What is the critical path

Assignment Help Operation Management
Reference no: EM1389666

Schedule the following activities using CPM:

Activity Immediate Predecessor Time (weeks)
A -- 5
B A 10
C A 8
D B 6
E C 7
F C 4
G D,E,F 4

a. Draw the network.

b. What is the critical path? Enumerate all the paths in the network.

c. For the cost data shown below, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule.

Activity Normal time Normal cost Crash time Crash cost
A 5 $7,000 3 $13,000
B 10 12,000 7 16,500
C 8 5,000 7 6,000
D 6 4,000 5 5,000
E 7 3,000 6 6,000
F 4 6,000 3 7,000
G 4 7,000 3 9,000

Reference no: EM1389666

Questions Cloud

Report of current outbreak : Determine a news report of a current outbreak or other health crisis (within a month) then search for a peer-reviewed scientific article on the same or closely related topic
Describe at least two actions a manager can take to protect : Describe at least two actions a manager can take to protect her- or himself and the organization she or he represents from a tort lawsuit.
Sufficient evidence to reject the manufacture claim : Do the sample data present sufficient evidence to reject the manufacture's claim? Test using a a=0.05. What is the p-value of the test.
Calculate the phenotypic variance : Assume you wish to increase fruit diameter in tomatoes, and you want to estimate heritability for this trait. You measured the diameter of tomatoes in two inbred lines.
What is the critical path : What is the critical path? Enumerate all the paths in the network. For the cost data shown below, reduce the project completion time by three weeks
Normal distributioin of university admissions test : Test scores on a university admissions test are normally distributed, with a mean of 500 and a standard deviation of 100. a) What is the probability that a randomly selected applicant scores between 425 and 575?
Writing a one page proposal consisting : Need help writing a one page proposal consisting of 300 words about informing people about the air pollution in china.
Has the new math program been effective : Construct a control chart for test errors and set the control limits to contain 99.73% of the random variations in test scores. What does the chart tell you? Has the new math program been effective?
Provide example of an animal species : Food resources are rarely shared uniformly in the environment. Most vary seasonally or have a patchy distribution and can become locally depleted.

Reviews

Write a Review

Operation Management Questions & Answers

  Explain why ethical and cultural factors

Explain why ethical and cultural factors should be an important consideration in analyzing and choosing among alternative strategies

  Illustrate what is the probability which the total weight

It is given which the total weight of 8 boxes chosen at random follows a normal distribution with a mean of 820 kg also a standard deviation of 140 kg. Illustrate what is the probability which the total weight of 8 boxes exceeds 880 kg.

  By explain how much would the accuracy rate improve

By explain how much would the accuracy rate improve if an additional (a second), equally accurate verifier were used.

  Elucidate how does henry larsen get away with such egregious

Elucidate how does Henry Larsen get away with such egregious behaviour in the Orion Shield case. Processes to consider may be related to policies also procedures, human resource management also customer service.

  What order size would you recommend

A manager just received a new price list from a supplier. It will now cost $1.00 a box for order quantities of 801 or more boxes, $1.10 a box for 200 to 800 boxes, What order size would you recommend

  Ow many dozen cookies should you make with each batch

The same bakery also makes gourmet chocolate-chip cookies by the dozen to sell to local grocers. The bakery is contracted to supply 30 dozen cookies a day to the grocers.

  Elucidate how is it to fine-tune your marketing plan

Elucidate how necessary is it to fine-tune your Marketing Plan so that your target market is clearly defined also measurable. Why is extensive research necessary for an accurate definition of a target market.

  Storage and distribution operation

storage and distribution operation

  Decide the number of units where either choice has same cost

Stan fawcetts company is considering producing a gear assembly that it now purchases from salt lake supply. Decide the number of units where either choice has same cost.

  Explain how would your remarks differ if the group

Explain how would your remarks differ if the group reservation had been made by the vice president of engineering, an incentive travel organization.

  Discuss the steps in the selection process for new employees

Discuss the steps in the selection process for new employees. Evaluate why some potential employees are likely to be put through all the steps

  Question on integer programming problem

Mention the advantages and disadvantages of solving integer programming problems by a) rounding off, b) enumeration, and c) the branch and bound method.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd