Part A Junee Auto Parts (JAP) are planning to expand their factory to cope with the additional demand for their products and have requested your help as an external consultant. IAP wants to determine what is involved in the project and how soon it can be completed. They have asked for a plan in the form of a Gantt Chart and Critical Path Network with relevant activity times, project duration and identification of the critical path. In the initial planning stages, you have decided that there are three major components (or sub-projects) in this expansion project - building, processing equipment and material handling system. After spending a few weeks in scoping the work, you have established a list of activities according to the three major components. Details of these are as follows: BUILDING A1 Design Building A2 Ordering of Materials A3 Construction of Building PROCESS EQUIPMENT B1 In house Design of Equipment B2 Detailed Design by Consultant B3 Tender Exercise for Equipment B4 Installation and Commissioning of Equipment MATERIAL HANDLING SYSTEM C1 Study of Processing Equipment by Consultant C2 Design of Material handling Equipment C3 Purchase of Equipment C4 Installation and Commissioning Discussions with contractors and the client have helped you to draw up a table of estimated durations for the activities and the relationships among them as indicated below. Write a report on the project plan to senior management of JAP, offering sufficient information for senior management to review and understand the implications of embarking on such a project.
Activity
Preceding Activity
Duration
(in weeks)
A1
None
6
A2
5
A3
1
B1
2
B2
8
B3
4
B4
C1
C2
C3
C4
Part B You realise that the information that JAP has requested is inadequate and suitable for only basic planning purposes. In a second section of the report, present your recommendations on what other information is relevant and what techniques and systems should be used to plan, monitor and control the project.
The data for the last week follows: Day # of Non-conformities 1 2 3 4 5 5 10 23 20 15 Construct a 3 standard deviation c chart of non-conformities. Elucidate what the control chart tells you about the IRS telephone operators
What are the major causes of absenteeism at work? How can companies minimize the level of absenteeism that takes place?
Acting as a merchandise buyer for a fictitious store, the University Boutique.First develop the retailer's six-month buying plan. Secondly develop the retailer's merchandise assortment plan.
determine the three-sigma control limits for defects per shirt. b. Suppose that the next shirt has 13 flaws. What can you say about the process now?
Based on the organization you selected, write a marketing plan of 750-1,000 words. Be sure to address the following, Describe the 4Ps of marketing in your organization?
Morton Financial must decide on the percentage of available funds to commit to each of two investments, referred to as A and B, over the next four periods.
What is vertical integration? Give examples of backward and forward integration.
The owner of a motel is considering outsourcing the daily room cleanup to Duffy's Maid Service. The manager rents an average of 50 rooms for each of 365 nights.
Address the impact on the project parameters as a result of these changes.
Think back to the executive who recognized employees with motivational stickers, like "Dynamite." Illustrate what impact might such a sticker have on your job performance also satisfaction.
Holding expenses of inventory are 24% of purchase price every year. Elucidate how much should be ordered each time to minimize total cost.
Computed the forecasting error using the exponential smoothing technique and computed the forecasting error using the weighted smoothing average method.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd