What should tom have done to avoid the present situation

Assignment Help Supply Chain Management
Reference no: EM13994168

THE BOARDROOM

In June 2002, Tom Dewey, supply manager for Builder's Bank, Inc.'s (BBI) New York office, wanted to resolve a set of problems arising from the purchase of eighty chairs for the executive boardroom.

General Company Background

BBI was a large international bank with operations throughout the world. It had recently purchased an office building and had hired the well-known architect Peter Tropper to do the major design and renovation plans.

The Supply Department

The supply department in the New York office was responsible for all local purchases, in addition to a few major purchases for the international offices. The bank did not have an approved supplier list; an invitation to bid was an indication that the potential supplier was considered qualified.

Building Renovation

The architectural firm of Peter Tropper was hired to redesign the entire building, including the selection of furniture. Once the design was completed, a working group, including the president and vice president, had approved the design, including selection and color for all major furniture. The supply department did not participate in this process.

In June 2001, Peter Tropper sent a specification sheet to the supply department for all purchases, which included model number and manufacturer. Suppliers would bid on the same manufacturer, with no substitutions allowed. Although the department had the option to split the order between suppliers, Tom Dewey decided to order through a single source.

In late June, the working group asked Tom Dewey to submit a budget of what the bank would have to spend to complete the renovation during fiscal 2002. Therefore, in early July, Tom Dewey submitted a request for proposal (RFP) to ten potential suppliers, all of which responded.

When the bids were received in mid-August, the working group reviewed the bids and rejected them as being too high. The working group and Peter Tropper agreed to a scaling down of the work proposed. A week later, Tom Dewey sent new specifications to the same ten suppliers, of which eight responded. The low bid on the RFP was $1.3 million, submitted by ABCO Furniture, a large local furniture dealer. In September, the working group authorized Tom Dewey to purchase major furniture and the chairs for the executive boardroom totaling $400,000.

Chairs for the Boardroom

Among the items on the RFP were eighty leather chairs for the executive boardroom. These chairs had a single pedestal and a fixed jury base, which would not allow the chairs to rock or swivel. Twelve of the chairs, costing $1,500 each, required installation in concrete, with the remaining sixty-eight chairs, costing $1,300 each, having bases that could be installed on wood flooring. The RFP made no mention of installation.

In February 2001, ABCO Furniture informed Tom Dewey that the chairs were ready. Since the boardroom was still under construction, he arranged to have ABCO store the chairs, with the agreement that he honor the invoice in March. The invoice was paid in late March and ABCO stored the chairs until they were delivered on the morning of April 22, 2001.

When the chairs were delivered, the construction manager talked with Peter Tropper regarding installation. The construction manager told Tom Dewey that the architect had said he would give detailed drawings regarding installation of the chairs, although the drawings had not been received. When Tom Dewey asked Peter Tropper about the problem, Peter indicated that Supply, having bought the chairs, was responsible for installation. Peter Tropper also stated that he had informed Supply, by letter in late March, that Supply was responsible for installation.

At the instruction of Tom Dewey, ABCO hired a local installer to install the chairs. The installer had seen neither the chairs nor the boardroom before. The installer arrived late on the 22d and discussed the installation procedure with the construction manager. They concluded that they would use expansion bolts in the concrete and wood screws in the platforms. Both the construction manager and the installer agreed that long lag screws could not be used since the platforms were elevated, with electrical conduit underneath.

After installing a few chairs on the morning of April 23d, the installer and construction manager concluded that the wood screws would not hold. Since the chairs were rigid, the smallness of the diameter of the base was insufficient for the torque applied to the base when the chair was used. Since no adequate support was designed into the floor when the room was remodeled, other support alternatives had to be evaluated.

The construction manager contacted the field representative of Peter Tropper and explained the problem. Peter Tropper indicated that toggle bolts were required. As a check on the architect, the construction manager called the furniture manufacturer in Pennsylvania. The call provided no additional information. The manufacturer's service representative stated that since they were not directly involved, they were unable to make suggestions. The representative did state, off the record, that the base was too small for the chair.

The installer, even after installing the toggle bolts, discovered that the chairs were still coming loose. In addition, the expansion bolts, installed in the concrete, would also eventually work loose. However, with the upcoming board meeting on May 6, 2001, the construction manager and installer agreed that the chairs could be used temporarily. The supplier, after discussing installation costs with the installer, told Tom Dewey that the current bill for setting up the chairs would be around $4,000. However, for the installer to do the job correctly would cost an additional $15,000.

The May 6 board meeting went smoothly, although many board members noted the instability of the chairs. In June, the executive directors expressed concern over the need to fix the chairs-and quickly. However, Tom Dewey's frequent discussions with Peter Tropper had yielded no results.

The installer billed ABCO Furniture at the end of May. In late June, Tom Dewey received a bill from ABCO for the installation of the chairs, and a copy of the invoice received by ABCO from the supplier. Tom Dewey recognized that BBI had not allowed for any additional installation costs and wondered what the best way to resolve the problem would be.

1. What alternatives are open to Tom?

2. What is the best course of action now?

3. Who is responsible for the present situation?

4. What should Tom have done to avoid the present situation?

Adapted from a case copyrighted by the Institute for Supply Management (formerly the National Association of Purchasing Management) and the School of Government and Business Administration, George Washington University. Reprinted by permission. Brian Sudweeks wrote this case during one of the ISM-sponsored case writing workshops.

Reference no: EM13994168

Questions Cloud

Prepare the current assets and current liabilities section : Prepare the current assets and current liabilities section of Parker's 2011 balance sheet, assuming Parker reports under U.S. GAAP.
What is the magnitude of the resultant force on the mass : Three 7 kg masses are located at points in the xy plane. What is the magnitude of the resultant force (caused by the other two masses) on the mass at the origin? The universal gravita- tional constant is 6.6726 x 10-11 N . m2/kg2. Answer in units ..
The complete accounting cycle without a work sheet : The Complete Accounting Cycle Without a Work Sheet: Two Months (second month optional) On May 1, 2011, Conrad Sayer opened Conrad's Repair Service. Prepare journal entries to record the May transactions. From the accounts in the ledger, prepare an ad..
What is the optimal order frequency : Sara’s Deli is famous for their delicious cupcakes and Sara purchases the cupcakes from a local bakery. The demand for the cupcakes is 400 per month. A cupcake costs Sara $5 to purchase from the bakery, and the inventory holding cost is for Sara 15%...
What should tom have done to avoid the present situation : What alternatives are open to Tom - what is the best course of action now and who is responsible for the present situation?
Watch two hours of prime-time major network : Watch two hours of prime-time major network (ABC, CBS, FOX, or NBC) television. What subculture groups are portrayed in the programs? Describe how they are portrayed. Do these portrayals match the descriptions in this text? How would you explain the ..
What is the notes effective interest rate : Reconstruct the journal entries to record the sale of the stock on January 1, 2011, and the adjusting entry to record interest revenue at the end of 2011. The company records adjusting entries only at year-end.
Calculate the weighted aggregate price index for hte prices : Zackron Associates, international corporate lawyers, use both email and fax to transmit documents. The company accountant has worked out that the price of sending a document by fax has increased from $0.25 in 1998 to $0.45 in 2003. The price of sendi..
Firms product managers should approach : Describe how each of the following firms’ product managers should approach the (i) Catholic, (ii) Protestant, (iii) born-again Christian, (iv) Jewish, (v) Muslim, and (vi) Buddhist subcultures. a. Red Bull b. Wendy’s c. The NBA d. Maxim magazine e. T..

Reviews

Write a Review

Supply Chain Management Questions & Answers

  Value stream mapping to gain a solid baseline

QUESTION What alternative first steps could you use instead of value stream mapping to gain a solid baseline prior to innovating the process?

  What are the inputs to and outputs of a supply chain

What are the inputs to and outputs of a supply chain? Why do you suggest this supply chain structure in the given situation? What are its benefits?

  Supply chain of pepsico

Research assignment on supply chain management Supply chain of PepsiCo

  Create a process flow diagram for the electric fan supply

Determine Riordan's manufacturing strategy (chase, level, or combination) and explain its benefits. Create a process flow diagram for the electric fan supply chain

  How primavera mitigated risk associate with procurement

Companies can seek the support of primavera, to assist in creating a systematic scheduling and work allotment to the contractors

  A chain of 5 pharmacies in suburban adelaide

You have recently joined a chain of 5 pharmacies in suburban Adelaide

  What types of forecasts would you want to create

As the regional manager of 27 Burger Queens, you are thinking about expanding the number of outlets in your area. What types of forecasts would you want to create in order to support your decision?

  Implications of service outsourcing for employees

Think about your own community. Draw a map that indicates each retail location and its type. Are similar types together? Are there any outliers? What are the most popular spots and are they surrounded by similar businesses?

  Contract amp procurement question good thoughts on ptn

contract amp procurement question good thoughts on ptn. however post tender negotiation sometimes gets to bid-shopping

  Design of the supply chain from a lean perspective

Analyze supply chains for various products to determine the impacts of the designs of the products supply chains - Analyze the design of the supply chain from a Lean perspective

  What were the implications for global supply chains

In 2010, Iceland experienced an epic volcanic eruption. From a supply chain and operations management chain perspective, what were the implications for global supply chains? Should planning for future events like this impact the strategy of a comp..

  Use of new open source packages

Critically analyse the theory, concepts and models of operations and information management and demonstrate an understanding of the strategic importance of information management in global organisations.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd