Asic based new product development project, Electrical Engineering

Assignment Help:

Assume you are working for an SME operating in the microelectronics sector. You are required to plan a new product development project. This is an internal project, so it does not generate any income during the development phase.

The product will be ASIC based and will be sold in fairly high volumes - about 50,000 units/month when sales become established.

Initial considerations indicate that the product will comprise the following:

  • a small plastic base and a plastic cover that clips to the base.
  • a small LCD that will be capable of displaying simple alphanumeric data, which will mount inside the cover.
  • a double sided PCB populated by surface mount components.
  • a simple "keyboard" using 6 keys, to be mounted on the front of the case cover.
  • an ASIC that will have about 12 pins. The ASIC will be die bonded and wire bonded to the PCB.

Requirements

Product development plan in Microsoft Project

The project plan should be commented in detail using the task notes facility within MSP. Produce a calendar and resource pool for the project: remember an SME will not employ many development engineers. The project should be fully costed so appropriate costs should be assigned to the project resources.


Project risk log and risk reduction strategies

ASIC risks should be included as well as risks associated with other tasks. Where appropriate, low cost strategies for reducing risk should be suggested.


Structured meetings directory

This will include an outline meeting agenda, an outline meeting minutes document and an outline action list.

Short report providing an overview of the proposal

This will explain the rationale behind your proposal and items of particular interest, such as the project risk log and risk reduction strategies. State any assumptions you make, for example about the resources available for the project.

Where appropriate the rationale associated with the activities, the development plan, the structured meetings directory, the proposal overview and the project implementation should be included.

The report should be structured, i.e. sections, diagrams and tables should be numbered. There should be a title page and a table of contents.

Project Implementation and Review

When you are satisfied with project plan, you should create a project baseline and start the project on the planned start date. This should be completed at the end of week 7. Note that you may subsequently change your project plan if you wish.

From week 8 onwards you should record project progress on selected tasks in the MSP plan on a weekly basis. Be sure to save the MSP project plan when you do this each week. In this way, you should end up with a series of 5 or more sets of files from earlier weeks which will be valuable later when it comes to undertaking the project review.


Related Discussions:- Asic based new product development project

Give examples of natural insulating materials, Give four examples of natura...

Give four examples of natural insulating materials. Illustrations of the natural insulating materials are rubber, cotton, wood and mica.

Transistor Amplifier, I need help designing a BJT amplifier with that meets...

I need help designing a BJT amplifier with that meets the following parameters: voltage gain greater than 300, Ic(Vce=0)=2uA, Vcc=20V.

The cross-sectional area of a wire of the same length, Some wire of cross-s...

Some wire of cross-sectional area 1mm 2 has a resistance of 20Ω. Determine: a)  The resistance of a wire of the same length and material if the cross-sectional area is 4 mm 2 .

What is barkhausen criterion, Q. What is Barkhausen criterion? Why is the v...

Q. What is Barkhausen criterion? Why is the value of Ab kept slightly greater than 1? The condition |Ab| = 1 is called the Barkhausen criterion. It implies that when |Ab| = 1,

When mt2 is negative and g is positive , When MT 2 is Negative  and g is ...

When MT 2 is Negative  and g is positive In this  case  gate  current  flows  through  junctions P 2 N 2   electrons  are injected from  N 2   layer to  P 2   a result  junct

Explain the working of direct memory access controller, Explain the various...

Explain the various modes in which DMAC works. Working of Direct memory access controller: The modes of operation has demand mode, block mode, single mode and cascade mode.

Math, How you write this number in letters. 20,000.000.000

How you write this number in letters. 20,000.000.000

What is macro, What is macro? A macro is a group of instructions writte...

What is macro? A macro is a group of instructions written within brackets  and recognized  by a name .This is used when a repeated group of instructions is too short or not app

Inductive coupling, #question. i want design of inductive coupling to trans...

#question. i want design of inductive coupling to transfer power @ 2 watt in air gap of 5mm radial distance..

Partial indicators method, Partial Indicators Method The partial indic...

Partial Indicators Method The partial indicators technique consists of calculating various measures of the financial, operating, commercial, and quality of a business's perfor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd