What is the critical path and expected completion time

Assignment Help Operation Management
Reference no: EM13225773

Question 1

A member of a project team that is implementing a new credit card payment process at a bank has direct responsibility to do all of the following EXCEPT:

be sensitive to conflicts between other team members and help resolve them.

ensure that the project has appropriate resources for the job to be completed.

help solve project problems that spill over into areas outside their expertise.

be called upon to share their expertise in credit card payment processes.

Question 2

Mike Multitask has three projects (A, B, and C) that are each four days long. Mike's supervisor suggests that he work first on project A, finish it, then work on project B until it is finished, and then on project C. Mike boldly declares, "My name isn't Multitask for nothing," so he decides to spend one day working on project A, one on B, one on C, then back to project A, and so on. There is no additional start up or shut down time required by splitting the projects this way. What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion?

There is no difference.

Mike's way is 3 days shorter.

Mike's way is 3 days longer.

Mike's way is 9 days longer.

Question 3

Slack time is routinely lost in a network:

at the point where multiple paths exit a common node.

at the point where multiple paths enter a common node.

at the point where the longest activity begins.

at the point where the shortest activity begins.

Question 4

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?

1, 9, 9

1, 5, 9

1, 1, 9

1, 5, 5

Question 5

You are responsible for managing a project with the following activities (times are given in days).

Activity      Expected Time    Immediate Predecessor(s)

A                 3                            ---

B                 6                            ---

C                 2                            ---

D                 5                             A

E                  2                            C

F                   7                            A

G                   4                         B, D, E

what is the critical path and expected completion time for this project?

A - F ; 12 days

A-D-G; 12 Days

B-G; 10 days

C, E, G; 10 days

Question 6

Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six weeks, what will happen to the expected time for that activity?


It will increase by one week.

It will decrease by one week.

It will increase by six weeks.

It will remain the same.

Question 7

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

50 percent

95 percent

100 percent

It cannot be determined.

Question 8

A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?

Less than or equal to $5,000

Greater than $5000 but less than or equal to $10,000

Greater than $10,000 but less than or equal to $15,000

Greater than $15,000

Question 9

You are given the following information about activity B:
Normal time = 9 weeks
Crash time = 5 weeks
Cost to crash per week = $2000
Crash cost = $41,000

What will it cost to complete activity B in 6 weeks?

Less than or equal to $34,000

Greater than $34,000 but less than or equal to $36,000

Greater than $36,000 but less than or equal to $38,000

Greater than $38,000

Question 10

You are given the following information about activity F:
Normal time = 16 weeks
Crash time = 10 weeks
Crash cost = $45,000
Cost to crash per week = $2,000

What is the normal cost for activity F?

Greater than or equat to $55,000

Less than $55,000 but greater than or equal to $47,000

Less than $47,000 but greater than or equal to $40,000

Less than $40,000

Reference no: EM13225773

Questions Cloud

The firm instead rents saucepans every period : Consider the pricing problem of Alcoa's cookware division. Suppose that the world last for only two periods, period 1 and period 2. A saucepan last two periods, so that a saucepan that is bought in period 1 can also be used in period 2. Consumers val..
What might happen with business across state lines : Also consider what might happen if there were no UCC in the United States. What might happen with business across state lines?
How did multitechs organization work : How did Multitech's organization work? How does he keep control?
What winding ratio should the transformer have : A 12V-DC power supply that gets it's power from the 110V (RMS) wall outlet needs a transformer as a first step in generating its output. The rectification and regulation stage of the power supply needs an input voltage of 15V (peak)
What is the critical path and expected completion time : What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion and what is the critical path and expected completion time for this project?
Determine the concentration of donor impurity atoms : A silicon sample at T = 300 K contains an acceptor impurity concentration of \(N_{A}\) = 1016 cm-3. Determine the concentration of donor impurity atoms that must be added so that the silicon is n-type and the Fermi energy is 0.20 eV
Define electrons in the new molecular orbitals : The four molecular p orbitals of the four carbon atoms can be lined up parallel in order to create four new molecular orbitals. The electrons in the new molecular orbitals benefit because they are not confined to just one atom.
How would you try to get individual managers : Assume for a moment that you are the HR Manager for a medium size company. How would you try to get individual managers to be more aware of the legal requirements of staffing systems and to take steps to ensure that they themselves engage in legal..
Allied health professional working with an endocrinologist : You are an allied health professional working with an endocrinologist. You have been working with the patient and need to update the doctor on the reason for the patient's visit. Begin describing the patient's concerns.

Reviews

Write a Review

Operation Management Questions & Answers

  Which of subsequent strategies would be most likely course

Which of subsequent strategies would be most likely course to help to reduce TCO of merged firms' technology investments.

  Determine how ship need from every plant to distribution

The shipping costs per truckload between the plants also distribution centres are given in the table. The Corporation needs to determine how much to ship from every plant to every distribution center also would like to minimize total shipping costs..

  Obtain remainder from overtime

Which of subsequent production plans is better: Plan A-chase demand by hiring also firing; or Plan B-make at a constant rate of 1200 also obtain remainder from overtime.

  Explain why diversity and creativity are important

Explain why diversity and creativity are important to the effectiveness functioning of the Freiburg team.

  Given the option to work for a company

Given the option to work for a company in a particular market, would you choose to work for a Western MNE such as IBM, moving into a developing country

  Facility building is paramount after cities win a bid

Facility building is paramount after cities win a bid to host the Olympic Games. What is one of the biggest concerns, outside of construction costs

  Question based on decision modeling

A bank is retrofitting part of its value to hold safety deposit boxes. It plans to build safety deposit boxes approximately 6 feet high along the walls on both sides of a 20-foot corridor.

  What is the chocolate raw material safety stock

What is the chocolate raw material safety stock Christian needs to hold? What is the expected inventory level for the chocolate raw material?

  Are current state and federal laws on gambling optimal

Are current state and federal laws on gambling optimal? Should the nation move in the direction of stricter prohibition? Or should it move to more permissive laws, including those to legalize online gambling?

  Compile list of major system life cycle activities

Compile a list of major system life-cycle activities. For each activity on the list, try to find the related supply chain activities. Present your finding in a table with the system life-cycle stage in the first colum.

  Compare organizational structure and organizational process

What five methods have traditionally been used to departmentalize work and workers? Give one advantage and one disadvantage of each.

  Analyze the diversity practices of organization

Analyze the diversity practices of your organization to determine if it is engaged in surface-level or deep-level diversity. Provide specific examples to support your response

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd