What is the critical path

Assignment Help Operation Management
Reference no: EM132087016

Vernon, Andy, and Sean are getting ready for their last period in the exchange study in CBS.

Following the final exams, they intend to throw a big party with many of their friends from back home. Presently, they have identified the following set of activities that need to be completed. They decide to not spend any work on preparing the party until all final exams are over. Moreover, they aim to spend a 3-day beach vacation as early as possible, but not before all party planning activities are completed.

On June 10, they will enter the final exam week, which will take 5 days. They then want to arrange for live music (which will take 5 days), evaluate a number of potential party sites (6 days), and prepare a guest list, which includes inviting their friends and receiving the RSVPs (7 days). They want to visit their two most promising party sites, which they expect to take 4 days. However, this can only be done once they have completed the list of party sites. Once they have finished the guest list and received the RSVPs, they want to book hotel rooms for their friends and created a customized T-shirt with their names on it as well as the name of the guest. Hotel room reservation (3 days) and T-shirt creation (6 days) are independent from each other, but both of them require the guest list to be completed. Once they have picked the party site, they want to have a meeting on site with an event planner, which they expect to take 4 days. And then, once all work is completed, they plan to take off to the beach.

(a) Draw a table to list all the activities, their immediate predecessors, and their durations. Draw the network based on the table.

(b) What is the critical path?

(c) For each activity, compute the slack time.

Reference no: EM132087016

Questions Cloud

What risks most concern you in using this app : Customers use mobile devices for a wide range of shopping and commercial activities. What risks most concern you in using this app?
What is the total amount of dollars received : The exercise price is $0.50. If the option is exercised, what is the total amount of dollars received (after accounting for the premium paid)?
Wide range of shopping and commercial activities : Customers use mobile devices for a wide range of shopping and commercial activities.
How is analog data converted to digital : Analog transmission has been around for a long time, but digital transmissions are more recent. Explain the differences between the two types of transmissions.
What is the critical path : Following the final exams, they intend to throw a big party with many of their friends from back home. What is the critical path?
What is the value of the yen in fijian dollars : What is the value of the yen in Fijian dollars (i.e., how many Fijian dollars do you need to buy a yen)?
Describe one anti-AIDS treatment strategy : Find one anti-AIDS treatment strategy that is currently under development, and describe it here or describe one of newer strategies that wasn't mentioned here
Approximate 10-year forecast of the peso spot rate : What is the approximate 10-year forecast of the peso's spot rate if the 10-year forward rate is used as a forecast?
Organization currently develop leaders and plan : What issues is the organization currently experiencing that may be related to leadership problems? How does the organization currently develop leaders and plan

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd