Phifer Landscaping Corp. capitalization of interest on construction of building

Phifer Landscaping Corp. purchased a parcel of land for $139,000. They also paid $2,000 for a survey and $4,000 in title insurance. An old dwelling on the land was demolished costing $3,000, with $1,000 being recovered from salvage materials on the demolished structure. $30,000 was paid for architect services and the building permit was $3,000. The following payments were made to the builder:

March 1, 2015 $240,000
May 1, 2015 $330,000
July 1, 2015 $60,000

The building was started on December 1, 2014 and completed on July 1, 2015.
Phifer borrowed $600,000 at 8% annual rate on December 1, 2014 specifically to fund this building project. The loan matures in 10 years.

1. What is the balance of land in 2014 and 2015?

2. What is the balance of building in 2014 and 2015?

3. What is the interest expense amount in 2014 and 2015?

4. Indicate the amount of interest Phifer should capitalize in 2014 and 2014 using the specific interest method.

Reference no: EM131015189

Questions Cloud

Confidence interval for the proportion of registered users : Find a 99% confidence interval for the proportion of registered users with false phone numbers and explain what it indicates. Use language that a manager could easily understand.
Find the volume of the solid whose base is the given region : Find the volume of the solid whose base is this region and whose cross-sections perpendicular to the x-axis are the following: squares. semi-circles
Estimate the proportion of defectives in the population : A production engineer monitoring a process that makes magic markers samples 500 markers at random and tests to see how many are defective. He finds 50 defective markers. (a) Estimate the proportion of defectives in the population. (b) Const..
Design and implement the netlogo mrs model : design and implement the NetLogo MRS model to satisfy the assignment objectives in any way subject to time and course constraints. In this and following sections a suggested approach is given for modelling MRS.
What is the interest expense amount : hat is the balance of land in 2014 and 2015? What is the balance of building in 2014 and 2015? What is the interest expense amount in 2014 and 2015?
What is volume of solid that is obtained by rotating region : Consider the shaded region bounded by y = f(x) and y = g(x) as shown. Set up the integral needed to find the volume of the solid obtained by rotating the region around the x-axis.
Hypothesis that the mean silica content : A toothpaste was formulated with a silica content of 3% by weight. The manufacturer randomly samples 33 tubes of toothpaste and finds their mean silica content is 3.4% and the standard deviation is 0.43%. Test the hypothesis that the mean silica c..
Expected impact of that approach on job performance : Explain how your recommended method of job evaluation aligns with MPBS's strategic focus.
List and explain three common types of spam : List and explain three common types of SPAM. Log onto your Email system (Ex: Gmail, Yahoo, etc.,) and locate SPAM filter functions. Configure SPAM filters to block known senders of SPAM

Reviews

Write a Review

Corporate Finance Questions & Answers

  Why is amazons cash cycle

Why is Amazons cash cycle so much shorter than that of competitor Barnes & Noble ? How does this comparison affect financial management decisions of other retailers ?

  What is the payback period for this project

The investment will result in additional cash flows of $525,000, $812,500, and $1,200,000 over the next three years. What is the payback period for this project?

  Calculate the dollar amount of acceptable accounts

Springer manufactures wants to borrow $80,000 from a local bank using accounts receivables to secure its loan. The banks procedure is to accept as collateral accounts that are normally paid within thirty days

  Breakeven number of units sold for each scale of operations

Complete the tables below for each scale of operations with the given levels of output and the relationships between quantity and fixed cost, quantity and variable costs, and quantity and total costs.

  Check whether a call option is priced correctly

Use the Black-Scholes option pricing formula to check whether a call option is priced correctly.

  What is the projects standard deviation of npv

What are the projects mostly likely worst and the best case NPV's, what is the projects expected NPV on the basis of the scenario analysis and what is the projects standard deviation of NPV?

  Breakeven analysis procrastinators anonymous pa is hosting

breakeven analysis procrastinators anonymous pa is hosting their annual convention this coming year in dallas tx.

  Assignments requirement1 support your assertions with at

assignments requirement1. support your assertions with at least two citations in apa format.2. acceptable sources

  Implied valuation of deal

Overview of deal -> implied valuation of deal, annual cash flows to and from each party

  Computation of sustainable growth rate

Computation of sustainable growth rate and Can Stieben's actual growth rate in sales be different from its sustainable growth rate? Why or why not? How can Stieben change its sustainable growth?

  What is the present value of the project

A project is forecast to produce a safe cash flow of $800,000 a year for 20 years. If the cost of capital is 4%, what is the present value of the project?

  What minimum rate of return

How could it have had a zero real rate of return and what minimum rate of return must the T-bill have earned to meet your requirement of a 2% real rate of return?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd