What is the lump-sum equivalent cost of this project at the

Assignment Help Civil Engineering
Reference no: EM13562690

A certain fluidized-bed combustion vessel has an investigation cost of $ 100,000, a life of 10 years, and negligible market (resale) value. Annual costs of materials, maintenance, and electric power for the vessel are expected to total $10,000. A major relining of the combustion vessel will occur during the fifth year at a cost of  $30,000. If the interest rate is 15% per year, what is the lump-sum equivalent cost of this project at the present time?

Reference no: EM13562690

Questions Cloud

Solubility of a substance which dissolves with an increase : Solubility of a substance which dissolves with an increase in volume and liberation of heat will be favoured by the A. low pressure and high temperature. B. low pressure and low temperature. C. high pressure and low temperature. D. high pressure and ..
Find the final temperature using the three methods : It is desired to compare the results of property predictions for water near or in the saturation region using (a) the ideal gas equation, (b) the compressibility chart and
Find the temperature of the contents in the cylinder : Consider a piston/cylinder arrangement that has a linear spring mounted such that as the piston rises to a certain point it will encounter the spring, which will offer a downward component of force as the piston rises further.  Initially the cylinder..
Determine dry unit weight of the fill : A 2 m high sandy fill material was placed loosely at a relative density of 47%. Laboratory studies indicated tht the maximum and minimum void ratios of the fill material are 0.92 and 0.53, respectively
What is the lump-sum equivalent cost of this project at the : A certain fluidized-bed combustion vessel has an investigation cost of $ 100,000, a life of 10 years, and negligible market (resale) value. Annual costs of materials, maintenance
Determine the true horizontal legth of the distance : A 100-ft steel tape was used in the field to measure a distance of 247.53 ft. the following data represents the conditions in the field at the time of measurement: tempreture = 41 F, tension = 30 ib
Determine whether a cmfr or a pfr is more efficient : Let a one-dimensional velocity field be u = u(x, t), with v = 0 and w = 0. The density varies a ?-?0(2-cos(wt)) Find an expression for u(x, t) if u(0, t) = U.
What is the head that must be added by the pump : The moist unit weight of a soil is 19.kN/m^3. Given that specific gravity is 2.72 and water content is 10.6%, calculate dry unit weight, void ratio, porosity, and degree of saturation.
Determine the value of k : A well pump test was made in a surface layer of sand 10m thick overlying impervious clay. Before the test the water table was at 1.5m depth. After steady state had been reached in the tests

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate the magnitude of the force supported by bearing

The uniform 25 kg plate is welded to the vertical shaft, which is supported by bearings A and B. Calculate the magnitude of the force supported by bearing B during application of the (M =) 140 N·m couple to the shaft.

  Explain how to determine the particles velocity at s

acceleration of a particle traveling along straight line is a=(1/5)s^(1/2), s is in m, if v=0, s=3 when t=0 determine the particles velocity at s=6

  Derive the expression for the hydraulic radius rh of a pipe

A sprinkler system uses an outdoor reservoir at El 50. A fire pump moves Q = 3 ft^3/sec through a 1.0' dia pipe 300' long to an 8" dia main at El 200. To distribute water to sprinklers, a pressure head at the pipe junction hp =100' is required.

  Design riveted end plated connection between beam and flange

Design a riveted end plated Connection between a beam ISHB-300 and the flange of the Column ISHB-200 to transfer a vertical factored shear of 125 kN and a factored hogging bending moment of 125kNm.Use Shop rivets of 20mm dia.

  What diameter is required if the concrete is to carry 25 cfs

A circular sewer is laid on a slope of 0.5%. What diameter is required if the concrete is to carry 25 cfs. If the desired design mean section velocity is between 3 and 7 feet per second, is the design acceptable

  What is the bod5 of the river water

A 250 cubic meter reaction tank contains a waste water having an ultimate BOD concentration of 755 mg/L. If the BOD reaction rate constant is -0.352/day, how much BOD is remaining after 12.0 days?

  The velocity and the total distance traveled

The acceleration of a particle is defined by the relation a=-8m/s^2. Knowing that x=20m when t=4s and that x=4m when v=16m/s, determine (a) the time when the velocity is zero, (b) the velocity and the total distance traveled when t=11s.

  Bernoulli equation-measure the flow rate through the meter

The meter inlet and throat are connected by the two legs of a mercury manometer. Use the Bernoulli equation to describe how this manometer can be used to measure the flow rate through the meter.

  Concrete pier is loaded on top with a uniformly

Concrete pier is loaded on top with a uniformly distributed load of600 lbs per square foot.  Investigate the state of stressat a level of 4 ft. above the base.

  Determine the time required for the particle to come to rest

Given: acceration = -k*sqrt(v) and k is a cosntant when x=0, v=81 m/s, t=0 when x=18 m, v=436 m/s determine: a) velocity of particle when x=20 m b) the time required for the particle to come to rest

  Determine expected rate of return per quarter and per year

ASM International, an Australian steel company, claims that a savings of 40% of the cost of stainless steel threaded bar can be achieved by replacing machined threads with precision weld depositions

  Draw a cross-section of the specified pavement design

The roadway to be constructed is 3 miles long and 60 feet wide. • The following pavement design specifications have been issued: - Base coarse: 6" DGA - Stabilized base: 4" - Bottom coarse of asphalt: 3" - Top coarse of asphalt: 2"

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd