Part A

Junee Auto Parts (JAP) are planning to expand their factory to cope with the additional demand for their products and have requested your help as an external consultant. IAP wants to determine what is involved in the project and how soon it can be completed. They have asked for a plan in the form of a Gantt Chart and Critical Path Network with relevant activity times, project duration and identification of the critical path. In the initial planning stages, you have decided that there are three major components (or sub-projects) in this expansion project - building, processing equipment and material handling system. After spending a few weeks in scoping the work, you have established a list of activities according to the three major components. Details of these are as follows:

BUILDING
A1 Design Building
A2 Ordering of Materials
A3 Construction of Building

PROCESS EQUIPMENT
B1 In house Design of Equipment
B2 Detailed Design by Consultant
B3 Tender Exercise for Equipment
B4 Installation and Commissioning of Equipment

MATERIAL HANDLING SYSTEM
C1 Study of Processing Equipment by Consultant
C2 Design of Material handling Equipment
C3 Purchase of Equipment
C4 Installation and Commissioning

Discussions with contractors and the client have helped you to draw up a table of estimated durations for the activities and the relationships among them as indicated below.

Write a report on the project plan to senior management of JAP, offering sufficient information for senior management to review and understand the implications of embarking on such a project.

Activity

Preceding Activity

Duration

(in weeks)

A1

None

6

A2

A1

5

A3

A2

1

B1

A1

2

B2

B1

8

B3

B2

4

B4

B3

4

C1

B2

2

C2

C1

4

C3

C2

4

C4

C3

4

Part B

You realise that the information that JAP has requested is inadequate and suitable for only basic planning purposes. In a second section of the report, present your recommendations on what other information is relevant and what techniques and systems should be used to plan, monitor and control the project.

Reference no: EM13230696

Questions Cloud

Define the crystallographers : Usually in solving a crystal structure, the known amino acid sequence is built into the electron density. Mistakes in the protein sequence can be discovered by the X-ray crystallographers.
What is the economic order quantity : The price of each valve is $76, the inventory carrying cost is $5, and the ordering cost is $150 per order. What is the economic order quantity?
Services to offer customers in the nashville region : Comcast and Verizon are considering which services to offer customers in the Nashville region.
Compute the solubilities of the compounds : Calculate the solubilities of the following compounds in a .0333M solution of Mg(CIO4)2 using 1. activities and 2. molar concentrations
Write a report on the project plan : Write a report on the project plan to senior management of JAP, offering sufficient information for senior management to review and understand the implications of embarking on such a project.
An environment of extreme price competition : List three strategies that can be used by firms to enhance profits in an environment of extreme price competition.
What is difference between significance and meaningfulness : What is the difference between significance and meaningfulness? Which one is more important to experimental results and why do you think so?
What factors could cause the monopolies to end : 2.What factors could cause the monopolies to end? Is there a difference between
Discuss also how organisations can be persuaded : Discuss also how organisations can be persuaded to adopt modern inventory control methodologies - Explain how such a basic mathematical model used in this question (the EOQ or Quantity Discount modes) can be altered to make it more realistic to inc..

Reviews

Write a Review

Operation Management Questions & Answers

  Elucidate what the control chart tells you about the irs

The data for the last week follows: Day # of Non-conformities 1 2 3 4 5 5 10 23 20 15 Construct a 3 standard deviation c chart of non-conformities. Elucidate what the control chart tells you about the IRS telephone operators

  Explain the major causes of absenteeism at work

What are the major causes of absenteeism at work? How can companies minimize the level of absenteeism that takes place?

  Developing merchandise buying plan for marketing

Acting as a merchandise buyer for a fictitious store, the University Boutique.First develop the retailer's six-month buying plan. Secondly develop the retailer's merchandise assortment plan.

  Determine the three-sigma control limits for defects

determine the three-sigma control limits for defects per shirt. b. Suppose that the next shirt has 13 flaws. What can you say about the process now?

  Describe the 4ps of marketing in organization

Based on the organization you selected, write a marketing plan of 750-1,000 words. Be sure to address the following, Describe the 4Ps of marketing in your organization?

  Maximize the cash value for the firm at the end

Morton Financial must decide on the percentage of available funds to commit to each of two investments, referred to as A and B, over the next four periods.

  What is vertical integration

What is vertical integration? Give examples of backward and forward integration.

  Determine the crossover point for the two options

The owner of a motel is considering outsourcing the daily room cleanup to Duffy's Maid Service. The manager rents an average of 50 rooms for each of 365 nights.

  Address the impact on the project parameters as a result

Address the impact on the project parameters as a result of these changes.

  Illustrate what impact might such a sticker have

Think back to the executive who recognized employees with motivational stickers, like "Dynamite." Illustrate what impact might such a sticker have on your job performance also satisfaction.

  Elucidate how much should be ordered each time to minimize

Holding expenses of inventory are 24% of purchase price every year. Elucidate how much should be ordered each time to minimize total cost.

  Computed the forecasting error

Computed the forecasting error using the exponential smoothing technique and computed the forecasting error using the weighted smoothing average method.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd