PRTI is a company whose primary business' focus is on upgrading servers for manufacturing companies. The company has a thorough knowledge of all aspects of its business, and a structured approach to manage this type of project, as shown below.

There are some indirect costs for the project, estimated on a daily basis: the first 30 days have indirect costs of $500/day, and all subsequent days $800/day.

below. Task

Code

Immediate Predecessor

Normal

Time

(days)

Crash

Time

(days)

Normal Cost

(x100)

Crash Cost

(x100)

Review system requirements for upgrade

A

None

3

2

$5

$20

Plan for clients

B

A

2

1

$2

$5

Gather information about your Project Server 2016 environment

C

A

2

---

$12

---

Plan to upgrade customizations

D

B & C

2

1

$28

$40

Prepare your environment for upgrade

E

D

9

6

$30

$90

Upgrade your databases and Project Web App site collections

F

E

4

2

$17

$34

Consolidate your Project Server 2016 databases to a Project Services database

G

F

2

1

$30

$32

Attach the Project Services database to the web application

H

G

3

1

$2

$4

Check your Project Services database for errors that can cause upgrade to fail

I

F

1

---

$2

---

Upgrade the Project Services database

J

I

8

5

$4

$16

Mount the Project Web App instance

K

H & J

1

---

$8

---

Check the Project Web App instance for issues that can cause upgrade to fail

L

K

2

---

$12

---

Upgrade the Project Web App instance

M

L

2

1

$34

$38

a) If the company requires a markup of 25%, what should be the total price charged for a normal [standard] project?

b) Examine and discuss PRTI's decision to propose a potential client to upgrade its server for a total amount of $50,000, completed in 31 days.

c) A key member of the project, recommended to the project manager to study the uncertainties exhibited in prior similar projects.

The project management gathered the information and found that the duration of six of the tasks could be modeled as Beta distributions.

Based on the following information (without "crushing"), what is the probability that a project could be completed between 30 and 38 days?

Activity

Normal Time

(days)

Optimist

Most Likely

Pessimist

Review system requirements for upgrade

1

3

5

Plan to upgrade customizations

1

2

4

Prepare your environment for upgrade

5

9

14

Check your Project Services database for errors that can cause upgrade to fail

0.5

1

2

Upgrade the Project Services database

5

8

12

Mount the Project Web App instance

0.5

1

1.5

Reference no: EM131923392

Questions Cloud

Rising health-insurance premiums make american businesses : Rising health-insurance premiums make american businesses less competitive and decrease workers' salaries.
Write the balance sheet for high yield fund : Write the balance sheet for HYT (Note: You just need a simple balance sheet like what we have done in class. It should have the aggregate equity.
Widely diversified investor : NVIDIA Corp. [NVDA] has a Beta of 1.45 (according to google finance) and a standard deviation of monthly returns of 9.6% since 2011.
What will happen to the wage of native workers : The 1986 Immigration Reform and Control Act (lRCA) makes it. What will happen to the wage of native workers if the penalties for hiring illegal aliens increase?
What should be the total price charged for a normal project : PRTI is a company whose primary business' focus is on upgrading servers for manufacturing companies.
Roe and retention ratio change : Assume that the ROE and retention ratio do not change. Report the answer to the nearest 0.01% (e.g., if your answer is 15.27%, submit it as 15.27).
What is the new equilibrium level of wages and employment : Suppose the supply curve of physicists is given by w = 10 + 5£, whereas the demand curve is given. What is the new equilibrium level of wages and employment?
By how much will the bond price change : A $1,000 par value bond with five years left to maturity has 6% coupon rate. Couponpayment is made annually and the bond is priced to have a 5% yield.
Illustrate the trend in the employment and wage of economist : Illustrate the trend in the employment and wage of economists as the market adjusts to this increase in demand.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd