Reference no: EM131855113
A machining area produces part QR for use in an adjacent assembly area. Estimated annual demand for the part is 20,000 units. The value of the part is $50 per unit. The annual carrying and handling cost rate is estimated to be 16%.
The plant operates 250 days a year. The assembly area uses one part QR for each product, and it produces 100 products per day. When producing part QR, the machining area can produce 200 units per day. The cost of ordering and setup for part QR is $200.
1. What is the economic order quantity?
2. Suppose the assembly area places an order whenever the on-hand amount of part QR reaches a certain level, the reorder point. If it takes the machining area 2 weeks to begin filling an order, and if the assembly area wants to maintain a minimum, or safety stock of 200 units, at what on-hand quantity should an order be plated (i.e., what is the reorder point)?
3. If part QR were ordered from a supplier for the same costs, and the supplier delivered the entire order all at once, what would the order quantity be?
Give the heap that results when starting with an empty heap
: Give the heap that results when, starting with an empty heap, insert is called successively for the keys EASY QUESTION.
|
List differential diagnosis
: List your differential diagnosis. What assessments would you perform?
|
What type of input file will make radix-exchange sort run
: How much memory is required to do a four-pass straight radix sort of N b-bit keys? What type of input file will make radix-exchange sort run the most slowly?
|
What or who influenced her to become a nurse
: Question #1: Where was influential nurse Margaret Sanger born, history of family.
|
What is the economic order quantity
: If part QR were ordered from a supplier for the same costs, and the supplier delivered the entire order all at once, what would the order quantity be?
|
What could be the possible passes in the project timeline
: A Project Manager is in charge to implement the supply chain integration, what could be the possible passes in the project timeline.
|
Occupational safety and health administration
: The Occupational Safety and Health Administration (OSHA), the Centers for Medicaid and Medicare Services (CMS), and The Joint Commission
|
Discuss the number of exchanges used by radix-exchange sort
: Compare the number of exchanges used by radix-exchange sort with the number used by Quicksort for the file 001, 011, 101, 110, 000, 001, 010, 111, 110, 010.
|
Explain the project management and operational management
: What is the main difference between a project management and operational management?
|