Which of the following is not one of the growth levels

Assignment Help Operation Management
Reference no: EM131392545

Oversight

Project Management Ch 16

6th Edition

1:The term that can be defined as a set of principles and processes to guide and improve the management of projects is

A)Project administration

B)Fiduciary responsibility

C)Management

D)Project oversight

E)Project regulation

2:The intent of project oversight includes all of the following EXCEPT

A)Meet the needs of the organization through procedures

B)Support the project manager

C)Meet the needs of the organization through continuous improvement

D)Meet the needs of the organization through improving everyday business activities

E)Meet the needs of the organization through accountability

3:Typical activities of project oversight cover which two dimensions?

A)Organization and project

B)Project and customer

C)Customer and industry

D)Industry and organization

E)Organization and customer

4:At the project level, all of the following are examples of oversight activities EXCEPT

A)Review project objectives

B)Track and assist the project to resolve bottlenecks

C)Project selection

D)Review status reports

E)Audit and review lessons learned

5:The centralized management of projects to ensure that the allocation of resources to projects is directed toward projects that contribute the greatest value to organization goals is known as

A)Portfolio Project Management

B)Project Office Management

C)Project Management Optimization

D)Project Priority Matrix Management

E)Resource Allocation Optimization

6:Project office functions typically include which of the following?

A)Create and maintain the internal project management information system

B)Recruit and select project managers

C)Train personnel in project management techniques

D)Develop risk management programs

E)All of these are typically functions of the project office

7:The in-depth review of individual projects at specific phases in the project life cycle is known as

A)Project Assessment Checkpoint Reviews

B)Go/Kill Decision Review Methodology

C)Phase Gate Methodology

D)Stargate Review Methodology

E)Project Implementation Review

8:During which of the following phase gates would the question of "Does this project align with our strategic direction?" be answered?

A)Proposal

B)Screening and selection

C)Implementation plan

D)Progress evaluation

E)Closure

9:During which of the following phase gates would the questions "Are the resources needed identified and available?" and "Are tasks sequenced and is a time-phased budget established?" be answered?

A)Proposal

B)Screening and selection

C)Implementation plan

D)Progress evaluation

E)Closure

10:Which of the following is not one of the growth levels in the Organization Project Management Maturity Model (OPM3TM)?

A)Repeatable (formal application of project management)

B)Defined (institutionalization of project management)

C)Managed (management of project management system)

D)Expanded (expansion of project management system)

E)Optimized (optimization of project management system)

11:The first appearance of standard approaches to managing projects including scope statements and WBS occurs in which of the following Project Management Maturity Model Levels?

A)Ad Hoc Project Management

B)Formal Application of Project Management

C)Institutionalization of Project Management

D)Management of Project Management System

E)Optimization of Project Management System

12:Project audits are performed on all significant projects and lessons learned are recorded and used on subsequent projects in which of the following Project Management Maturity Model Levels?

A)Ad Hoc Project Management

B)Formal Application of Project Management

C)Institutionalization of Project Management

D)Management of Project Management System

E)Optimization of Project Management System

13:Each gate within the phase gate review process should, at a minimum, include the following EXCEPT

A)Required deliverables

B)A plan to proceed

C)Gate criteria

D)Specific outputs

E)A clear yes/no decision on whether to go ahead

14:In which of the following Project Management Maturity Model Levels is the focus is on continuous improvement through incremental advancements of existing practices and by innovations using new technologies and methods?

A)Ad Hoc Project Management

B)Formal Application of Project Management

C)Institutionalization of Project Management

D)Management of Project Management System

E)Optimization of Project Management System

15:The balanced scorecard model differs from selection models by reviewing projects over a longer horizon ___________ after the project is implemented.

A)1-2 years

B)1-5 years

C)5-10 years

D)10-15 years

E)15 years

Reference no: EM131392545

Questions Cloud

Show how the gauges are connected in a bridge : Show how the gauge mounting in given Figure can be changed so that all four gauges are active but temperature compensation is still provided. Show how the gauges are connected in a bridge.
Write a report on the concept of tolerable risk : write a report (that includes three references) on the concept of tolerable risk and risk reduction. In this report, provide definitions for hazard, probability, residual risk, risk, safety, severity, and tolerable risk.
What sensor voltage results for range of specific gravity : What is the pressure of water at the sensor? What is the range of pressure of the liquid at the sensor?- What sensor voltage results for the range of 1.0 to 2.0 specific gravity?
Solve the health problem and/or reduce citizen complaints : What are the advantages and disadvantages of such a system of "distributing" the pollution? Does spreading the pollution solve the health problem and/or reduce citizen complaints?
Which of the following is not one of the growth levels : The centralized management of projects to ensure that the allocation of resources to projects is directed toward projects that contribute the greatest value to organization goals is known as.During which of the following phase gates would the quest..
Advantages and disadvantages of allowing gambling : what would your state engineering board provide as guidelines, if any, for your conduct as an engineer? From a sociological perspective, what are the advantages and disadvantages of allowing gambling?
Find the general equilibrium allocation for tax equal : Consider the Robinson Crusoe Economy in the Post-Walras Arrival Age. Robinson’s utility function over yams (y) and leisure (l) is U ( y , l )= √2 y +l . Robinson’s endowment of time is L. The production function for yams is y = h where h is the amoun..
Advantages and disadvantages of the government : Can these incentives be gamed, i.e., interest and competitiveness created and made an activity that companies participate in.?
What does this imply about the indifference map : Consider an individual with the following utility function: U(r, y) = ln(r+ 1) + y. The marginal utility of r is 1/(1 + r); the marginal utility of y is 1. Find the marginal rate of substitution of y for r. Is there anything unusual about the MRSyr? ..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd