Q. Sand layer vs. cement sand used as bedding of precast concrete paving units

Cement sand is a mixture of sand and cement and it behaves as a cohesive mass once mixed. Usually a 20mm to 30mm sand layer is laid beneath precast paving block units. Though in locations of steep gradients where it stands a high possibility that rain runoff will wash out in filling sand and sand layers, cement sand should be sued instead. Correspondingly when high pressure jetting is anticipated to be used frequently in routine maintenance, sand layers beneath precast paving block units isn't preferable due to the reason of potential washing out of sand.


Related Discussions:- Bedding of precast concrete paving units

Precaution of damp, i need simple ans for this question tell me precaution ...

i need simple ans for this question tell me precaution of dampness

Bearing capacity, which kind of pile can increase the bearing capacity, if ...

which kind of pile can increase the bearing capacity, if the water level high in sang soil surface?

Residual stresses in steel after welding, Q. Residual stresses in steel aft...

Q. Residual stresses in steel after welding? Considerable residual stresses are persuaded in connecting steel members after welding operation. Local temperature of steel where

Principal stresses and strains, Principal Stresses and Strains: Princi...

Principal Stresses and Strains: Principal Stresses and Strains is a very important link in the analysis of solids so as to make sure safe design of different components of str

Define about the inclined borings, Define about the Inclined Borings In...

Define about the Inclined Borings Inclined  brings may also be used in exploration of  inclined strata and for the detection of weak pockets (lenses),  buried channels,  caviti

Stress design method, You have been selected to assist the structural engin...

You have been selected to assist the structural engineer for a bridge replacement project.  Your task is to design the size of the footing for an interior bridge pier, based on the

Calculate surface loading rate for each clarifier, A wastewater plant is op...

A wastewater plant is operating at 10MGD with a suspended solids concentration of 200mg/L. It has 6 clarifiers operating in parallel. Each clarifier is 40 foot in diameter and 10 f

Determine the soil shrinkage, Soil at a borrow area has a total unit weight...

Soil at a borrow area has a total unit weight of 120-PCF and a water content of 15 percent.  The soil from the borrow area will be used as structural fill and compacted to an avera

Surveying, Describe the two fundamental purposes of surveying

Describe the two fundamental purposes of surveying

Parallel pipe systems or multipath pipeline problems, Parallel Pipe Systems...

Parallel Pipe Systems or Multipath Pipeline Problems Two or more sections of piping (branches) of different diameters, lengths and/or pipe materials originating and terminating

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd