What is the variance in completion time for the project

Assignment Help Operation Management
Reference no: EM131258864

1. Your company has just received an order for a specially designed electric motor. The contract states that if the project is not completed 12 days from now, then beginning on the 13th day, your firm will experience a penalty of $300 per day. The table below shows the activities that need to be completed for this project, along with data on direct costs and precedence relations. (Crash Time represents the minimum activity time if it was completely crashed; the Crash Cost represents the cost of each activity if it is crashed to its minimum.)

Activity Normal Time (days) Normal Cost ($) Crash Time(days) Crash Cost($) Immediate Predecessors
A 4 1000 3 1300 None
B 7 1400 4 2000 None
C 5 2000 4 2700 None
D 6 1200 5 1400 A
E 3 900 2 1100 B
F 11 2500 6 3750 C
G 4 800 3 1450 D, E
H 3 300 1 500 F, G

a. Draw the network diagram (only draw Activity on Node).

b. Find the critical path(s). What is the normal duration (i.e. without crashing) of the entire project?

c. What is the slack time of activity D?

d. Right now, would you rather incur the late cost of $300 per day, or would you want to crash the project at some cost? What is the project completion time that you recommend for this project? Remember: it will be better to incur the penalty cost if the cost of reducing the project duration is greater than $300 per day. What are the activities that you crash, and by how much? What is the total project cost for your recommended project length?

2. Suppose a project has activities A, B, C and D. Given the table below, assess the current progress of this project. Is the project ahead or behind the schedule? By how much? Is the project over or under budget? By how much?

3. The activities of a project are shown in the following table, with their precedence relations and the three time estimates.



Three Time Estimates (Weeks)
Activity Immediate Predecessor(s) Optimistic Most likely Pessimistic
A - 2 5 8
B A 1 2 3
C A 1 2 15
D B 1 4 13
E B 1 5 9
F C 2 5 8
G E, F 1 2 3
H D 1 2 9
I G, H 1 5 9

a. Find the expected time for activity F.

b. What is the variance for activity C?

c. What is the variance in completion time for the project? (Hint: find critical path).

4. A bank is considering opening a drive-through window for customer service.

Customers are estimated to arrive at the average rate of 15 per hour. The teller who works at the window can service customers at the average rate of one every three minutes. Assume Poisson arrivals and exponential service times.

a. Find the average number of customers in the waiting line (waiting but not being serviced).

b. Find the average waiting time in the system (including waiting in line and in service).

c. Suppose that now the service times are deterministic at the same rate; that is, the teller can service exactly one customer every three minutes. Do you think your answer in (b) will become larger, or smaller, or remain the same? No calculation needed.

5. A bank is considering opening two drive-through windows for customer service.

Customers are estimated to arrive at the average rate of 15 per hour. The tellers who work at the windows are assumed to be identical, and can service customers at the average rate of one every six minutes. Assume Poisson arrivals and exponential service times.

a. Find the average number of customers in the waiting line (waiting but not being serviced).

b. Find the average waiting time in the system (including waiting in line and in service).

c. Suppose that now the inter-arrival times are deterministic at the same rate; that is, every hour exactly 15 customers arrive at the bank. Do you think your answer in (b) will become larger, or smaller, or remain the same, and why? No calculation needed.

Reference no: EM131258864

Questions Cloud

Develop a new diversity policy and training series : BANKS Industries continues to work on bridging cultural gaps as it embraces the diversity that resulted from its merger. You have been asked to develop a new diversity policy and training series for your team to help employees recognize the impact..
Calculate and display the rankine : Create a Matlab program that will calculate and display the Rankine, Celsius, and Kelvin equivalent temperature for a user entered Fahrenheit temperature.
Compare two certifications in the same industry : Research several certifications for an industry you are familiar with. Compare two certifications in the same industry. Which do you think is the stronger, or more effective, and why? Write a short analysis of your findings.
What is an augmenting walk : Now consider the network shown in Figure 6.26(b). Show that this network contains an infinite sequence of augmenting walks whose residual capacities sum to a value different than the maximum flow value.
What is the variance in completion time for the project : Suppose that now the inter-arrival times are deterministic at the same rate; that is, every hour exactly 15 customers arrive at the bank. Do you think your answer in (b) will become larger, or smaller, or remain the same, and why? No calculation n..
Book on grantham library page : how do i find a book on grantham library page with the isbn number my teacher gives me?
Return on investment-profit margin and investment turnover : Return on Investment, Profit Margin, and Investment Turnover Consider the following information for HandyCraft Stores for 2014 and 2015. 2014 Total Assets 42,000,000 Noninterest-bearing current liabilities 3,600,000 Net income 3,000,000 Interest expe..
Does anyone have any insights into globalization premium : Does anyone fear that U.S. equity markets may take a huge hit because globalization premium is slowing? Does anyone have any insights into globalization premium?
Compare two string classes using the equal sign : How do you compare two String classes using the equal sign to one another?

Reviews

Write a Review

Operation Management Questions & Answers

  Physician orders full treatment-including resuscitation

You work in a hospital where there is a patient that is 85 years old on a ventilator. A nurse sees from the patient's old records that the patient is a do not resuscitate (DNR), but the physician orders full treatment, including resuscitation. The nu..

  Discuss five trends in external environment scanning process

Complete a Porter’s Analysis to Industry Analysis on the Airline Industry using the six forces. Indicate each force’s competitiveness intensity by signifying Low-Medium-High, or combination of two grades. Support your evaluation on each force’s compe..

  Equipment effectiveness

Every successful Manager must evaluate the operating efficiencies of the enterprise. A mathematical measuring system known as Equipment Effectiveness (EE) was developed to meet this need. EE can be used to measure the effectiveness of an individual p..

  How does one avoid infringing those rights in the future

What rights, if any, are infringed by not referencing Internet sources, and how does one avoid infringing those rights in the future?

  What are the major types of knowledge work systems

What are the major types of knowledge work systems and how do they provide value for firms?

  The value of the optimal integer solution

Which of the following is true of the relationship between the value of the optimal integer solution and the value of the optimal solution to the LP Relaxation? For any linear program involving either minimization or maximization, the value of the op..

  Explain the interlinking model of quality and profitability

Explain the interlinking model of quality and profitability. How does it connect to business and operations strategy? Can you provide any examples of goods and services that support and add credibility to this model?

  Distribution center to serve the southhouteast region

Based on the available information is Atlanta the best location for a distribution center to serve the southhouteast region? If not, what would you recommend? show grid calculations

  Concerned with capital rationing

Project A has an NPV of $20,000 and a PI of 1.2. Project B has an NPV of $10,000 and a PI of 1.3. Both projects have equal lives. Which project should be preferred if we are NOT concerned with capital rationing (that is, we are NOT concerned with bei..

  Cost associated with patenting a product

There is a cost associated with patenting a product, and some companies produce more than one new product in a month. The products might have a short life (6 months to two years). Products with short life cycles normally are simple and easy to copy.

  Describe ways to identify and manage uncertainties

Describe ways to identify and manage uncertainties in a complex corporate environment (utilize contemporary and classical leadership theories to support your argument).

  What was the final outcome

What was the final outcome? If you did not intervene, what prevented you from doing so and if you encounter a similar situation in the future, what would you do differently?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd