What is the remaining duration for the project overall

Assignment Help Operation Management
Reference no: EM131036950

1. Determining Critical Path and Activity Slack

Assume we have a set of activities, their expected durations, and immediate predecessors. Enter this information using MS Project to produce a Gantt chart - enable project summary.

(a) Identify the critical path.

(b) Identify activity slack times that are non-zero and record in the table below.

Activity

Duration
(days)

Predecessors

Free Slack

Total Slack

A

6

....

 

 

B

7

 

 

 

C

5

A

 

 

D

3

A, B

 

 

E

4

C

 

 

F

5

D

 

 

G

8

E, F

 

 

H

3

F, G

 

 

Now, now assume that activity C has taken 8 days past its anticipated duration to complete.

(c) How does the project's schedule duration change?

(d) Why does the duration change?

(e) Is there a new critical path? If so, what is it?

2. Refer to the task/activity table shown here.Enter this information using MS Project to produce a Gantt chart - enable project summary. Assume that each resource has been assigned to the project activity on a full-time basis.

Construct System 20 days Design System Harry Smith, Biil Plant
Test System 10dyas Gather Requirements, Construct System (FS with minus 10 day lag/lead) Kate Stone, Bill Plant
Revise System from Test 5days Test system Harry Smith, Biil Plant
Deploy System s days Revise system from test Ryan Burns

(a) Using the above information, produce a resource usage sheet identifying the total number of hours and daily commitments of each project team member. Record the total hours for each resource.

Resource

Hours

Bill Plant

 

Harry Smith

 

Kate Stone

 

Ryan Burns

 

Sue Peterson

 

(b) Identify any members of the project team who have been overassigned.

(c) Determine and record the specific dates when there is a conflict in the resource assignment schedule.

(d) Using the information above, describe how you could level the resource load to remove conflicts? What is affected by the change? What assumptions are made?

3. Use the following information to construct a tracking Gantt chart using MS Project - enable project summary.

Activities Duration Preceding Activites  Percent Complete
A 2 days None 100%
B 4 days A 100%
C 6days B 35%
D 3days B,C 0%
E 4 days B 0%
F 5 days C,E 0%

(a) What is the total % complete for the project overall?

(b) What is the Actual Duration for the project overall?

(c) What is the Remaining Duration for the project overall?

4. Assume you have collected the following data for your project. The roject budget is $90,000 and it is planned to last a total of 120 workdays. After collecting status partway through the project., you have collected the following status information,

PV = $100,000

EV = $80,000

AC = $65,500

Schedule Performance Index(SPI)
Estimated Time to Completion

Cost Performance Index(CPI)
Estimated Cost to Completion

Based on these values, estimate the time and budget necessary to complete the project.

(a) Describe how would you evaluate these findings? Are they good news or bad news?

(b) What could possibly cause this situation to occur? Be specific with examples.

Reference no: EM131036950

Questions Cloud

Discuss whether assets should be measured at historical cost : In answering the following questions, choose either property, plant and equipment or financial assets- With reference to the article discuss whether assets should be measured at historical cost or fair value
Determine the magnitude of the total velocity of b : Assume that the cable between B and the pulley remains vertical and solve for a given value of x.
Analyze local impact of global public administration policy : Analyze the local impact of global public administration policies and relationships. Analyze the core controversies, theories and rationale surrounding global public administration.
Determine the velocity v when the acceleration is 3 m/s2 : The position s of a particle along a straight line is given by where s is in meters and t is the time in seconds. Determine the velocity v when the acceleration is 3 m/s2
What is the remaining duration for the project overall : Based on these values, estimate the time and budget necessary to complete the project. Describe how would you evaluate these findings? Are they good news or bad news? What could possibly cause this situation to occur? Be specific with examples.
What is the absolute speed of the ball : The speed of the ball relative to the quarterback is 60 ft/sec. What is the absolute speed of the ball? Treat the problem as two-dimensional.
Creative thinking skills and achievement in e-learning : My Research topic is: The Impact of Flipped Classroom via Edmodo Platforms on Increasing Student's Creative Thinking Skills and Achievement in E-Learning Course at Jeddah University.
Determine the coordinates of the point : A golfer is out of bounds and in a gulley. For the initial conditions shown, determine the coordinates of the point of first impact of the golf ball. The camera platform B is in the plane of the trajectory.
What is the legal affect of stamping the specifications : CSM8003 & CMS800003 - CONSTRUCTION LAW. In the case can the specifications in the contract vary the written terms of the contract Describe the Legal Principles applicable and the hierarchy of contract documentation. What is the legal affect of st..

Reviews

Write a Review

Operation Management Questions & Answers

  Complaint instead of a federally protected class

Company fails fair -employment test: Why do you think "parental discrimination was the grounds for this complaint instead of a federally protected class? could you make a case on the bases of sex? why? or why not?

  Ethics-international factors-cross-cultural considerations

You have been asked by your supervisor to develop a PowerPoint presentation for an upcoming training on the following topics: ethics, international factors, and cross-cultural considerations in project management. Include one scenario applicable to e..

  What are the dangers slowing down economic growth

There are many factors that help the growth of the economy, but two of these factors are more important for economic global growth. What are the dangers slowing down economic growth?

  The project risks in the cost management plan

Assume that you are the project manager for the construction of 10 conference facilities in your organization’s building in Florida. A statement of work has been given to you, and contracts have already been awarded. How did you account for the proje..

  What is the reorder point if the firm is willing to tolerate

Lead time is one week and the lead-time demand is normally distributed with a mean of 150 units and a standard deviation of 40 units. What is the reorder point if the firm is willing to tolerate a 1% chance of stockout on any one cycle?

  What is your overall interpretation of this result

A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances, the CPI, and the SPI. What is your overall interpretation of this result?

  Finding any healthcare organization

finding any healthcare organization, select a process management such as hospital admissions process, order fulfillment process, claims process, school admissions process, hiring process, capital procurement process or any work process in an existing..

  What would operational advantage limited or focused strategy

Why do companies (retailers) expand their product like food or drugs? Think about which companies have done so, what have they had to do to accommodate the product lines. List all the things the company had to do. How does the strategy of expansion c..

  Insight communications promotes employees with good

Insight Communications Promotes employees with good technical skills into supervisory positions and then teaches them leadership skills.

  Communication means the process of becoming like one

Write an essay on the principle that "Communication means the process of becoming like one or as one." Tell what this principle means to you; tell how important is this principle from your experience; and, most important, tell very specifically how..

  Analyze the steps involved in the night audit

Analyze the steps involved in the night audit and make at least one recommendation for improving the process.

  Determine optimal order size also minimum annual total cost

Annual cost of carrying a pound of cheese in a refrigerated storage area is $12. Determine optimal order size also minimum annual total inventory cost.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd