKS: Types of Docks Docks are artificial enclosures for the reception of ships. Three types of docks are found : (a)        Harbour Docks, or Wet Docks, which ar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd