What is the completely accelerated project duration

Assignment Help Operation Management
Reference no: EM13229353

A company has developed a project and is interested in accelerating the schedule if possible. Below network diagram and tables show all information needed.Partial crashing is available.

1905_What is the completely accelerated project duration.png

1. For the network, how many potential paths exist?

2. For present schedule, how long will project take?

3. What activity should be crashed first to accelerate the project by 1 day?

4. What activity should be crashed next to accelerate the project by another day?

5. What is the completely accelerated project duration after maximum crashing?

6. What is the total additional cost for reducing the duration by the maximum?

Reference no: EM13229353

Questions Cloud

What are the remedies available to bella under the fmla : Was Bella's leave covered under the Family Medical Leave Act? Outline the steps Bella would need to take to file a claim under the FMLA. What are the remedies available to Bella under the FMLA?
Describe what is called a homopolar generator : A plane circular disk of radius 0.25m rotates at a speed of 200 rad/s about an axis through the center of the disk perpendicular to the plane of the disk. There is a uniform magnetic flux B = 1 Tesla parallel to the axis of rotation.
What steps can ford motor take : What steps can the UAW take if there is no agreement? What steps can Ford Motor take if there is no agreement? Will the laws of the state of Michigan influence the collective bargaining process?
Discuss the liability of each party and the potential amount : As a result, Ralph sues to recover damages and names Kotaku, LP, Bob, Carol, Ted, Alice, and Nick in the lawsuit. Discuss the liability of each party and the potential amount Ralph might recover from each.
What is the completely accelerated project duration : What is the completely accelerated project duration after maximum crashing and what is the total additional cost for reducing the duration by the maximum?
Find the coordinates of the particle at a time t later : A charged particle starts from rest at the origin of coordinates in a region where there is a uniform electric field E parallel to the x-axis, and a uniform magnetic flux density B parallel to the z-axis. Show that the coordinates of the particle ..
Compare and contract unsecured credit and secured credit : Compare and contract unsecured credit and secured credit, and explain the key differences. Provide an example for each.
Which includes virtual employees : Introduce a new special form of insurance for current business operating on a global scale with a deverse work force, which includes virtual employees.
What is probability that customer will only be able internet : An internet access provider (IAP) owns two servers. Each server has a 50% chance of being "down" independently of the other. Fortunately, only one server is necessary to allow the IAP to provide service to its customers

Reviews

Write a Review

Operation Management Questions & Answers

  What is the optimal safety stock

Ordering larger quantity would increase safety stock. Ordering more frequently would reduce safety stock and increase the chance of stock outs.

  What are the pros and cons of an airline implementing

What are the pros and cons of an airline implementing a policy that heavier customers need to buy a second seat? Research an airline and provide their policy on heavier customers and seats. Do you agree or disagree with this policy?

  Estimate the total cost of ordering

A jewelry firm buys semiprecious stones to make bracelets and rings. The supplier charges $20 per stone, annual carrying costs are 50%, and the cost of processing orders is $40.

  Illustrate what is the probability that the project

Illustrate what is the probability that the project will be finished in less than 57 days. Illustrate what is the probability that the project will desire at least 50 days.

  What are the annual ordering costs

a) Calculate the EOQ for the workbooks. b) What are the annual holding costs for the workbooks? c) What are the annual ordering costs?

  How does the traditional approach to doing business equate

How does the traditional approach to doing business equate quality with higher cost?

  Why does corporate america have human resource planning

Why does corporate America have human resource planning?

  Elucidate enough money for a full-blown cross-functional

Elucidate however, there is not enough money for a full-blown, cross-functional enterprise application, also you will need to limit first step to a single functional area or constituency. Illustrate what will you choose, also why.

  Demand is normally distributed with a standard deviation

Chicago's Hard Rock Hotel distributes a mean of 1,000 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 100 towels per day

  Illustrate what are main objectives of work-center schedule

Illustrate what are the main objectives of work-center scheduling. Illustrate what are the differences among occupation shop, Group Technology cell and flow shop.

  What was its capacity utilization rate last month

Both production lines can produce all the different types of nozzles. The bronze machines needed for the bronze sprinklers require two operators and can produce up to 12,000 sprinklers.

  Estimate the upper and lower control limits

A machine at the Pacific Fruit Company fills boxes with raisins. The labeled weight of the boxes is 9 oz. The quality control department sampled five boxes at two hour time intervals to construct a control chart.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd