Castle Company produces throw blankets that are popular holiday gifts. Standard variable costs relating to a single blanket are given below
Standard Quantity or Hours
Standard Price or Rate
Standard Cost
Direct materials
2.62 yards
$5 per yard
$?
Direct labor
1.35 DLH
$6.80 per DLH
Variable manufacturing overhead
$2 per direct labor-hour
Total standard cost
Overhead is applied to production on the basis of direct labor hours. During March, 924 blankets were manufactured and sold.
Selected information related to the month's production is given below:
Materials Used
Direct Labor
Variable Manufacturing Overhead
Actual costs incurred
$11,500
$8,408
$3,100
Direct materials price variance
?
Actual
2,620 yards
1400 hours
Direct materials quantity variance
$1,000 U
Direct labor rate variance
Direct labor efficiency variance
Variable overhead rate variance
Variable overhead efficiency variance
*For this month's production of 924 blankets
Submit an Excel document with each tab labeled by item number in good form that demonstrates the following through your calculations:
1. What is the standard cost of a single blanket?
2. What was the actual cost per blanket produced during March?
3. What was the direct materials price variance for March?
4. What was the direct labor rate variance for March? The direct labor efficiency variance?
5. What was the variable overhead rate variance for March? The variable overhead efficiency variance
Toni is relying on financial feedback, and the product costing method adopted by the large bakery. What are the strengths and weaknesses of these approaches?
production cost report missing informationmarion chemicals produces a chemical used as a base in paints. in the
Energy Inc. is working on its direct labor budget for next two months. Each unit of output needs 0.77 direct labor-hours.
Determine the equivalent units of conversion. What is the conversion costs assigned to completed calendars? What amount of conversion is assigned to the ending work-in-process inventory?
Develop all of your managerial accounting reports. Examples of a few of those reports are the horizontal analyzes, vertical analyzes, and ratios.
List and describe the four perspectives of the Balanced Scorecard and what steps would you encourage him or her to take in order to successfully implement and use the Scorecard?
What should he do if he follows the EMV criterion and what is the expected value of perfect information - write a report to your manager advising - the advantages and disadvantages of simulation models
question 1 be able to describe comprehend and apply the process of theory development.theories should be evaluated
Evaluate the capital loss
The beginning work in process inventory was $20,000 and the ending work in process inventory was $11,000, What was the cost of goods manufactured for the month?
You're interested in developing the budget but are struggling with basics - do the numbers have to be exact? Can a budget have any flexibility in it? First, describe what a budget is.
There are different views of how quality can be managed. While a certain level of quality may be accepted, there is an argument to aim for the highest level of quality. Discuss these two views of "quality as cost" and "quality as value".
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd