What is the total standard cost per unit

Assignment Help Managerial Accounting
Reference no: EM133440523

Question: Lindt company standard and actual costs per unit for the most recent period, during which 30,000 units were actually produced, are given below:

Raw Materials:

Standard usage and price - 2 feet per unit at $7.45 per foot

Actual usage - 32,000 feet

Purchased - 32,000 feet at $7.55 per foot

Direct Labor:

Standard hours and rate - 1.4 hours per unit at $12.00 per hour

Actual total direct labor - $687,300

Actual hours used - 43,500 hours

Variable overhead:

            Standard application rate - $2.25 per direct labor hour

            Actual variable overhead - $108,000

Fixed overhead:

            Budgeted - $210,000

            Actual - $211,800

            Standard application rate - $6.00 per direct labor hour
Favorable and Unfavorable for A-H

A. Material Price Variance

B. Material price quantity 

C.Direct labor rate variance.  

d. Direct labor efficiency variance

e. Variable overhead controllable (spending) variance
f. Variable overhead volume (efficiency) variance.  
g. Fixed overhead budget (controllable) variance

h. Fixed overhead volume (uncontrollable) variance. 

I. What is the total standard cost per unit?

j. What is the total actual cost per unit?

Reference no: EM133440523

Questions Cloud

Determine for papst company for the month of may : calculate requirements 1 and 2 under the assumption that estimated collections in the month of sale equal 60% and in the first month following the month of sale
What is the binary addition of 1101 and 0010 : What is the binary addition of 1101 and 0010? The result of adding 1+1 is 0. In binary, the result of 0*1 is _?
Address the regulatory and financial statement differences : create is one of the most important decisions an enterprise makes. The extent of liability and control the owner will have depends on the form of the business
Compare the two policies effects on the quantity of housing : Compare the two policies' effects on the quantity of housing consumed, consumer surplus, producer surplus, government expenditure, and deadweight loss.
What is the total standard cost per unit : Fixed overhead volume (uncontrollable) variance. What is the total standard cost per unit? j. What is the total actual cost per unit
Prepare the statement of owners equity : Prepare the Statement of owners equity and Prepare the Balance sheet - Consulting, an unincorporated consulting firm. The following information is based
How far away are you from retiring : What resources do you want to have in place that can fund your retirement? What do you want to have in place from an Estate Planning Standpoint?
Explain the relationship between the cost management system : Explain the relationship between the Cost Management System and the Financial Accounting System. Be sure to include users from both systems.
Prepare a production budget by quarters : Management wants to have an ending finished goods inventory equal to 20% of the next quarter's expected unit sales. Prepare a production budget by quarters

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd