1) Classify the following list of items as A, B, or C item.

Item

Estimated Annual Demand

UnitPrice

H4-010

20,000

2.50

H5-201

60,200

4.00

P6-400

9,800

28.50

P6-401

14,500

12.00

P7-100

6,250

9.00

P9-103

7,500

22.00

TS-300

21,000

45.00

TS-400

45,000

40.00

TS-041

800

20.00

V1-001

33,100

4.00

2) A small grocery store sells fresh produce, which it obtains from a local farmer. During the strawberry season, demand for fresh strawberries can be reasonably approximated using normal distribution with a mean of 40 quarts per day and a standard deviation of 6 quarts per day. Excess costs run 35 cents per quart. The grocery orders 49 quarts per day.

a) What is the implied cost of shortage per quart?

Reference no: EM13230228

Questions Cloud

Design a 4 bit register with 4 different kinds of flip flops : design a 4 bit register with 4 different kinds of flip flops, that has at least 12 different functions. list clearly the functions. Do something creative, and say exactly your innovation. at least one flip flop should have some input besides a mul..
What are the three basic financial statements : What are the three basic financial statements, and what major information does each contain?
Who are learning software programming : Discuss when scripting should be taught to individuals
Calculate the normal force n exerted by the side of the slot : The flat circular disk rotates about a vertical axis through O with a slowly increasing angular velocity ?. Prior to rotation, each of the 0.44-kg sliding blocks has the position x = 22 mm with no force in its attached spring.
What is the implied cost of shortage per quart : demand for fresh strawberries can be reasonably approximated using normal distribution with a mean of 40 quarts per day and a standard deviation of 6 quarts per day.
Determine the efficiency of the transformer : A 23-kVA, 2300/230-V, 60-Hz, step-down transformer has the following resistance and leakage-reactance values: R1 = 4 ohm, R2 = 0.04 ohm, Xl = 12 ohm, and X2 = 0.12 ohm. The transformer is operating at 75% of its rated load.
What are the resultant values for the output period : A PWM unit is set-up with a pre-scale factor of 128. If the PWMPER register is loaded with 34 and the PWMDTY is loaded with 3, what are the resultant values for the output period and pulse width
Find the extension and retraction load-carrying capacities : An 8cm diameter hydraulic cylinder has a 4cm diameter rod. If the cylinder receives flow at 100Lpm and 12MPa, find the a) Extension and retraction speeds b) Extension and retraction load-carrying capacities
Explain the importance of unix : Explain the importance of UNIX® to the Internet. Support your position using examples.

Reviews

Write a Review

Operation Management Questions & Answers

  Company is considering the introduction of a new product

Your company is considering the introduction of a new product line. The initial investment required for this project is $500,000, and annual maintenance costs are anticipated to be $35,000

  Describe the difference in inputs and output between a pmo

Describe the difference in inputs and output between a PMO that is customer-focused vs. PMO that is oriented to enforcement of standards.

  What is productivity measure of units of output per dollar

What is the productivity measure of "units of output per dollar of input" averaged during the 3 year period? (Show calculations).

  Creating the monthly sales data on a sheet of graph paper

The monthly sales for Telco Batteries, Plot the monthly sales data on a sheet of graph paper and Forecast January sales for the new year.

  Would it be more valuable if it were updated daily

Many practitioners currently update MRP weekly or biweekly. Would it be more valuable if it were updated daily? Discuss.

  What is their productivity with the standard equipment

They utilized 10 gallons of solvent and 2 employees worked 20 days per month, 8 hours per day. Illustrate what is their productivity with the standard equipment.

  What is systems development

What is systems development? List the main activities in systems development.

  Direct versus indirect distribution

Once you have developed your product/service, you then need to determine how to make it available to the end user. Using your textbook and the articles from the Databases

  What are porters competitive forces in an organisation

What are Porter's competitive forces in an organisation's environment? Explain them and provide examples to illustrate your answer.

  How many doses in total are prepared for a single order

On average, the pharmacy prepares 500 CSP doses per day. Use Little's law to calculate how many doses in total are prepared for a single order on average.

  Illustrate some sources of risk in systems analysis

Illustrate what are some sources of risk in a systems analysis also design project, also elucidate how does a project manager cope with risk during stages of project management.

  Compare and contrast large-scale change techniques

Compare and contrast large-scale change techniques with the traditional guiding coalition approach. What are the strengths and weaknesses of each?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd