1. Schedule the following activities using CPM:
|
Activity
|
IMMEDIATE PREDECESSOR
|
TIME (WEEKS)
|
|
A
|
-
|
1
|
|
B
|
A
|
4
|
|
C
|
A
|
3
|
|
D
|
B
|
2
|
|
E
|
C, 0
|
5
|
|
F
|
D
|
2
|
|
G
|
F
|
2
|
|
H
|
E, G
|
3
|
a. Draw the network.
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
2. The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:
|
Activity
|
IMMEDIATE PREDECESSOR
|
TIME (WEEKS)
|
|
A
|
-
|
3
|
|
B
|
A
|
2
|
|
C
|
A
|
4
|
|
D
|
A
|
4
|
|
E
|
B
|
6
|
|
F
|
C. D
|
6
|
|
G
|
D. F
|
2
|
|
H
|
D
|
3
|
|
I
|
E. G. H
|
3
|
a. Draw the network diagram.
b. What is the critical path?
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?
d. What is the new critical path and earliest completion time?
3. The following represents a project that should be scheduled using CPM-
|
Activity
|
IMMEDIATE PREDECESSORS
|
TIMES (DAYS)
|
|
a
|
m
|
b
|
|
A
|
-
|
1
|
3
|
5
|
|
B
|
-
|
1
|
2
|
3
|
|
C
|
A
|
1
|
2
|
3
|
|
D
|
A
|
2
|
3
|
4
|
|
E
|
B
|
3
|
4
|
11
|
|
F
|
C. D
|
3
|
4
|
5
|
|
G
|
D. E
|
1
|
4
|
6
|
|
H
|
F,G
|
2
|
4
|
5
|
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?
|
Entry strategy-technology based-quality based or cost based
: Success of a company investing and operating in a foreign country depends on the competitive advantage of the company. The entry strategy could be technology based, quality based, or cost based. Explain and comment.
|
|
Compliance with regulatory agency guidelines
: As a CMAA in a clinic, you are responsible for ensuring that job performance is in compliance with regulatory agency guidelines. There are many areas of compliance that a CMAA must be familiar with: financial risk, local and state regulations, Occ..
|
|
Exit gas streams are at 8 bar and at the same temperature
: A gas stream is entering a separator at 1 mole/sec with mole fractions 15% A and 85% B. (Component 1 is A, component 2 is B.) At surface, the gas stream is 8 bar and 350K. Two streams exit the separator, one primarily of A (0.99 A1, 0.01 A2), and one..
|
|
Legal establishment of a nuclear family unit
: Today, people marry for a variety of reasons, including family obligations, arranged marriages, the legal establishment of a nuclear family unit, the legal protection of children, or the public declaration of commitment. Discuss the following:
|
|
What is the critical path
: What is the critical path. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten
|
|
What is significance of brown and board of education
: What was the relationship between consumer culture and the emphasis on family life in the postwar era? What is the significance of the Brown v. Board of Education of Topeka decision?
|
|
Construct a b+ tree
: Construct a B+ tree for the following set of key value (2,3,5,7,11,19,23,29,31) in ascending order where the pointers that will fit in one node is as follows:A. four B. six C. eight assuming the tree is initially empty and values are in ascending ..
|
|
Strategic leaders are concerned with vision and mission
: A management consultant said that strategic leaders are concerned with vision and mission, while strategic managers are concerned with strategy.
|
|
Prepare a sample portfolio with resume
: Each student is required to prepare a sample portfolio with (1) resume, (2) letter of interest, (3) sample thank you letter, (4) memo, and (5) sample interview questions and answers
|