What return period must an engineer use in the design of a bridge opening for 50% risk that flooding will occur at least once in two successive years?

Reference no: EM13303645

Questions Cloud

Calculate the flow rate through the pipe and the force : A thin-walled pipe, of diameter 4 in., is held stationary in a river flowing at 6 ft/s parallel to its axis. The pipe contains a sharp-edged orifice, of diameter 3 in., with a contraction coefficient of 0.60 based on the area.
What is the maximum possible overhang distance : A child is trying to stack two uniform wooden blocks, 12 cm in length, so they will protrude as much as possible over the edge of a table
Find what flow of water in gallons per second is required : The volume of water in a reservoir is often expressed using the unit of acre-foot. A volume of 1 acre-foot is the amount of water covering an area of 1 acre to a depth of 1 foot. Lake Mead is the largest man-made lake in the United States.
Determine the maximum current in the inductor : A 5.25 uF capacitor is initially charged to a potential of 15.0 V. It is then connected in series with a 3.55 mH inductor. What is the maximum current in the inductor
What return period must an engineer use in the bridge : What return period must an engineer use in the design of a bridge opening for 50% risk that flooding will occur at least once in two successive years
How to determine the efficiency of the pump : Water is pumped at a rate of 1.57 cfs from one large open tank into another through a 6 in diameter cast iron pipe 400 ft long. The water level in the second tank is 160 ft above the level of the first tank and the discharge end of the pipe is sub..
Find laser beam intensity will produce such a field : When a high-power laser is used in the Earth's atmosphere, the electric field associated with the laser beam can ionize the air, What laser beam intensity will produce such a field
What is the annual operating cash flow : A nine year project is expected to generate annual revenues of $114,500, variable costs of 73600 and fixed costs of $14000 the annual depreciation is $3500 and the tax rate is 34% what is the annual operating cash flow?
What is the amount the firm should use as the initial cash : A new project will increase A/R by $18000, decrease A/P by $6000, increase fixed assets by $36000 and decrease inventory by $11000. What is the amount the firm should use as the initial cash flow atributable to net work capital?

Reviews

Write a Review

Civil Engineering Questions & Answers

  Check whether the pressure is adequate for service

If the elevation of the pipeline at the treatment plant is 125 m, estimate the pressure in the pipeline 1 km downstream where the elevation if 110 m. Hint: Use the Colebrook equation to estimate f, and the energy equation to estimate P2 .

  Find what design speed was used for a freeway exit ramp

a freeway exit ramp has a single lane and consists entirely of a horizontal curve with a central angle of 90 degrees and a length of 628 ft. if the distance cleared from the centerline for sight distance is 19.4ft, what design speed was used

  Determine the velocity of the solid sphere

A solid steel sphere with a specific gravity of 7.85 and diameter of 0.02 m is falling at its terminal velocity through water at 25 °C. Using either trial-and-error or a graphical approach, determine the velocity of the sphere

  Calculate the amount of heat transferred during process

The tank is heated to a pressure of 10 bar. Assuming that Xe behaves like an ideal gas with a specific heat ration of 1.7, Calculate the amount of heat transferred during the process in Kj.

  Design an algorithm that lists all possible rearrangements

Design an algorithm that lists all possible rearrangements of the symbols in a string of five distinct characters. (in pseudocode)

  Four-lane freeway on a mountainous terrain

A four-lane freeway is on a mountainous terrain with 11-ft lanes, a 5-ft right-side shoulder, and a 3-ft left side shoulder. During the peak hour there are 12% trucks and buses and 6% recreational vehicles.

  Find change in depth and in absolute water level produced

water is flowing at a velocity of 10ft/s and a depth of 10ft in a channel of rectangular section. find the change in depth and in absolute water level produced by a smooth upward step of 1 ft. a smooth downward step of 1 ft in the channel bed.

  Should bernard bid for the project assignment

Does Bernard have an unfair advantage over firms having designed the project on which he wants to bid?

  How high a column of ethyl alcohol would be required

How high (m) a column of ethyl alcohol would be required to give the same pressure as 700 mm Hg

  How much caco3 is produced per hour

A slurry containing 20 percent by weight of limestone (CaCO3) is processes to separate pure dry limestone from water. If feed rate is 2000kg/h, how much CaCO3 is produced per hour?

  Detyermine what is the percent voids in the total mix

An asphalt concrete mixture includes 94% aggregate by weight. The specific gravities of aggregate and asphalt are 2.65 and 1.0, respectively. If the bulk density of themix is 147 pcf, what is the percent voids in the total mix

  Find the value of the angle at which the projectile is fired

A projectile is fired with an initial velocity of 800 ft/s at a target B located 2000 feet above the gun A and at a horizontal distance of 12,000 feet. Neglecting air resistance, determine the value of the angle at which the projectile is fired.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd