What is the upper control limit for the r chart

Assignment Help Operation Management
Reference no: EM13228734

Q1: In a single sampling plan the sample size n =5. The submitted lot has on an average 25% defective items. Three acceptance numbers ( c = 0, c =1, and c=2) are being negotiated between the manufacturer and the buyer. Which acceptance number is most desirable from the manufacturer's viewpoint. You may use the following OC curve to find the answer.

a)  c = 0

b)  c = 1

c)   c = 2

926_Find the project duration.png

Q 2: In a double sampling plan the two acceptance numbers are: c1 = 8 and c2 = 12. The number of defectives found in the first sample is 9. Therefore, a second sample is taken. What is the maximum number of defectives allowed in the second sample for the lot to be accepted?

a) 0

b) 1

c) 2

d) 3

e) 4

Twenty samples of n = 200 were taken by an operator at a workstation in a production process. The number of defective items in each sample was recorded as follows. Answer

Q 3.

  Number                    Number

Sample  of Defectives      Sample    of Defectives

  1       12               11         16

  2       18               12         15

  3       10               13         13

  4       15               14         16

  5       16               15         18

  6       19               16         17

  7       17               17         18

  8       12               18         20

  9       11               19         21

  10      14               20         22

Management wants to develop a p-chart. The desired confidence level is 80.0 percent.

Q 3: What is the upper control limit?

Cans of soup are supposed to weigh exactly 16 oz. Inspectors want to develop process control charts. They take eight samples of five boxes and weigh them. They obtain the following data. Answer Q 4, and Q 5.

Sample      Mean       Range

1       15.2         1.8

2       14.6         0.7

3       16.5         0.5

4       18.1         0.4

5       13.2         0.2

6       16.0         0.4

7       15.9         0.5

8       14.8         0.9

 

Q 4: What is the upper control limit for the x-bar chart?

Q 5: What is the upper control limit for the R chart?

Cholesterol Palace is a fast-food restaurant. Management was concerned with errors in filling orders at its drive-up window. It hired several undercover quality inspectors to randomly place 100 orders while the process seemed to be in control. The completed orders were then checked for accuracy. The following table shows the results of the survey. Answer Q 6, Q 7, and Q 8.

Defect                                                Frequency

Incomplete, shorted order                              12

Unordered items dispensed                             2

Wrong product dispensed                               14

Wrong toppings                                            14

Wrong size drink                                            2

Drink lid not sealed                                        17

No drinking straw with soft drink order              0

No napkins                                                  18

Far too many condiment packets                     65

No salt with sandwich or fries order                  10

Wrong change                                               3

Other                                                          12

QC 6: Use these data to estimate the average number of defects per order.

QC 7: What is the lower control limit for a c-chart. Use z =3.

QC 8: A quality inspector just used the drive-up window and now checks her order. Her cheeseburger has mustard on it although she ordered it without ketchup or mustard. Three handfuls of ketchup and mustard packets are in the sack, but no napkins. And hot coffee has spilled because the lid wasn't properly sealed. Is the drive-up process in control?

 PROBLEMS ON PROJECT MANAGEMENT

Q 9: Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. Find the project duration (earliest completion time of the project).

 

1670_Find the project duration1.png

Activity

A

B

C

D

E

F

G

Time (days)

5

6

9

4

9

3

4

a)  21

b)  22

c)   25

d)  28

e)  31

Q 10: Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. What is the latest start time of activity C if the project completion time (due date) is set at 33 day?

58_Find the project duration2.png

Activity

A

B

C

D

E

F

G

Time (days)

5

6

9

4

9

3

4

a)  5

b)  7

c)   33

d)  Zero (0)

You may use the following table.

Activity

Immediate Predecessor

Time

Late Start

Late Finish

A

 

 

 

 

B

 

 

 

 

C

 

 

 

 

D

 

 

 

 

E

 

 

 

 

F

 

 

 

 

G

 

 

 

33

Q 11: The data for a Time-Cost CPM Scheduling model analysis are given below. The times are in days. What is the minimum cost to complete this project in 14 days?

Activity

Immediate Predecessor

Normal Time

Crash Time

Normal Cost ($)

Crash Cost ($)

A

None

4

2

2000

4000

B

A

4

3

3000

6000

C

A

2

1

2000

2500

D

B and C

4

2

5000

5600

E

D

3

1

6000

9000

a)  18,000

b)  27,100

c)   18,300

d)  300

Q 12: You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below.

Activity

Immediate Predecessor

Normal Time (days)

Crash Time (days)

Normal Cost (Direct) $

Crash Cost (Direct) $

A

None

3

2

300

400

B

A

3

3

100

100

C

A

1

1

200

200

D

B and C

3

2

400

550

E

D

2

1

500

900

F

E

3

3

200

200

G

F

2

2

100

100

The network for this project is given below.

641_Find the project duration3.png

The indirect costs for the project are determined on a daily duration basis and are given below:

Total indirect costs for 16 days of project duration: $ 600

Total indirect costs for 15 days of project duration: $ 400

Total indirect costs for 14 days of project duration: $ 200

Total indirect costs for 13 days of project duration: $ 100

At what project duration do we achieve the lowest total project cost (i.e., direct plus indirect costs)?

(a) 16 days

(b) 15 days

(c) 14 days

(d) 13 days

Consider a project having the following ten activities. Answer Q13 and Q14.

Activity

A

B

C

D

E

F

G

H

I

J

Immediate Predecessors

None

None

A

A,B

C,D

D

C

E,G

E,F

H,I

Time (weeks)

 

7

3

5

6

4

4

9

8

6

5













Q13: What is the critical path?

a) A-C-G-H-J

b) A-B-C-D-E-F-G-H-I-J

c) A-D-E-H-J

d) B-D-F-I-J

Q 14: What is the slack time of activity B?

a)  zero

b)  8

c)   11

d)  3

e)  19

You may use the following table.

Activity

Immediate Predecessor

Time

Early Start

Early Finish

Late Start

Late Finish

Slack Time

A

 

 

 

 

 

 

 

B

 

 

 

 

 

 

 

C

 

 

 

 

 

 

 

D

 

 

 

 

 

 

 

E

 

 

 

 

 

 

 

F

 

 

 

 

 

 

 

G

 

 

 

 

 

 

 

H

 

 

 

 

 

 

 

I

 

 

 

 

 

 

 

J

 

 

 

 

 

 

 

Problems on Scheduling

Q 15: A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the first-come-first-served priority rule, what is the number of late (tardy) jobs?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 16: A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest (earliest) due date rule, what is the average completion (flow) time of all jobs?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 17: A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest processing (operating)) time priority rule, what will be the average tardiness of these orders?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 18:   A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest processing (operating)) time priority rule, what will be the average number of jobs in the system?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 19: A machine shop has two machines, M1 and M2. Four jobs A, B, C, and D need to be processed through machines M1 first and M2 second. Job A will take one hour on machine M1 and three hours on machine M2. Job B will take three hours on M1 and two hours on M2. Job C, takes seven hours on M1and three hours on M2. Job D, requires five hours on M1 and one hour on M2. Using Johnson's rule, in what order should these jobs be done?

Q 20: Consider the following data for a five-job, 2-machine, flow-shop problem. Find the value of make-span (minimum time to complete all jobs) using the sequence ABCDE. 

 

Time

Job

M1

M2

A

1

2

B

4

2

C

1

3

D

5

4

E

3

5

You may use the following Gantt Chart template.

Reference no: EM13228734

Questions Cloud

Determine what is the average velocity of an electron : average velocity of v meters/second. If the concentration of free electrons is 10^{29} electrons per cubic meter and if they are uniformly dispersed throughout the wire, then what is the average velocity of an electron
Define how magnesium can exhibit metallic behavior : Using a band diagram, explain how magnesium can exhibit metallic behavior when its 3s band is completely full.
Find the frequency components at the output of the circuit : In a certain communications system a resonant-tuned circuit (tuned at 1200 kHz with Bandwidth = 15 kHz) is connected to the output of a non-linear amplifier (mixer). Find the frequency components at the output of the resonant-tuned circuit
Explain the collision cross-section for the reaction : Use the collision theory to calculate the theoretical value of the second-order rate constant (in m3 mol-1 s-1) for the gas-phase reaction D2 + Br2 = 2 DBr at 450 K assuming that it is elementary bimolecular. The collision cross-section for this r..
What is the upper control limit for the r chart : What is the upper control limit, what is the upper control limit for the x-bar chart and what is the upper control limit for the R chart?
Determine the induced emf if a short in the rheostate : The resistance of the shunt field winding and the resistance setting of the shunt field rheostat of a separately excited generator are 10.26 ohm and 14.23 ohm respectively. The field circuit is connected to a 120-V DC source.
Evaluate the electric field at each of the two points : The electric field in a certain region of space is given by the vector field E(r ) = E(x, y, z) = (x ? z)xˆ + (z ? y) yˆ V/m Find any two points P( x1 , y 1, z 1) and Q( x2 , y2 , z2 ) such that the electric field at P is perpendicular to the elec..
Explain the secondary structure of a polypeptide : Explain why rotation about N-Ca and Ca-C bonds is solely responsible for the secondary structure of a polypeptide
What are the risks associated with backdoor : What are the risks associated with backdoor (maverick) buying and selling? Why is purchasing interested in controlling this business practice?

Reviews

Write a Review

Operation Management Questions & Answers

  What do you think the important objectives are for a mne

What do you think the important objectives are for a MNE to have effective compensation policies and why? Also, why is it important for MNEs to understand the compensation practices of other countries?

  A recently negotiated union contract allows workers

A recently negotiated union contract allows workers in a shipping department 29 minutes for rest, 12 minutes for personal time, and 17 minutes for delays for each four hours worked

  Illustrate what ways would proposal by vice president

illustrate what ways would proposal by vice president of sales affect plant production capacity illustrate what o r remedies can be provided to case above.

  Based on what you discovered in the e-activity

Based on what you discovered in the e-Activity, develop a strategy that any manager could use to boost sales from customers using this Website.

  Promotional campaign for new running shoe

You are a member of an advertising team assembled to develop a promotional campaign for a new running shoe. Describe how you may apply the 5 levels of Maslow's needs hierarchy in developing your promotional strategy.

  Why it is important to gain employee cooperation

Explain why it is important to gain employee cooperation before beginning a job analysis program. Describe other issues and means that can aid in the job analysis process.

  Problem in the production line

Clarify whether the automated process is under control and explain what could be the reasons for possible under-weight or over-weight problems.

  Discuss the challenges faced by hr management

Discuss the challenges faced by HR management when significant staff cutbacks occur and how they should be addressed.

  Define corporate governance

What is corporate governance? What role does corporate governance play in strategic planning? Why is it important? Explain your answer and provide an example.

  Discuss the organizational design you would select

Discuss the organizational design you would select. Make sure you explain why you would select that organizational design.

  Determine the independent variable

Solve for x: log_10?x=3 5. You've earned your degree and have been hired by an established company. You were able to negotiate a beginning salary of $2500 per month with annual 6% raises each year.

  If joe and bud have an e-mail exchange that documents

If Joe and Bud have an e-mail exchange that documents their agreement, does this change your answer? Why or why not?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd