Question
Does occurrence of rust have adverse collision to bond performance of bar reinforcement?

Answer
In fact, presence of rust in bars cannot have adverse impact to the bond performance and it depends on sorts of bar reinforcement in consideration.

In plain round bars, rust on bars improves bond presentation by formation of rough surfaces which enhances friction amid steel and concrete.

But, for deformed bars, same theory cannot concern. Presence of rust impairs bond strength since corrosion occurs at raised ribs and subsequently fills space between ribs, therefore evening out unique deformed shape. In essence, bond between concrete and deformed bars originates from mechanical lock among raised ribs and concrete. On contrary, bond between concrete and plain round bars obtains from adhesion and boundary friction. With such distinction in mechanism in bonding, behaviour of bond between deformed bars and plain round bars in occurrence of rust varies.

 


Related Discussions:- Bond performance of bar reinforcement

Theodolite, definion of local attraction and correction

definion of local attraction and correction

Landslides induced by rainfall, Landslides induced by rainfall After r...

Landslides induced by rainfall After rainfall, groundwater pressure is built up and this elevates ground water table. Water inside the pores of soil reducesthe effective stres

Moisture content, What is moisture content for road work

What is moisture content for road work

Define collisions - underwater inspection of bridge, Define Collisions - Un...

Define Collisions - Underwater Inspection of Bridge? Structural damage to underwater portions of a bridge can either be collision related or direct result of a collision. Colli

Describe the behaviour of pre and post-tensioned members, Describe the beha...

Describe the behaviour of pre and post-tensioned members The behaviour of pre and post-tensioned members under imposed loads may be different, especially when the cracking patt

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd