Cost Management Earned Value Exercise

Given the following information - Let us assume that the figures are a representation of your Capstone Project. Your project projections for One Year are included below. We will need you to answer the following questions. Please refer to Chapter 7 of your Course Book to Recall that:

PV is the planned value,
EV is the earned value,
AC is the actual cost, and
BAC is the budget at completion.
Given the Following Figures (from your Capstone Project) - Please Answer the proceeding Questions:

PV = $22,000

EV = $20,000

AC = $25,000

BAC = $120,000

A. What is the Cost Variance? (Please List the Question and then completee the Answer - Write the Actual Calculations and the Answer!)

B. What is the Schedule Variance? (Please list the Question and then complete the Answer - Write the Actual Calculations and the Answer!))

C. What is the Cost Performance Index (CPI)? (Please list the Question and then complete the Answer - Write the Actual Calculations and the Answer!))

D. What is the Schedule Performance Index (SPI) for the Project? (Please list the Question and then complete the Anwer - Write the Actual Calculations and the Answer!))

E. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

(All Answers must be in completee Sentences and Paragraph form. No one-liners and No one-word answers.- Justify your Answer!)

F. Use the CPI to Calculate the estimate at completion (EAC) for this Project. Is the Project performing better or worse than Planned?

(All Answers must be in complete Sentence and Paragraph form. No one-liners and No one-word answers. - Justify your Answer!)

G. Use the SPI to estimate how long it will take to finish the project?

(All Answers must be in completee Sentence and Paragraph form. No one-liners and No one-word answers. - Justify your Answer!)

H. Now, with the Figures and numbers you calculated previously, Sketch the Earned Value Chart for this Project. You can Glean (use) Figure 7-6, which is found in the Coursebook and the PowerPoint as a guide in completing this last portion.

Reference no: EM133550479

Questions Cloud

Explain your plans for registering, studying : There are 9 Major Assessments needed for program completion. Identify each major assessment. Then explain your plans for registering, studying, and completing
What is provided even if it may not be what you expect : Implementing the code, or worried about any language at this point. This is a very simplistic model of an ATM, refrain from trying to mimic a real life ATM
Write a pseudo-code of your improved query algorithm : Show that without changing the data structure, we can improve the query time to O(log n) time. Write a pseudo-code of your improved query algorithm and prove
Briefly describe three tools and three types of software : Briefly describe three tools and three types of software used to collect data in an organisation.
What is the schedule variance : What is the Schedule Variance? (Please list the Question and then complete the Answer - Write the Actual Calculations and the Answer!))
Identify which of the six cs of communication, clear : Identify which of the six Cs of communication, clear, complete, concise, consistent, correct, and courteous, is missing from the sentence below, and describe
How do you typically respond to change : How do you typically respond to change? Do you embrace it? Seek it out? Accept it reluctantly? Avoid it at all cost? Is this behavior like that of your friends?
Find an example in popular culture of communication about : Find an example in popular culture of communication about gender identity/expression. Analyze the example and identify its theoretical assumptions about
What is the maximal miss rate of this l2 cache : What is the maximal miss rate of this L2 cache so that this multi-level cache has a smaller AMAT than the above cache without L2

Reviews

Write a Review

Applied Statistics Questions & Answers

  Hypothesis testing

What assumptions about the number of pedestrians passing the location in an hour are necessary for your hypothesis test to be valid?

  Calculate the maximum reduction in the standard deviation

Calculate the maximum reduction in the standard deviation

  Calculate the expected value, variance, and standard deviati

Calculate the expected value, variance, and standard deviation of the total income

  Determine the impact of social media use on student learning

Research paper examines determine the impact of social media use on student learning.

  Unemployment survey

Find a statistics study on Unemployment and explain the five-step process of the study.

  Statistical studies

Locate the original poll, summarize the poling procedure (background on how information was gathered), the sample surveyed.

  Evaluate the expected value of the total number of sales

Evaluate the expected value of the total number of sales

  Statistic project

Identify sample, population, sampling frame (if applicable), and response rate (if applicable). Describe sampling technique (if applicable) or experimental design

  Simple data analysis and comparison

Write a report on simple data analysis and comparison.

  Analyze the processed data in statistical survey

Analyze the processed data in Statistical survey.

  What is the probability

Find the probability of given case.

  Frequency distribution

Accepting Manipulation or Manipulating

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd