What is the project duration and critical path

Assignment Help Operation Management
Reference no: EM131664791

A project consists of four activities: A, B, C, and D. 1.C follows A. 2.D follows B and C. The durations of each are A=4, B=6, C=3, D= 3 days. Answer the following questions.a) What is the project duration? b) What is the critical path? c) Which activities can be delayed, and for how many days?

Reference no: EM131664791

Questions Cloud

Fire detection system by security safety : Kuznicki made a contract for the installation of a fire detection system by Security Safety Corp. ("Security") for $498.
What sort of changes in the business system : What sort of changes in the business system would Kantian ethics require? Does Utilitarianism prioritize the quality of life? What would you choose as your ethi
Discusses many variations of teaching : Your required reading discusses many variations of teaching and what classrooms can look like.
Describe how these forces can impact a technology firm : What are the five forces in Porter's model? Describe how these forces can impact a technology firm.
What is the project duration and critical path : What is the project duration? What is the critical path? Which activities can be delayed, and for how many days?
Describe the real-life crisis : Describe the real-life crisis that you will use throughout this class and explain the perspective of your role as the key spokesperson.
Each hidden layer when creating neural network : Determine the number of hidden layers and the number of node in each hidden layer when creating a neural network?
Why bench marking is so important to practice management : Explain why bench marking is so important to practice management. Give at least two specific examples.
Explain how gerber benefit from using the decision analysis : Explain how Gerber benefit from using the decision analysis / theory.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd