Reference no: EM132528278 
                                                                               
                                       
question 1: Yama Corporation's actual direct labor cost for the month of July was $45,000. Its labor rate variance for July was $1,000 unfavorable. Its labor efficiency variance was $5,000 favorable. What summary journal entry would Yama make to record this information?
1. DR: Work in Process               41,000
DR: Labor Efficiency Variance      5,000
CR: Labor Efficiency Variance                 1,000
CR: Wages Payable                           45,000
2. DR: Work in Process              49,000
DR: Labor Rate Variance           1,000
CR: Labor Efficiency Variance                5,000
CR: Wages Payable                          45,000
3. DR: Wages Payable               41,000
DR: Labor Efficiency Variance     5,000
CR: Labor Rate Variance                    1,000
CR: Work in Process                       45,000
4. DR: Wages Payable               49,000
DR: Labor Rate Variance           1,000
CR: Labor Efficiency Variance             5,000
CR: Work in Process                      45,000