What is the correct total time and what is critical path

Assignment Help Computer Engineering
Reference no: EM13705145

Question: Forest Point Construction At Forest Point Construction, your boss says that he can estimate the total project time based on his personal experience.

You are trying to convince him that he should use project management techniques to handle a complex project.

To prove your point, you decide to use a simple example of a commercial steel building construction project, with eight steps. You create a hypothetical work breakdown structure, as follows: • Prepare the site (3 days), and then set the building footers (3 days).

- Finish the foundation (5 days), and then assemble the building (3 days).

- When the building is assembled, start two tasks at once: finish the interior work (5 days) and set up an appointment for the final building inspection (15 days).

- When the interior work is done, start two more tasks at once: landscaping (7 days) and driveway paving (3 days). • When the landscaping and driveway are done, do the painting (2 days).

- Finally, when the painting is done and the final inspection has occurred, arrange the sale (2 days). Now you ask your boss to review the tasks, estimate the total time, and write the answer on a piece of paper. You look at the paper and see that his guess is wrong.

Task 1: What is the correct total time?

Task 2: What is the critical path?

Task 3: Create a Gantt chart that shows the WBS.

Task 4: Create a PERT/CPM chart. 2

Can you find critical path and correct total time?

Reference no: EM13705145

Questions Cloud

Create a void function that takes as parameters : Create a void function that takes as parameters two integers, adds them, and prints them out to the command line.
How much heat is released when 3g of hydrogen reacts : Problem- The enthalpy of formation of water is -241.8 kJ/mol. How much heat is released when 3g of hydrogen reacts with excess oxygen to form water
Print all lines where the birthdays are in november : Print all lines where the birthdays are in November or December - Append three asterisks to the end of lines starting with Fred
Calculate the change in energy of the balloon in j : Problem- A balloon is inflated to its full extent by heating the air inside of it. During this process, 1100 J of heat is added and the work done by the balloon is 121 cal. Calculate the change in energy of the balloon in J.
What is the correct total time and what is critical path : Forest Point Construction At Forest Point Construction, your boss says that he can estimate the total project time based on his personal experience.
What is the specific chemical function of the lipoic acid : Problem- For the pyruvate dehydrogenase complex, what is the specific chemical function of the lipoic acid cofactor
Implement a generic class set : Implement a generic class Set that maintains a set of items of generic type T using the class LinkedList in the Java API. Your Set class must provide the subsequent functionality:
Explain sensitivity of a spectrophotometer allows detection : Problem- The sensitivity of a spectrophotometer allows detection of 1 percent of one colored form of an indicator (for example HIn) in the presence of 99 percent of the other colored form (In-).
Write a test program that obtains from the user : Write a test program that obtains from the user the items to store in two sets A and B, and displays the union A u B, the inter- section A n B, and the dierence A \ B. The data type of the items is your choice. ( you can only store objects.)

Reviews

Write a Review

Computer Engineering Questions & Answers

  Prepare chens er model diagram with 10 entities with

question 1.create chens er model diagram with 10 entities with attributes and 10 relationships.question 2.convert

  1 consider the one time pad encryption scheme to encrypt a

1. consider the one time pad encryption scheme to encrypt a 1-bit message. replace the xor operation with another

  Analyze running time of algorithm

Analyze running time of algorithm

  List the two new or changed features in ipv6

List two new or changed features in IPv6. define how each one affects Internet Protocol including the affects to inter-networking issues. Be thorough in your discussion.

  Make a plan to deploy several visual basic.net

Your supervisor has asked you to develop a plan to deploy several Visual Basic.NET applications to users in your company. Discuss the important considerations in this effort and give a summary of the technical approach you would use to deploy thes..

  Write a program that takes a single phone digit

Write a program that takes a single phone digit. If the digit is a letter, the number corresponding to the letter is returned by reference and return 0 by value indicating it is a valid digit. Here are the letters associated with each digit.

  Write down a swing applet that displays

Write down a Swing applet that displays your name (Gary Vega) in blue the first time the user clicks a JButton4, and then displays your name larger and in gray second time the user clicks the JButton. Save program as JBlueGray.java

  Write down a program on visual basic format

Write down a program on visual basic format

  What are the roles of the management sponsors

What are the roles of the management sponsors

  Program with a function that returns a random integer

Program with a function that returns a random integer

  Compute the dollar amount of money in a piggy bank

Write down a detailed set of instructions, in English, to calculate the dollar amount of money in a piggy bank that contains h half-dollars, q quarters, n nickels, d dimes and p pennies.

  Breach of security

A company has the resource XYZ. If there exist a breach of security, company may face a fine of $100,000 and pay other $20,000 in order to clean up the breach.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd