1. What is a work package?
A grouping of components into the scope baseline
The work defined at the highest level of the WBS
The work defined at the lowest level of the WBS
Another name for the WBS
2. What does WBS stand for?
Work Breakdown Survey
Work Baseline Structure
Work Borderline Survey
Work Breakdown Structure
3. What is involved in the 'Inspection' Tool & Technique for validating scope?
Preparing, Assessing and Correcting
Addressing, Negating and Approving
Measuring, Examining and Validating
Examining, Assessing and Modifying
4. What technique plans near-term work in detail, with longer-term work given a higher level of planning?
Iterative
Rolling Wave
Sequential
Strategic Planning
5. Which of the following is NOT an activity attribute?
The assigned project Calendar
Leads and Lags
Logical Relationships
Activity Name