What is the earned value for project

Assignment Help Microeconomics
Reference no: EM133219548

As a PMO officer, you are asked to do an evaluation for a natural gas pipeline right in the middle of the project's planned schedule. There are concerns that it will go over budget and schedule because 40 million dollars has been spent in the project so far. According to the project charter, the pipeline length is 72 km and must be completed in 6 months, with a budget of 57.6 million AUD. You performed an inspection and find out that installation of 30 km of pipeline has been completed.

Using earned value analysis, answer the following questions:

A) What is the earned value (EV) for this project at the time of inspection (month 3)? [

B) What is the planned value (PV) for this project at the time of inspection? [

C) Calculate the Schedule variance (SV) and the cost variance (CV) at month 4. What do they mean?

D) Calculate the Schedule performance index (SPI) and the cost performance index (CPI) at the time of inspection. What do they mean? [

E) According to your analysis, how much is the project going to be over budget? (Calculate the estimate to completion (ETC).) [

F) As a key part in your report to the management, what is your advice for cutting the expenditure in the rest of the project, in order to finish the project "on-budget"? Determine the "to complete performance index (TCPI)" for this project. What does it mean?

Reference no: EM133219548

Questions Cloud

What is socially responsibly management : In an Essay form explain What is Socially Responsibly Management and Why should Corporate Social Responsibly be a priority for organization?
Why is research important : Why is research important? Why is an introduction important in a research proposal? What information should the author communicate to the audience
How important are social media channels-networks : How important are social media channels/networks such as Facebook, Twitter, LinkedIn, and YouTube in attracting qualified candidates for jobs?
Find the most recent version of victorian acts : Explain the ethical standards associated with making price guide recommendations and find the most recent version of Victorian Acts and Regulations
What is the earned value for project : What is the earned value (EV) for project at the time of inspection (month 3) and What is the planned value (PV) for this project at the time of inspection
How could a team of talented individuals : How could a team of talented individuals, after an eight-month investigation and in the face of cautionary criticism, produce a report that ended in people
What are the characteristics of a strategic leader : What are the characteristics of a strategic leader? What are the behaviors of a strategic leader?
How could companies utilize technology : Technology is changing how we work - from customer engagement to supply chain management to basic job functions. How could companies utilize technology
Who were your favorite explorers and why : An Interpretive History 9th edition by James J. Rawls and Walton Bean with particular attention to the European explorers.

Reviews

Write a Review

Microeconomics Questions & Answers

  The free rider problem

Question: Explain why the free rider problem makes it difficult for perfectly competitive markets to provide the Pareto efficient level of a public good.

  Failure of the super committee is good thing for economy

Some commentators have argued that the failure of the “Super committee” is good thing for the economy?  Do you agree?

  Case study analysis about optimum resource allocation

Case study analysis about optimum resource allocation: -  Why might you suspect (even without evidence) that the economy might not be able to produce all the schools and clinics the Ministers want? What constraints are there on an economy's productio..

  Fixed cost and vairiable cost

Questions:  :   Which of the following are likely to be fixed costs and which variable costs for a chocolate factory over the course of a month?  Explain your choice.

  Problem - total cost, average cost, marginal cost

Problem - Total Cost, Average Cost, Marginal Cost: -  Complete the following table of costs for a firm.  (Note: enter the figures in the  MC   column  between  outputs of  0 and 1, 1 and 2, 2 and 3, etc.)

  Oligopoly and demand curve problem

Problem based on Oligopoly and demand curve,  Draw and explain the demand curve facing each firm, and given this demand curve, does this mean that firms in the jeans industry do or do not compete against one another?

  Impact of external costs on resource allocation

Explain the impact of external costs and external benefits on resource allocation;  Why are public goods not produced in sufficient quantities by private markets?  Which of the following are examples of public goods (or services)? Delete the incorrec..

  Shifts in demand and movements along the demand curve

Describe the differences between shifts in demand and movements along the demand curve. What are the main factors which can shift the demand curve? Explain why they cause the demand curve to shift. Use examples and draw graphs to support your discuss..

  Article review question

Article Review Question: Read the following excerpts from the article "Fruit, veg costs surge' by Todd, Dagwell, published in the Herald on January 25th 2011 and answer questions below:

  Long-term growth, international trade & globalization

Long-term Growth, International Trade & Globalization:- This question deals with concepts such as long-term growth, international trade and globalization. Questions related to trade deficit, trade surplus, gains from trade, an international trade sce..

  European monetary union (emu) in crisis

"Does the economic bailout of Spain and Greece spell the beginning of the end for the European Monetary Union (EMU)?"

  Development game “settlers of catan”

Read the rules of the game, the overview and the almanac for the Development Game "Settlers of Catan"

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd