Which activity or activities should be crashed

Assignment Help Operation Management
Reference no: EM13251553

The managing partner of the Scott Corey accounting firm has decided that the system must be up and running in 16 weeks. Consequently, information about crashing the project was put together and is shown in the following table:

Activity Normal time Crash time Normal Cost Crash Cost Crash cost/pd Crash by Crashing cost

Project 17 10

A 3 2 8000 9800 1800 1 1800
B 4 3 9000 10000 1000 0 0
C 6 4 12000 15000 1500 2 3000
D 2 1 15000 15500 500 1 500
E 5 3 5000 8700 1850 2 3700
F 2 1 7500 9000 1500 1 1500
G 4 2 8000 9400 700 2 1400
H 5 3 5000 6600 800 2 1600
TOTALS 69500 13500

(a) If the project is to be finished in 16 weeks, which activity or activities should be crashed to do this at the least additional cost? What is the total cost of this?

(b) List all the paths in this network. After the crashing in part (a) has been done, what is the time required for each path? If the project completion time must be reduced another week so that the total time is 15 weeks, which activity or activities should be crashed? Solve this byinspection.

 

Reference no: EM13251553

Questions Cloud

Conduct a swot analysis : Conduct a SWOT analysis (7) Make sound recommendations regarding the situation (8) Create/list the initial workable strategies that you will implement
Calculate the work done on the block by the normal force : A wooden block of mass M = 0.170 kg is placed on a wooden inclined board 0.930 m long and raised to a height h1 = 0.050 m at the lower end, calculate the work done on the block by the normal force
Find the angular velocity of the earth : Find the angular velocity of the earth as it spins on its axis and the tangential velocity of an object at the equator and one at the University of West Florida in Pensacola
Is utilization rate always an important consideration : Is "utilization rate" always an important consideration in queuing systems? Give several examples where low utilization rate is a desired characteristic.
Which activity or activities should be crashed : If the project is to be finished in 16 weeks, which activity or activities should be crashed to do this at the least additional cost? What is the total cost of this?
Find the number of moles of gas : Suppose the temperature of 4.72 L of ideal gas drops from 351 K to 275 K. (a) If the volume remains constant and the initial pressure is atmospheric pressure, Find the number of moles of gas
What masses of nacl and water are required to make solution : What masses of NaCl and water are needed to prepare 1000g of a solution that is 0.90% by mass
What is the total cost of crashing : Which activity should be crashed, and what is the total cost of crashing? (Assume that A-E-G-H remains the critical path after crashing)
Compare and contrast project management : They are different names for possibly the same thing. These are very different topics. Compare and contrast project management, program management, and project portfolio management.

Reviews

Write a Review

Operation Management Questions & Answers

  What is the maximum number of orders waiting

What is the maximum number of orders waiting to be packed? If we double the packing capacity (from 60 to 120 orders per hour), what impact does this have on your answers in parts b, c, and d?

  What is statistical process control

What is Statistical Process Control? What are the advantages and disadvantages of SPC? Identify two or three applications in your organization that could benefit from Statistical Process Control.

  Estimate brake-even point in units

Utah is a popular resort and is being developed as a hot new spring break destination. Unfortunately, Utah regularly faces shortages of fresh water.

  Explain how many units should be ordered each time

To minimize total cost, explain how many units should be ordered each time an order is placed. If the holding cost per unit was $6 instead of $5, illustrate what would the optimal order quantity be.

  A manager is quite concerned about the recent deterioration

A manager is quite concerned about the recent deterioration of a section of the roof on a building that houses her firm's computer operations.

  What would be your goal in each area

what would be your goal in each area, and what measures would you use? What would be your rationale?

  Elucidate how large a sample size is necessary to estimate

Elucidate how large a sample size is necessary to estimate proportion of walkers with low blood pressure within 10% with 95% confidence.

  How do groups interact with each other both

How do groups interact with each other both from an internal and external standpoint?

  Calculate the total amount

During the 1950s and 609, Mr. T. Ohno of Toyota developed the k a n Production System. Subsequently many other Japanese automobile companies adopted it.

  Why did mcdonald start to lose its competitive advantage

Why did McDonald's start to lose its competitive advantage in the 2000's? Whatdid it do to halt the erosion in its competitive position? What does this teachyou about the sustainability of competitive advantage?

  How does dealing with personal capacity issues differ

How does dealing with personal capacity issues differ from dealing with organizational capacity issues? Discuss with examples.

  Conduct a vrio analysis of a successful firm relative

Conduct a VRIO analysis of a successful firm relative to one of it's rivals. Contrat the value, rarity, imitabilty, and organizational aspects of its tangible and intangible

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd